0% found this document useful (0 votes)
13 views6 pages

- BTC Mitigation Program Rev.01

Uploaded by

Aniee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
13 views6 pages

- BTC Mitigation Program Rev.01

Uploaded by

Aniee
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 6

BTC Mitigation Program Rev.01.

mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
1 BTC BASELINE WORK PROGRAM REV.05 313 days Fri 09-08-24 Tue 17-06-25 1% BTC BASELINE WORK PROGRAM REV.05
2 MILESTONE & PROJECT COMPLETION DATES 235 days Fri 25-10-24 Tue 17-06-25 0%
3 MILESTONE 1 Roof Topping Up 0 days Tue 04-02-25 Tue 04-02-25 66 0% 04-02

4 MILESTONE 2 Water Tightness 0 days Sat 12-04-25 Sat 12-04-25 238 0% 12-04

5 MILESTONE 3 Mock-Up Unit 0 days Fri 25-10-24 Fri 25-10-24 87 0% 25-10

6 MILESTONE 4 Power Energization 0 days Mon 12-05-25 Mon 12-05-25 264 0% MILESTONE 4 Power Energization 12-05

7 CPC / CCC Issuance 0 days Tue 17-06-25 Tue 17-06-25 669,668 0% CPC / CCC Issuance 17-06

8 Preliminaries work 28 days Fri 09-08-24 Thu 05-09-24 77%


9 PMA Approval 30 days Fri 09-08-24 Sat 07-09-24 95% PMA Approval

10 Re-inspect tower crane & Passenger hoist 7 days Sun 08-09-24 Sat 14-09-24 9 0% Re-inspect tower crane & Passenger hoist

11 Structural Work 143 days Fri 30-08-24 Tue 04-02-25 3% Structural Work
12 Dismantle of Formwork 7 days Sun 15-09-24 Sat 21-09-24 9FF-2 days 80% Dismantle of Formwork

13 Demolisioin Work 7 days Sun 15-09-24 Sat 21-09-24 9FF-2 days 50% Demolisioin Work

14 Level 21 13 days Sun 22-09-24 Fri 04-10-24 0%


15 Zone A 10 days Sun 22-09-24 Tue 01-10-24 12,10,13 0% Zone A

16 Lift Shaft 21 & 22 10 days Wed 25-09-24 Fri 04-10-24 15SS+3 days 0% Lift Shaft 21 & 22

17 Level 22 20 days Sun 22-09-24 Fri 11-10-24 0%


18 Zone B 10 days Sun 22-09-24 Tue 01-10-24 12,13 0% Zone B

19 Zone A 10 days Wed 02-10-24 Fri 11-10-24 15 0% Zone A

20 Lift Shaft Level 23 5 days Mon 07-10-24 Fri 11-10-24 16,19SS+5 days 0% Lift Shaft Level 23

21 Level 23 20 days Wed 02-10-24 Mon 21-10-24 0%


22 Zone A 10 days Sat 12-10-24 Mon 21-10-24 19 0% Zone A

23 Zone B 10 days Wed 02-10-24 Fri 11-10-24 18 0% Zone B

24 Lift Shaft Level 24 5 days Thu 17-10-24 Mon 21-10-24 22SS+5 days,20 0% Lift Shaft Level 24

25 Level 24 20 days Sat 12-10-24 Thu 31-10-24 0%


26 Zone A 10 days Tue 22-10-24 Thu 31-10-24 22 0% Zone A

27 Zone B 10 days Sat 12-10-24 Mon 21-10-24 23 0% Zone B

28 Lift Shaft Level 25 5 days Sun 27-10-24 Thu 31-10-24 24,26SS+5 days 0% Lift Shaft Level 25

29 Level 25 20 days Tue 22-10-24 Sun 10-11-24 0%


30 Zone A 10 days Fri 01-11-24 Sun 10-11-24 26 0% Zone A

31 Zone B 10 days Tue 22-10-24 Thu 31-10-24 27 0% Zone B

32 Lift Shaft Level 26 5 days Wed 06-11-24 Sun 10-11-24 28,30SS+5 days 0% Lift Shaft Level 26

33 Level 26 20 days Fri 01-11-24 Wed 20-11-24 0%


37 Level 27 20 days Mon 11-11-24 Sat 30-11-24 0%
41 Level 28 20 days Thu 21-11-24 Tue 10-12-24 0%
45 Level 29 20 days Sun 01-12-24 Fri 20-12-24 0%
49 Level 30 20 days Wed 11-12-24 Mon 30-12-24 0%
53 Level 31 20 days Sat 21-12-24 Thu 09-01-25 0%
57 Level 32 20 days Tue 31-12-24 Sun 19-01-25 0%
61 Level 33 20 days Fri 10-01-25 Wed 29-01-25 0%
62 Zone A 10 days Mon 20-01-25 Wed 29-01-25 58 0% Zone A

