0% found this document useful (0 votes)
2 views

Normalization Copy

Uploaded by

rambongajorella
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
2 views

Normalization Copy

Uploaded by

rambongajorella
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 28

1.

RAW DATA
Economic Constructability
Design Project Cost Schedule Labor Cost
Impounding + Earth 1 1,722,210.29 720 2000000
Impounding + Concrete 2 7,150,898.09 770 2500000
Impounding + Pipe 3 5,809,702.18 740 2000000
Diversion + Earth 4 1,322,210.29 720 2000000
Diversion + Concrete 5 6,750,898.09 770 2500000
Diversioin + Pipe 6 5,409,702.18 740 2000000
Fuel + Earth 7 1,122,210.29 180 250000
Fuel + Concrete 8 6,550,898.09 220 400000
Fuel + Pipe 9 5,209,702.18 200 200000
Solar + Earth 10 1,422,210.29 180 250000
Solar + Concrete 11 6,850,898.09 220 400000
Solar + Pipe 12 5,509,702.18 200 200000

Costs
Impounding
Diversion
Fuel Pump
Solar Pump
Pipe
Concrete
Excavation
2. Normalized data
Economic Constructability
Design Project Cost Schedule Labor Cost
1 9.10 1.76 2.96
2 1.00 1.00 1.00
3 3.00 1.46 2.96
4 9.70 1.76 2.96
5 1.60 1.00 1.00
6 3.60 1.46 2.96
7 10.00 10.00 9.80
8 1.90 9.39 9.22
9 3.90 9.69 10.00
10 9.55 10.00 9.80
11 1.45 9.39 9.22
12 3.45 9.69 10.00

Normalization for PC1


((max-actual)/(max-min))*(9)+1
Design 1 (PC1)
Nomalization
((900000-900000)/(900000-700000))*(9)+1 =

Table 3
PC Weight (%) D1 D2
Project Cost 1 0.2 9.10 1.00
Schedule 2 0.05 1.76 1.00
Labor Cost 3 0.15 2.96 1.00
Lifespan 4 0.2 1.00 1.00
Maintenance Cost 5 0.15 7.41 8.00
Risk Assessment 6 0.15 2.69 2.13
Safety 7 0.05 1.00 1.00
Uncertainty 8 0.05 1.00 1.00
Weighted
Sum 4.16642016851692 2.21849225754395

Table 4
PC Weight (%) D1 D2
Project Cost 1 0.15 9.10 1.00
Schedule 2 0.05 1.76 1.00
Labor Cost 3 0.1 2.96 1.00
Lifespan 4 0.2 1.00 1.00
Maintenance Cost 5 0.2 7.41 8.00
Risk Assessment 6 0.2 2.69 2.13
Safety 7 0.05 1.00 1.00
Uncertainty 8 0.05 1.00 1.00
Weighted
Sum 4.07 2.62

Table 5
PC Weight (%) D1 D2
Project Cost 1 0.2 9.10 1.00
Schedule 2 0.05 1.76 1.00
Labor Cost 3 0.05 2.96 1.00
Lifespan 4 0.15 1.00 1.00
Maintenance Cost 5 0.25 7.41 8.00
Risk Assessment 6 0.2 2.69 2.13
Safety 7 0.05 1.00 1.00
Uncertainty 8 0.05 1.00 1.00
Weighted
Sum 4.70 2.97
Sustainability Uncertainty Safety Uncertainty
LifespanMaintenance and(or) Operating
(Calamities)
Cost (to residents) (existing site conditions??) will
50 4888411.5456 34 1.5 80
50 4000000 36 1.5 80
50 1000000 21 1.5 80
50 4888411.5456 37 1.5 80
50 4000000 40 1.5 80
50 1000000 21 1.5 80
20 14488411.5456 22 1.25 30
20 9600000 19 1.25 30
20 9600000 8 1.25 30
25 4888411.5456 26 1.1 40
25 4000000 23 1.1 40
25 1000000 12 1.1 40

Dimensions
400000 per hectare pipe/canal line 1383 m
300000 per hectare canal area (concrete onl 0.232 m²
1000000 per pc earth excavation 0.384 m²
1300000 per pc
3043.89166666667 lm (pipe, installation, labor?)
16919.39 per cu. M
230.12 per cu. M

