ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
1 BTC BASELINE WORK PROGRAM REV.05 313 days Fri 09-08-24 Tue 17-06-25 1% BTC BASELINE WORK PROGRAM REV.05
2 MILESTONE & PROJECT COMPLETION DATES 235 days Fri 25-10-24 Tue 17-06-25 0%
3 MILESTONE 1 Roof Topping Up 0 days Tue 04-02-25 Tue 04-02-25 66 0% 04-02
4 MILESTONE 2 Water Tightness 0 days Sat 12-04-25 Sat 12-04-25 238 0% 12-04
6 MILESTONE 4 Power Energization 0 days Mon 12-05-25 Mon 12-05-25 264 0% MILESTONE 4 Power Energization 12-05
7 CPC / CCC Issuance 0 days Tue 17-06-25 Tue 17-06-25 669,668 0% CPC / CCC Issuance 17-06
10 Re-inspect tower crane & Passenger hoist 7 days Sun 08-09-24 Sat 14-09-24 9 0% Re-inspect tower crane & Passenger hoist
11 Structural Work 143 days Fri 30-08-24 Tue 04-02-25 3% Structural Work
12 Dismantle of Formwork 7 days Sun 15-09-24 Sat 21-09-24 9FF-2 days 80% Dismantle of Formwork
13 Demolisioin Work 7 days Sun 15-09-24 Sat 21-09-24 9FF-2 days 50% Demolisioin Work
16 Lift Shaft 21 & 22 10 days Wed 25-09-24 Fri 04-10-24 15SS+3 days 0% Lift Shaft 21 & 22
20 Lift Shaft Level 23 5 days Mon 07-10-24 Fri 11-10-24 16,19SS+5 days 0% Lift Shaft Level 23
24 Lift Shaft Level 24 5 days Thu 17-10-24 Mon 21-10-24 22SS+5 days,20 0% Lift Shaft Level 24
28 Lift Shaft Level 25 5 days Sun 27-10-24 Thu 31-10-24 24,26SS+5 days 0% Lift Shaft Level 25
32 Lift Shaft Level 26 5 days Wed 06-11-24 Sun 10-11-24 28,30SS+5 days 0% Lift Shaft Level 26
64 Lift Motor Room 5 days Sat 25-01-25 Wed 29-01-25 62SS+5 days,60 0% Lift Motor Room
Page 1
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
67 Zone B 5 days Mon 20-01-25 Fri 24-01-25 63 0% Zone B
68 MILESTONE 1 COMPLETED 0 days Tue 04-02-25 Tue 04-02-25 67,66 0% MILESTONE 1 COMPLETED 04-02
79 Column/Drop/Ceiling Panel Skim 5 days Mon 30-09-24 Fri 04-10-24 78SS+4 days 0% Column/Drop/Ceiling Panel Skim
81 Painting work 5 days Thu 03-10-24 Mon 07-10-24 80SS+3 days 0% Painting work
85 Floor & Wall Tiles 5 days Mon 14-10-24 Fri 18-10-24 77,84SS+4 days 0% Floor & Wall Tiles
88 Door installation 2 days Mon 21-10-24 Tue 22-10-24 87SS 0% Door installation
89 Vanity Counter Top 2 days Sun 22-09-24 Mon 23-09-24 72FF 0% Vanity Counter Top
91 Sanitary Fittings & Wares 3 days Mon 21-10-24 Wed 23-10-24 88SS 0% Sanitary Fittings & Wares
100 Column/Drop/Ceiling Panel Skim 4 days Thu 26-09-24 Sun 29-09-24 99SS+4 days 0% Column/Drop/Ceiling Panel Skim
102 Painting work 4 days Sun 29-09-24 Wed 02-10-24 101SS+3 days 0% Painting work
105 Plaster Ceiling 4 days Sat 05-10-24 Tue 08-10-24 104 0% Plaster Ceiling
106 Floor & Wall Tiles 2 days Wed 09-10-24 Thu 10-10-24 97,105SS+4 days 0% Floor & Wall Tiles
107 Floor Finishes 3 days Fri 11-10-24 Sun 13-10-24 106 0% Floor Finishes
108 Door installation 1 day Mon 14-10-24 Mon 14-10-24 107 0% Door installation