63 Zone B 10 days Fri 10-01-25 Sun 19-01-25 59 0% Zone B

64 Lift Motor Room 5 days Sat 25-01-25 Wed 29-01-25 62SS+5 days,60 0% Lift Motor Room

65 Roof Level 16 days Mon 20-01-25 Tue 04-02-25 0%


66 Zone A 6 days Thu 30-01-25 Tue 04-02-25 62 0% Zone A

Page 1
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
67 Zone B 5 days Mon 20-01-25 Fri 24-01-25 63 0% Zone B

68 MILESTONE 1 COMPLETED 0 days Tue 04-02-25 Tue 04-02-25 67,66 0% MILESTONE 1 COMPLETED 04-02

69 Architectural works 230 days Sun 15-09-24 Fri 02-05-25 0%


70 Mock up Unit LEVEL 13 & 14 41 days Sun 15-09-24 Fri 25-10-24 0% Mock up Unit LEVEL 13 & 14
71 Level 13 41 days Sun 15-09-24 Fri 25-10-24 0%
72 AAC Block & Door & Window Frame9 days Sun 15-09-24 Mon 23-09-24 10 0% AAC Block & Door & Window Frame

73 M&E Work 2 days Tue 24-09-24 Wed 25-09-24 0%


74 2nd Fix (Cable Tray & Trunking) 2 days Tue 24-09-24 Wed 25-09-24 72 0% 2nd Fix (Cable Tray & Trunking)

75 Waterproofing 3 days Tue 24-09-24 Thu 26-09-24 72 0% Waterproofing

76 Ponding Test 2 days Fri 27-09-24 Sat 28-09-24 75 0% Ponding Test

77 Façade work 3 days Sun 29-09-24 Tue 01-10-24 76 0% Façade work

78 Screeding 5 days Thu 26-09-24 Mon 30-09-24 74 0% Screeding

79 Column/Drop/Ceiling Panel Skim 5 days Mon 30-09-24 Fri 04-10-24 78SS+4 days 0% Column/Drop/Ceiling Panel Skim

80 Plastering 5 days Mon 30-09-24 Fri 04-10-24 79SS 0% Plastering

81 Painting work 5 days Thu 03-10-24 Mon 07-10-24 80SS+3 days 0% Painting work

82 M&E Work 2 days Tue 08-10-24 Wed 09-10-24 0%


83 3rd Fix (Fitting Installation) 2 days Tue 08-10-24 Wed 09-10-24 81 0% 3rd Fix (Fitting Installation)

84 Plaster Ceiling 5 days Thu 10-10-24 Mon 14-10-24 83 0% Plaster Ceiling

85 Floor & Wall Tiles 5 days Mon 14-10-24 Fri 18-10-24 77,84SS+4 days 0% Floor & Wall Tiles

86 Steel Staircase 2 days Sat 19-10-24 Sun 20-10-24 85 0% Steel Staircase

87 Floor Finishes 5 days Mon 21-10-24 Fri 25-10-24 86 0% Floor Finishes

88 Door installation 2 days Mon 21-10-24 Tue 22-10-24 87SS 0% Door installation

89 Vanity Counter Top 2 days Sun 22-09-24 Mon 23-09-24 72FF 0% Vanity Counter Top

90 Ironmongeries 2 days Mon 21-10-24 Tue 22-10-24 88SS 0% Ironmongeries

91 Sanitary Fittings & Wares 3 days Mon 21-10-24 Wed 23-10-24 88SS 0% Sanitary Fittings & Wares

92 Level 14 (Unit E2) 30 days Sun 15-09-24 Mon 14-10-24 0%


93 AAC Block & Door & Window Frame5 days Sun 15-09-24 Thu 19-09-24 72SS 0% AAC Block & Door & Window Frame

94 M&E Work 2 days Fri 20-09-24 Sat 21-09-24 0%


95 2nd Fix (Cable Tray & Trunking) 2 days Fri 20-09-24 Sat 21-09-24 93 0% 2nd Fix (Cable Tray & Trunking)