Sustainability Risk Assessment Safety Uncertainty


Lifespan Maintenance Cost Risk Assessment Safety Uncertainty
1.00 7.41 2.69 1.00 1.00
1.00 8.00 2.13 1.00 1.00
1.00 10.00 6.34 1.00 1.00
1.00 7.41 1.84 1.00 1.00
1.00 8.00 1.00 1.00 1.00
1.00 10.00 6.34 1.00 1.00
10.00 1.00 6.06 6.63 10.00
10.00 4.26 6.91 6.63 10.00
10.00 4.26 10.00 6.63 10.00
8.50 7.41 4.94 10.00 8.20
8.50 8.00 5.78 10.00 8.20
8.50 10.00 8.88 10.00 8.20
D3 D4 D5 D6 D7
3.00 9.70 1.60 3.60 10.00
1.46 1.76 1.00 1.46 10.00
2.96 2.96 1.00 2.96 9.80
1.00 1.00 1.00 1.00 10.00
10.00 7.41 8.00 10.00 1.00
6.34 1.84 1.00 6.34 6.06
1.00 1.00 1.00 1.00 6.63
1.00 1.00 1.00 1.00 10.00

3.86836624687083 4.15928664280516 2.16917123183218 3.98779522115906 7.86127717391304

D3 D4 D5 D6 D7
3.00 9.70 1.60 3.60 10.00
1.46 1.76 1.00 1.46 10.00
2.96 2.96 1.00 2.96 9.80
1.00 1.00 1.00 1.00 10.00
10.00 7.41 8.00 10.00 1.00
6.34 1.84 1.00 6.34 6.06
1.00 1.00 1.00 1.00 6.63
1.00 1.00 1.00 1.00 10.00

4.39 3.99 2.49 4.48 7.22

D3 D4 D5 D6 D7
3.00 9.70 1.60 3.60 10.00
1.46 1.76 1.00 1.46 10.00
2.96 2.96 1.00 2.96 9.80
1.00 1.00 1.00 1.00 10.00
10.00 7.41 8.00 10.00 1.00
6.34 1.84 1.00 6.34 6.06
1.00 1.00 1.00 1.00 6.63
1.00 1.00 1.00 1.00 10.00

4.84 4.65 2.87 4.96 6.78


Flooding Landslide or Erosion Earthquake
te conditions??) will Likelihood Severity Score Likelihood Severity Score Likelihood Severity Score
3 3 9 4 4 16 3 3 9
3 4 12 4 3 12 3 4 12
2 3 6 3 3 9 3 2 6
4 3 12 4 4 16 3 3 9
4 4 16 4 3 12 3 4 12
3 3 9 3 2 6 3 2 6
2 2 4 4 3 12 3 2 6
1 1 1 3 3 9 3 3 9
1 1 1 3 2 6 1 1 1
2 2 4 4 3 12 3 2 6
1 1 1 3 3 9 3 3 9
1 1 1 3 2 6 1 1 1

138029.36 liters per yr


31.60819 liters per hr
5 liters per hr
8 hrs operational
60 price diesel per liter
D8 D9 D10 D11 D12
1.90 3.90 9.55 1.45 3.45
9.39 9.69 10.00 9.39 9.69
9.22 10.00 9.80 9.22 10.00
10.00 10.00 8.50 8.50 8.50
4.26 4.26 7.41 8.00 10.00
6.91 10.00 4.94 5.78 8.88
6.63 6.63 10.00 10.00 10.00
10.00 10.00 8.20 8.20 8.20

6.737692 7.734844 8.34253 6.818602 8.116012

D8 D9 D10 D11 D12


1.90 3.90 9.55 1.45 3.45
9.39 9.69 10.00 9.39 9.69
9.22 10.00 9.80 9.22 10.00
10.00 10.00 8.50 8.50 8.50
4.26 4.26 7.41 8.00 10.00
6.91 10.00 4.94 5.78 8.88
6.63 6.63 10.00 10.00 10.00
10.00 10.00 8.20 8.20 8.20

6.74 7.75 7.99 6.97 8.39

D8 D9 D10 D11 D12


1.90 3.90 9.55 1.45 3.45
9.39 9.69 10.00 9.39 9.69
9.22 10.00 9.80 9.22 10.00
10.00 10.00 8.50 8.50 8.50
4.26 4.26 7.41 8.00 10.00
6.91 10.00 4.94 5.78 8.88
6.63 6.63 10.00 10.00 10.00
10.00 10.00 8.20 8.20 8.20

6.09 7.16 7.92 6.56 8.13


Typhoon
Likelihood Severity Score table 1
0 34 values based on computatio
0 36
0 21
0 37
0 40
0 21
0 22
0 19
0 8
4 1 4 26
4 1 4 23
4 1 4 12

table 2
use the formula for normali
Table 3
the weight value are subjec
the D1, D2, D3 you just copy
the weighted sum there is a

table 4
change the values of the we
same value for D1, D2 D3
weighted sum there is an em

change the values of the we


tablevalue
same 5 for D1, D2 D3
weighted sum there is an em
values based on computation for each design per constraints