109 Vanity Counter Top 1 day Thu 19-09-24 Thu 19-09-24 93FF 0% Vanity Counter Top
111 Sanitary Fittings & Wares 1 day Mon 14-10-24 Mon 14-10-24 108SS 0% Sanitary Fittings & Wares
Page 2
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
112 MILESTONE 3 COMPLETED 0 days Fri 25-10-24 Fri 25-10-24 87 0% MILESTONE 3 COMPLETED 25-10
116 Ponding Test 4 days Fri 11-10-24 Mon 14-10-24 115 0% Ponding Test
117 Façade work 2 days Tue 15-10-24 Wed 16-10-24 116 0% Façade work
118 Screeding 6 days Tue 01-10-24 Sun 06-10-24 114SS+7 days 0% Screeding
119 Column/Drop/Ceiling Panel Skim 7 days Mon 07-10-24 Sun 13-10-24 118 0% Column/Drop/Ceiling Panel Skim
121 Painting work 7 days Thu 10-10-24 Wed 16-10-24 120SS+3 days 0% Painting work
122 Plaster Ceiling 7 days Sun 20-10-24 Sat 26-10-24 121FS+3 days 0% Plaster Ceiling
123 Floor & Wall Tiles 7 days Thu 17-10-24 Wed 23-10-24 121 0% Floor & Wall Tiles
127 Ponding Test 4 days Fri 25-10-24 Mon 28-10-24 126 0% Ponding Test
128 Façade work 2 days Tue 29-10-24 Wed 30-10-24 127 0% Façade work
129 Screeding 6 days Tue 15-10-24 Sun 20-10-24 125SS+7 days 0% Screeding
130 Column/Drop/Ceiling Panel Skim 7 days Mon 21-10-24 Sun 27-10-24 129 0% Column/Drop/Ceiling Panel Skim
132 Painting work 7 days Thu 24-10-24 Wed 30-10-24 131SS+3 days 0% Painting work
133 Plaster Ceiling 7 days Sun 03-11-24 Sat 09-11-24 132FS+3 days 0% Plaster Ceiling
134 Floor & Wall Tiles 7 days Thu 31-10-24 Wed 06-11-24 132 0% Floor & Wall Tiles
237 Ponding Test 4 days Mon 07-04-25 Thu 10-04-25 226 0% Ponding Test
238 Façade work 2 days Fri 11-04-25 Sat 12-04-25 237 0% Façade work
239 Ponding Test 2 days Tue 15-04-25 Wed 16-04-25 236 0% Ponding Test
240 Screeding 6 days Mon 07-04-25 Sat 12-04-25 235SS+7 days 0% Screeding
241 Column/Drop/Ceiling Panel Skim 7 days Sun 13-04-25 Sat 19-04-25 240 0% Column/Drop/Ceiling Panel Skim
243 Painting work 7 days Wed 16-04-25 Tue 22-04-25 242SS+3 days 0% Painting work
244 Plaster Ceiling 7 days Sat 26-04-25 Fri 02-05-25 243FS+3 days 0% Plaster Ceiling
245 Floor & Wall Tiles 7 days Wed 23-04-25 Tue 29-04-25 243 0% Floor & Wall Tiles
246 MILESTONE 2 COMPLETED 0 days Sat 12-04-25 Sat 12-04-25 238 0% MILESTONE 2 COMPLETED 12-04
Page 3
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
247 Other Finishes 60 days Tue 04-03-25 Fri 02-05-25 0%
248 Swimming Pool 45 days Wed 19-03-25 Fri 02-05-25 244FF 0% Swimming Pool
249 Door & Window installation 60 days Tue 04-03-25 Fri 02-05-25 248FF 0% Door & Window installation
250 Glass frame & glass installation 60 days Tue 04-03-25 Fri 02-05-25 249SS 0% Glass frame & glass installation
251 Sanitary Fittings & Wares 60 days Tue 04-03-25 Fri 02-05-25 249SS 0% Sanitary Fittings & Wares
252 Toilet Cubicle 30 days Tue 04-03-25 Wed 02-04-25 249SS 0% Toilet Cubicle
253 Glazing Work 60 days Tue 04-03-25 Fri 02-05-25 249SS 0% Glazing Work
