Sample Project Pile Foundation-compressed

Uploaded by

sinanicik
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 11

06/07/2022

Sequence of work

The working sequence for the construction of bored piles with


temporary casing comprises the following key elements
 Preparation Works
 Driving temporary casing
 Boring
 Cleaning of Base

Photo Album 


Reinforcement Cage Preparation and Installation
Bored Pile Concreting
BY EPHREM FELEKE

Con… Positioning Equipment


 One set of piling equipment to be used for piling will be positioned
near the pile location to be constructed
 Extracting Temporary Casing  All foundation excavation in which bored piles and deep
 Tolerance of Bored Pile foundation piles are to be constructed will be completed before
any drilling begins.
 Disposal of Excavated Materials
 The mast of the drilling rig will be checked for the verticality
 Bored Pile Recording
 Pile Testing

1
06/07/2022

Demarcation of pile location Installation of Temporary Casing

 Careful site survey and demarcation of pile location in accordance  Support the overburden soil above the underlain hard strata from
with approved for shop drawings. collapsing during drilling
 The centre of the pile will be fixed at site by driving a steel pin and a  guide the rig during the drilling process
red colour identification ribbon will be tied at top of the steel pin. The temporary casing shall be of stable construction to avoid any

 two reference offset points shall be drawn in orthogonal direction loss of shape or distortion during installation
with minimum 2m from the centre of the pile location for monitoring  The temporary casing will be installed by means of the service crane
of pre drilling holes. of the drilling rig
 After fixing two reference offset points and alignment of the rock  extracted back from the soil by an oscillation motion to reduce the
auger in the pile centre, pre-drilling of the bore hole shall
skin friction between casing and soil.
commence.

2
06/07/2022

3
06/07/2022

4
06/07/2022

Drilling fluid / Stabilization Unit


 The density viscosity and pH of the slurry will be monitored frequently
and adjusted when necessary in order to maintain the required quality
of the slurry.
 The operation of re-cycled through a de-sanding unit
 The Soil Stabilization raw materials shall be mixed with fresh water in a
digester (high speed / high shear mixer)
Test of Slurry
 Test will be done during the drilling to establish a consistent working
pattern.
 Prior to placing concrete in the bored pile, slurry samples will be taken
from the bottom and at intervals not exceeding 3 meters for the full
height of slurry

5
06/07/2022

Con…

 Once the drilling reached the required toe level, cleaning of the
bore hole shall be cleaned using a flat bottom cleaning bucket
 Cleaning of the bore hole shall continue until material coming out
from the bucket is purely water.

6
06/07/2022

7
06/07/2022

Sequence of the Bored Piling Construction Using Koden Test


Stabilization Liquid
 KODEN test is measurement of pile boreholes
 The KODEN measuring device is a system based on ultrasonic distance
measurement and is used to measure the shape and deviations of pile
boreholes and slurry trenches.

Purpose of koden test Con…

 To observe verticality and dimension of drill hole of bored pile or D-  Connect the 220V AC power supply and turn on the recorder.
Wall before cage installing and concreting.  Input related data of the bored hole.
 To investigate wall surface;  Turn on the system and lower down the sensor for testing.
 Necking Testing result shall be automatically printed on a special paper on

 Bulging site
General Test Procedure  The quality of excavated shaft for bored pile are accepted when
A crane is used to mobilize the winch to the centre of the verticality is within 1/100 of its length

excavation.
 Connect the winch and recorder through the 15-pin connecting
cable.

8
06/07/2022

9
06/07/2022

REINFORCEMENT CAGE PREPARATION AND


INSTALLATION
 After drilling, the borehole depth will be checked and
verified versus the depth given on daily piling sequence
and pile data
 A reference site datum level will be given to ensure the
correct positioning of the cage with respect to cut off
level
A reinforcement cage will be prepared by steel fixers as
specified in the drawing
 The reinforcement segments will be connected together
by lapping and fixed together using binding wires and
cage holders

10
06/07/2022

11