150 mm diameter hdpe

160 mm 6641 per 5 m per piece 733 pesos per cu.m 1376 per lm of pipe installation
1383 1328.2 per lm 265.64 total volume on excavation 1328.2
1836901 194714.1 1827603

use the formula for normalization for each design per constraints
the weight value are subjective
the D1, D2, D3 you just copy the result from table 2 for each design per tradeoff
the weighted sum there is an embedded formula

change the values of the weights still subjective


same value for D1, D2 D3
weighted sum there is an embedded formula

change the values of the weights still subjective


same value for D1, D2 D3
weighted sum there is an embedded formula
per lm of pipe installation
imrf, 2w, spiral col, t beam, combined fooing Trade-off
smrf, oneway, tied, rec col, isolated footings Identification Design
IMRF, One-way Slab,
T-beams, Spiral
1
Columns, Combined
Footings
IMRF, Two-way Slab,
T-beams, Spiral
2
Columns, Combined
Footings

SMRF, Two-way Slab,


Rectangular Girders,
3
Tied Columns, Isolated
Footings

Trade-off Economic
Design Project Cost
1 4.00
2 1.00
3 10.00

Project Constraint
Project Cost 1
Schedule 2
Labor Cost 3
Lifespan 4
Maintenance Cost 5
Story Drift 6
Weighted Sum

Project Constraint
Project Cost 1
Schedule 2
Labor Cost 3
Lifespan 4
Maintenance Cost 5
Story Drift 6
Weighted Sum

Project Constraint
Project Cost 1
Schedule 2
Labor Cost 3
Lifespan 4
Maintenance Cost 5
Story Drift 6
Weighted Sum
Economic Constructability Sustainability
Project Cost Schedule Labor Cost Lifespan Maintenance Cost

114,240,000.00 803 34,272,000.00 50 1,142,400.00

115,920,000.00 810 34,776,000.00 50 1,159,200.00

110,880,000.00 730 33,264,000.00 50 1,108,800.00

Constructability Sustainability Uncertainty


Schedule Labor Cost Lifespan Maintenance Cost Story Drift (mm)
1.79 4.00 1.00 4.00 1.00
1.00 1.00 1.00 1.00 1.00
10.00 10.00 1.00 10.00 10.00

Weight (%) D1 D2 D3
0.3 4.00 1.00 10.00
0.1 1.79 1.00 10.00
0.15 4.00 1.00 10.00
0.1 1.00 1.00 1.00
0.15 4.00 1.00 10.00
0.2 1.00 1.00 10.00
1 2.88 1.00 9.10

Weight (%) D1 D2 D3
0.25 4.00 1.00 10.00
0.15 1.79 1.00 10.00
0.15 4.00 1.00 10.00
0.1 1.00 1.00 1.00
0.15 4.00 1.00 10.00
0.2 1.00 1.00 10.00
1 2.77 1.00 9.10

Weight (%) D1 D2 D3
0.4 4.00 1.00 10.00
0.1 1.79 1.00 10.00
0.15 4.00 1.00 10.00
0.15 1.00 1.00 1.00
0.1 4.00 1.00 10.00
0.1 1.00 1.00 10.00
1 3.03 1.00 8.65
Uncertainty
Story Drift (mm)

4.2

4.2

1.3
1. RAW DATA
Economic Constructability
Design Material Cost Schedule Labor Cost
Impounding + Eart 1 1,720,000.00 720 194714.12
Diversion + Earth 2 1,290,000.00 710 194714.12
Impounding + Pipe 3 3,556,900.60 720
Diversion + pipe 4 3,126,900.60 710
fuel + pipe 5 1,929,400.60 360 1827603.2
solar + pipe 6 1,929,400.60 360 1827603.2

2. Normalized data
Economic Constructability
Design Material Cost Schedule Labor Cost
1 8.29 1.00 10.00
2 10.00 1.25 10.00
3 1.00 1.00 11.07
4 2.71 1.25 11.07
5 7.46 10.00 1.00
6 7.46 10.00 1.00

Normalization for PC1


((max-actual)/(max-min))*(9)+1

Design 1 (PC1)
Nomalization
((900000-900000)/(900000-700000))*(9)+1 =

Table 3
PC Weight (%) D1 D2
1 0.2 8.29 10.00
2 0.15 1.00 1.25
3 0.15 10.00 10.00
4 0.1 1.00 1.00
5 0.13 #DIV/0! #DIV/0!
6 0.12 #DIV/0! #DIV/0!
7 0.05 #DIV/0! #DIV/0!
8 0.1 #DIV/0! #DIV/0!
Weighted
Sum #DIV/0! #DIV/0!

Table 4
PC Weight (%) D1 D2
1 0.2 8.29 10.00
2 0.15 1.00 1.25
3 0.15 10.00 10.00
4 0.1 1.00 1.00
5 0.13 #DIV/0! #DIV/0!
6 0.12 #DIV/0! #DIV/0!
7 0.05 #DIV/0! #DIV/0!
8 0.1 #DIV/0! #DIV/0!
Weighted
Sum #DIV/0! #DIV/0!