254 Vanity Counter Top 45 days Wed 19-03-25 Fri 02-05-25 249SS+15 days 0% Vanity Counter Top
256 Staircase Railing 30 days Thu 03-04-25 Fri 02-05-25 250FS-30 days 0% Staircase Railing
257 Signanage Work 30 days Wed 19-03-25 Thu 17-04-25 249SS+15 days 0% Signanage Work
258 Floor Finishes 45 days Wed 19-03-25 Fri 02-05-25 249SS+15 days 0% Floor Finishes
262 Local Authority Approval 32 days Thu 13-03-25 Sun 13-04-25 261 0% Local Authority Approval
264 Testing & Commisioning 20 days Wed 23-04-25 Mon 12-05-25 243,263 0% Testing & Commisioning
265 MILESTONE 4 COMPLETED 0 days Mon 12-05-25 Mon 12-05-25 264 0% MILESTONE 4 COMPLETED 12-05
275 Zone B 3 days Wed 09-10-24 Fri 11-10-24 271FS+7 days 0% Zone B
305 Zone B 3 days Fri 17-01-25 Sun 19-01-25 302FS+7 days 0% Zone B
306 2nd Fix (Cable Tray & Trunking) 210 days Tue 08-10-24 Mon 05-05-25 0%
307 L15 7 days Tue 08-10-24 Mon 14-10-24 114 0% L15
Page 4
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
310 L18 7 days Tue 29-10-24 Mon 04-11-24 309 0% L18
326 L13 & L14 7 days Tue 01-04-25 Mon 07-04-25 325 0% L13 & L14
331 3rd Fix (Fitting Installation) 204 days Mon 21-10-24 Mon 12-05-25 0%
332 L15 3 days Mon 21-10-24 Wed 23-10-24 121FS+4 days 0% L15
333 L16 3 days Mon 28-10-24 Wed 30-10-24 332FS+4 days 0% L16
334 L17 3 days Mon 04-11-24 Wed 06-11-24 333FS+4 days 0% L17
335 L18 3 days Mon 11-11-24 Wed 13-11-24 334FS+4 days 0% L18
336 L19 3 days Mon 18-11-24 Wed 20-11-24 335FS+4 days 0% L19
337 L20 3 days Mon 25-11-24 Wed 27-11-24 336FS+4 days 0% L20
338 L21 3 days Sat 14-12-24 Mon 16-12-24 337FS+4 days,154 0% L21
339 L22 3 days Sat 21-12-24 Mon 23-12-24 338FS+4 days 0% L22
340 L23 3 days Sat 28-12-24 Mon 30-12-24 339FS+4 days 0% L23
341 L24 3 days Sat 04-01-25 Mon 06-01-25 340FS+4 days 0% L24
342 L25 3 days Sat 11-01-25 Mon 13-01-25 341FS+4 days 0% L25
343 L26 3 days Sat 18-01-25 Mon 20-01-25 342FS+4 days 0% L26
344 L27 3 days Sat 22-02-25 Mon 24-02-25 343FS+4 days,319,187 0% L27
345 L28 3 days Sat 01-03-25 Mon 03-03-25 344FS+4 days 0% L28
346 L29 3 days Sat 08-03-25 Mon 10-03-25 345FS+4 days 0% L29
347 L30 3 days Sat 15-03-25 Mon 17-03-25 346FS+4 days 0% L30
348 L31 3 days Sat 22-03-25 Mon 24-03-25 347FS+4 days 0% L31
349 L32 3 days Sat 29-03-25 Mon 31-03-25 348FS+4 days 0% L32
350 L33 3 days Sat 05-04-25 Mon 07-04-25 349FS+4 days,325 0% L33
351 L13 & L14 3 days Sat 12-04-25 Mon 14-04-25 350FS+4 days 0% L13 & L14
352 L11 3 days Sat 19-04-25 Mon 21-04-25 351FS+4 days 0% L11
353 L12 3 days Sat 26-04-25 Mon 28-04-25 352FS+4 days 0% L12
354 L09 3 days Sat 03-05-25 Mon 05-05-25 353FS+4 days 0% L09
Page 5
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
355 L10 3 days Sat 10-05-25 Mon 12-05-25 354FS+4 days 0% L10
356 Testing & Commisioning 20 days Tue 13-05-25 Sun 01-06-25 355 0% Testing & Commisioning
