cash flow only mengesh
cash flow only mengesh
0 Construction of guard house size 3m*4m No. 1.00 145,750.00 145,750.00 145,750.00
1.7 3*4m2 ,Toilet and Shower Construction No. 2.00 145,750.00 291,500.00 291,500.00
1.9 Generator and guard house size (3*4m2) No. 1.00 145,750.00 145,750.00 145,750.00
1.1 Generator rent with fuel No. 1.00 864,000.00 864,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00 36,000.00
1.11 Asbuilt drawings and Site plan Ls 1.00 100,000.00 100,000.00 100,000.00
1.12 Provision and maintenance of Sign Boards No. 2.00 50,000.00 100,000.00 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67 4,166.67
Preparation and submission of Operation and
1.13 maintenance manual Ls 1.00 100,000.00 100,000.00 100,000.00
1.14 Allow for medical facilities Ls 1.00 168,000.00 168,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00 7,000.00
1.15 Running cost for water supply Months 24.00 30,000.00 720,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00 30,000.00
1.16 Allow for security service Ls 1.00 576,000.00 576,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00 24,000.00
1.17 Temporary access and haul roads Ls 1.00 500,000.00 500,000.00 500,000.00
Total
Concrete work
Sub total
U/S Cut-Off
Excavation
Concrete work
Sub total
U/S APRONE
Excavation
Concrete work
Sub total
HUNDUMA NECHO WATER WORKS CONTRACTOR
CASH FLOW DISTRIBUTION
Project:- Gebuyi Kumi Mengesh(GKM) Medium Scale irrigation Weir Project
Employer:Gambella Peoples Regional State Irrigation and Lowland Bureau
2025 2026
Item No. Work Description Unit Qty Unit Rate Total cost/birr/ January February March Aprill May June July August September October November December January February March Aprill May June July August September October November December
D/S Cut-Off
Excavation
Concrete work
Sub total
D/S APRONE
Excavation
Concrete work
Sub total
Masonry Work
Concrete work
Concrete work
Sub total
HUNDUMA NECHO WATER WORKS CONTRACTOR
CASH FLOW DISTRIBUTION
Project:- Gebuyi Kumi Mengesh(GKM) Medium Scale irrigation Weir Project
Employer:Gambella Peoples Regional State Irrigation and Lowland Bureau
2025 2026
Item No. Work Description Unit Qty Unit Rate Total cost/birr/ January February March Aprill May June July August September October November December January February March Aprill May June July August September October November December
Masonry Work
2.7.6 Lean concrete, c-15 (for bedding) m3 7.94 12,034.01 95,550.06 95,550.06
Sub total
Masonry Work
2.8.5 Lean concrete, c-15 (for bedding) m3 9.52 12,034.01 114,563.80 114,563.80
Sub total
2.9 GATES
EARTH WORKS
Clear the area of earth works and road works from
3.1.1 bush,trees and shrubs m2 11,620.00 35.48 412,219.50 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21 24,248.21
Rectangular canal excavation of common soil
3.1.2 material m3 9,776.56 354.75 3,468,234.66 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80 204,013.80
3.1.3 Rectangular canal excavation of soft rock material m3 488.83 30.00 14,664.90 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64 862.64
3.1.4 Rectangular canal excavation of hard rock material m3 488.83 40.00 19,553.20 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19 1,150.19
3.1.5 Backfill and compaction from excavated material m3 1,760.27 443.44 780,569.73 22,957.93 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 45,915.87 22,957.93
Masonry Works
Basaltic or equivalent Stone Masonry work in cement
3.1.6 stand mortar 1:3 mix ratio m3 6,329.81 6,650.94 42,099,157.31 1,238,210.51 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 2,476,421.02 1,238,210.51
3.1.7 Plastering work by 1:3 ratio mortar m2 18,147.34 450.34 8,172,473.10 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71 480,733.71
Total
EARTH WORKS
Clear the area of earth works and road works from
3.2.1 bush,trees and shrubs m2 8,100.00 35.48 287,347.50 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79 16,902.79
Rectangular canal excavation of common soil
3.2.2 material m3 4,224.03 354.75 1,498,474.64 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57 88,145.57
3.2.3 Rectangular canal excavation of soft rock material m3 211.20 30.00 6,336.00 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71 372.71
3.2.4 Rectangular canal excavation of hard rock material m3 211.20 40.00 8,448.00 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94 496.94
3.2.5 Backfill and compaction from excavated material m3 1,164.03 443.44 516,174.55 15,181.60 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 30,363.21 15,181.60
3.2.7 Plastering work by 1:3 ratio mortar m2 10,384.08 450.34 4,676,366.59 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39 275,080.39
Total
HUNDUMA NECHO WATER WORKS CONTRACTOR
CASH FLOW DISTRIBUTION
Project:- Gebuyi Kumi Mengesh(GKM) Medium Scale irrigation Weir Project
Employer:Gambella Peoples Regional State Irrigation and Lowland Bureau
2025 2026
Item No. Work Description Unit Qty Unit Rate Total cost/birr/ January February March Aprill May June July August September October November December January February March Aprill May June July August September October November December
3.3.1.2 Channel excavation in all type of except rocks m3 10.80 354.75 3,831.30 1,915.65 1,915.65
3.3.1.3 Backfill around pipe culvert m3 8.00 443.44 3,547.50 1,773.75 1,773.75
3.3.1.4 Reinforced concrete C-20 with formwork m3 1.60 13,435.32 21,496.52 10,748.26 10,748.26
Pipe Culverts
3.3.1.5 Supply and lay precast RC pipe culverts ,dia.900mm No. 7.00 30,000.00 210,000.00 105,000.00 105,000.00
Masonry Work
Basaltic or equivalent Stone Masonry work in cement
3.3.1.6 stand mortar 1:3 mix ratio m3 17.12 6,650.94 113,864.01 56,932.01 56,932.01
3.3.1.7 Plastering work by 1:3 ratio mortar m2 6.00 450.34 2,702.04 1,351.02 1,351.02
Total
Crossing Structures (foot path , Cattle crossing
,supperpassage)
Basaltic or equivalent Stone Masonry work in cement
3.3.1.8 stand mortar 1:3 mix ratio m3 27.00 6,650.94 179,575.26 89,787.63 89,787.63
3.3.1.9 Reinforced concrete C-20 with formwork m3 14.40 13,435.32 193,468.66 96,734.33 96,734.33
Furnish and install Reinforcement bars having
3.3.1.10 dia.12mm Kg 2,352.84 217.60 511,976.42 255,988.21 255,988.21
Total
3.4.2 Channel excavation of common soil m3 720.00 354.75 255,420.00 127,710.00 127,710.00
Total
GRAND TOTAL 7,580,860.57 2,363,757.96 5,084,110.04 5,122,249.57 5,122,249.57 5,122,249.57 101,166.67 101,166.67 5,122,249.57 17,432,245.55 5,122,249.57 5,122,249.57 5,950,860.58 5,950,860.58 5,122,249.57 5,122,249.57 5,122,249.57 5,122,249.57 101,166.67 101,166.67 5,122,249.57 15,308,857.54 2,859,658.28 439,306.20
COMMULATIVE 7,580,860.57 9,944,618.53 15,028,728.56 20,150,978.13 25,273,227.71 30,395,477.28 30,496,643.95 30,597,810.61 35,720,060.19 53,152,305.73 58,274,555.31 63,396,804.88 69,347,665.46 75,298,526.03 80,420,775.61 85,543,025.18 90,665,274.75 95,787,524.33 95,888,690.99 95,989,857.66 101,112,107.23 116,420,964.77 119,280,623.06 119,719,929.26