Table 5
PC Weight (%) D1 D2
1 0.2 8.29 10.00
2 0.15 1.00 1.25
3 0.15 10.00 10.00
4 0.1 1.00 1.00
5 0.13 #DIV/0! #DIV/0!
6 0.12 #DIV/0! #DIV/0!
7 0.05 #DIV/0! #DIV/0!
8 0.1 #DIV/0! #DIV/0!
Weighted
Sum #DIV/0! #DIV/0!
Sustainability Risk Assessment Safety Uncertainty
Lifespan Maintenance Cost
30
30
30
30
15
22.5

92.5

Sustainability Risk Assessment Safety Uncertainty


Lifespan Maintenance Cost
1.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
1.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
10.00 #DIV/0! #DIV/0! #DIV/0! #DIV/0!
5.50 #DIV/0! #DIV/0! #DIV/0! #DIV/0!

D3 D4 D5 D6
1.00 2.71 7.46 7.46
1.00 1.25 10.00 10.00
11.07 11.07 1.00 1.00
1.00 1.00 10.00 5.50
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!

#DIV/0! #DIV/0! #DIV/0! #DIV/0!

D3 D4 D5 D6
1.00 2.71 7.46 7.46
1.00 1.25 10.00 10.00
11.07 11.07 1.00 1.00
1.00 1.00 10.00 5.50
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!

#DIV/0! #DIV/0! #DIV/0! #DIV/0!

D3 D4 D5 D6
1.00 2.71 7.46 7.46
1.00 1.25 10.00 10.00
11.07 11.07 1.00 1.00
1.00 1.00 10.00 5.50
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!
#DIV/0! #DIV/0! #DIV/0! #DIV/0!

#DIV/0! #DIV/0! #DIV/0! #DIV/0!


table 1
values based on computation for each design per constraints

150 mm diameter hdpe

160 mm 6641 per 5 m per piece 733 pesos per cu.m


1383 1328.2 per lm 265.64 total volume on excavation
1836901 194714.1

table 2
use the formula for normalization for each design per constraints

Table 3
the weight value are subjective
the D1, D2, D3 you just copy the result from table 2 for each design per tradeoff
the weighted sum there is an embedded formula
table 4
change the values of the weights still subjective
same value for D1, D2 D3
weighted sum there is an embedded formula

change the values of the weights still subjective


tablevalue
same 5 for D1, D2 D3
weighted sum there is an embedded formula
1376 per lm of pipe installation
1328.2
1827603
1. RAW DATA
PC3 (Risk - # of PC4 (Environmental
Design PC1 (Cost in Pesos) PC2 (Duration in mo.) casualties) Impact/Friendliness - %
Purity of Air )
1 900,000.00 7 3 95
2 800,000.00 8 2 98
3 700,000.00 9 4 93

2. Normalized data
PC3 (Risk - # of PC4 (Environmental
Design PC1 (Cost in Pesos) PC2 (Duration in mo.) casualties) Impact/Friendliness -
Purity of Air)
1 1.00 10 5.5 6.4
2 5.50 5.5 10 1
3 10.00 1 1 10

Normalization for PC1


((max-actual)/(max-min))*(9)+1

Design 1 (PC1)
Nomalization
((900000-900000)/(900000-700000))*(9)+1 =

Table 3
PC Weight (%) D1 D2 D3
1 0.4 1.00 5.5 10
2 0.3 10 5.5 1
3 0.2 5.5 10 1
4 0.1 6.4 1 10
Weighted
Sum 5.14 5.95 5.5

Table 4
PC Weight (%) D1 D2 D3
1 0.38 1.00 5.5 10
2 0.28 10 5.5 1
3 0.22 5.5 10 1
4 0.12 6.4 1 10
Weighted
Sum 5.158 5.95 5.5

Table 5
PC Weight (%) D1 D2 D3
1 0.35 1.00 5.5 10
2 0.15 10 5.5 1
3 0.38 5.5 10 1
4 0.12 6.4 1 10
Weighted
Sum 4.708 6.67 5.23
table 1

values based on computation for each design per constraints

table 2

use the formula for normalization for each design per constraints

Table 3
the weight value are subjective
the D1, D2, D3 you just copy the result from table 2 for each design per tradeoff
the weighted sum there is an embedded formula

table 4
change the values of the weights still subjective
same value for D1, D2 D3
weighted sum there is an embedded formula

change the values of the weights still subjective


tablevalue
same 5 for D1, D2 D3
weighted sum there is an embedded formula
gn per tradeoff

You might also like