357 Cold & Hot Water 246 days Sun 29-09-24 Sun 01-06-25 0%
448 Sanitary & Plumbing 246 days Sun 29-09-24 Sun 01-06-25 0%
539 Fire Protection Services 246 days Sun 29-09-24 Sun 01-06-25 0%
630 Lift Installation 73 days Wed 05-02-25 Fri 18-04-25 0%
631 L09 8 days Wed 05-02-25 Wed 12-02-25 0%
632 Hoistway Preparation 2 days Wed 05-02-25 Thu 06-02-25 10,66 0% Hoistway Preparation
633 Guilde rail installation 2 days Fri 07-02-25 Sat 08-02-25 632 0% Guilde rail installation
634 Landing Door 2 days Sun 09-02-25 Mon 10-02-25 633 0% Landing Door
635 Electrical & Control System 2 days Tue 11-02-25 Wed 12-02-25 634 0% Electrical & Control System
636 L10 3 days Sun 09-02-25 Tue 11-02-25 633SS+2 days 0% L10
637 L11 3 days Tue 11-02-25 Thu 13-02-25 636SS+2 days 0% L11
638 L12 3 days Thu 13-02-25 Sat 15-02-25 637SS+2 days 0% L12
639 L13 3 days Sat 15-02-25 Mon 17-02-25 638SS+2 days 0% L13
640 L14 3 days Mon 17-02-25 Wed 19-02-25 639SS+2 days 0% L14
641 L15 3 days Wed 19-02-25 Fri 21-02-25 640SS+2 days 0% L15
642 L16 3 days Fri 21-02-25 Sun 23-02-25 641SS+2 days 0% L16
643 L17 3 days Sun 23-02-25 Tue 25-02-25 642SS+2 days 0% L17
644 L18 3 days Tue 25-02-25 Thu 27-02-25 643SS+2 days 0% L18
645 L19 3 days Thu 27-02-25 Sat 01-03-25 644SS+2 days 0% L19
646 L20 3 days Sat 01-03-25 Mon 03-03-25 645SS+2 days 0% L20
647 L21 3 days Mon 03-03-25 Wed 05-03-25 646SS+2 days 0% L21
648 L22 3 days Wed 05-03-25 Fri 07-03-25 647SS+2 days 0% L22
649 L23 3 days Fri 07-03-25 Sun 09-03-25 648SS+2 days 0% L23
650 L24 3 days Sun 09-03-25 Tue 11-03-25 649SS+2 days 0% L24
651 L25 3 days Tue 11-03-25 Thu 13-03-25 650SS+2 days 0% L25
652 L26 3 days Thu 13-03-25 Sat 15-03-25 651SS+2 days 0% L26
653 L27 3 days Sat 15-03-25 Mon 17-03-25 652SS+2 days 0% L27
654 L28 3 days Mon 17-03-25 Wed 19-03-25 653SS+2 days 0% L28
655 L29 3 days Wed 19-03-25 Fri 21-03-25 654SS+2 days 0% L29
656 L30 3 days Fri 21-03-25 Sun 23-03-25 655SS+2 days 0% L30
657 L31 3 days Sun 23-03-25 Tue 25-03-25 656SS+2 days 0% L31
658 L32 3 days Tue 25-03-25 Thu 27-03-25 657SS+2 days 0% L32
659 L33 3 days Thu 27-03-25 Sat 29-03-25 658SS+2 days 0% L33
660 Lift Car Installation 14 days Tue 04-03-25 Mon 17-03-25 646 0% Lift Car Installation
661 Counterweight Rail Installation 14 days Fri 14-03-25 Thu 27-03-25 660SS+10 days 0% Counterweight Rail Installation
662 Testing & Commisioning 20 days Sun 30-03-25 Fri 18-04-25 659,661 0% Testing & Commisioning
665 Final Touch Up 45 days Wed 09-04-25 Fri 23-05-25 664FF+14 days 0% Final Touch Up
666 BOMBA Inspection 7 days Sat 24-05-25 Fri 30-05-25 664,665 0% BOMBA Inspection
667 JKKP inspection 7 days Sat 24-05-25 Fri 30-05-25 664,665 0% JKKP inspection
668 CCC Issuance 14 days Wed 28-05-25 Tue 10-06-25 665SS+10 days,667SS+4 days
0% CCC Issuance
669 CPC issuance 7 days Wed 11-06-25 Tue 17-06-25 668 0% CPC issuance