96 Waterproofing 2 days Fri 20-09-24 Sat 21-09-24 93 0% Waterproofing

97 Ponding Test 2 days Sun 22-09-24 Mon 23-09-24 96 0% Ponding Test

98 Façade work 2 days Tue 24-09-24 Wed 25-09-24 97 0% Façade work

99 Screeding 4 days Sun 22-09-24 Wed 25-09-24 95 0% Screeding

100 Column/Drop/Ceiling Panel Skim 4 days Thu 26-09-24 Sun 29-09-24 99SS+4 days 0% Column/Drop/Ceiling Panel Skim

101 Plastering 4 days Thu 26-09-24 Sun 29-09-24 100SS 0% Plastering

102 Painting work 4 days Sun 29-09-24 Wed 02-10-24 101SS+3 days 0% Painting work

103 M&E Work 2 days Thu 03-10-24 Fri 04-10-24 0%


104 3rd Fix (Fitting Installation) 2 days Thu 03-10-24 Fri 04-10-24 102 0% 3rd Fix (Fitting Installation)

105 Plaster Ceiling 4 days Sat 05-10-24 Tue 08-10-24 104 0% Plaster Ceiling

106 Floor & Wall Tiles 2 days Wed 09-10-24 Thu 10-10-24 97,105SS+4 days 0% Floor & Wall Tiles

107 Floor Finishes 3 days Fri 11-10-24 Sun 13-10-24 106 0% Floor Finishes

108 Door installation 1 day Mon 14-10-24 Mon 14-10-24 107 0% Door installation

109 Vanity Counter Top 1 day Thu 19-09-24 Thu 19-09-24 93FF 0% Vanity Counter Top

110 Ironmongeries 1 day Mon 14-10-24 Mon 14-10-24 108SS 0% Ironmongeries

111 Sanitary Fittings & Wares 1 day Mon 14-10-24 Mon 14-10-24 108SS 0% Sanitary Fittings & Wares

Page 2
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
112 MILESTONE 3 COMPLETED 0 days Fri 25-10-24 Fri 25-10-24 87 0% MILESTONE 3 COMPLETED 25-10

113 Level 15 & 16 33 days Tue 24-09-24 Sat 26-10-24 0%


114 AAC Block & Door & Window Frame 14 days Tue 24-09-24 Mon 07-10-24 72 0% AAC Block & Door & Window Frame

115 Waterproofing 3 days Tue 08-10-24 Thu 10-10-24 114 0% Waterproofing

116 Ponding Test 4 days Fri 11-10-24 Mon 14-10-24 115 0% Ponding Test

117 Façade work 2 days Tue 15-10-24 Wed 16-10-24 116 0% Façade work

118 Screeding 6 days Tue 01-10-24 Sun 06-10-24 114SS+7 days 0% Screeding

119 Column/Drop/Ceiling Panel Skim 7 days Mon 07-10-24 Sun 13-10-24 118 0% Column/Drop/Ceiling Panel Skim

120 Plastering 7 days Mon 07-10-24 Sun 13-10-24 118 0% Plastering

121 Painting work 7 days Thu 10-10-24 Wed 16-10-24 120SS+3 days 0% Painting work

122 Plaster Ceiling 7 days Sun 20-10-24 Sat 26-10-24 121FS+3 days 0% Plaster Ceiling

123 Floor & Wall Tiles 7 days Thu 17-10-24 Wed 23-10-24 121 0% Floor & Wall Tiles

124 Level 17 & 18 33 days Tue 08-10-24 Sat 09-11-24 0%


125 AAC Block & Door & Window Frame 14 days Tue 08-10-24 Mon 21-10-24 114,72,93 0% AAC Block & Door & Window Frame

126 Waterproofing 3 days Tue 22-10-24 Thu 24-10-24 125 0% Waterproofing

127 Ponding Test 4 days Fri 25-10-24 Mon 28-10-24 126 0% Ponding Test

128 Façade work 2 days Tue 29-10-24 Wed 30-10-24 127 0% Façade work

129 Screeding 6 days Tue 15-10-24 Sun 20-10-24 125SS+7 days 0% Screeding

130 Column/Drop/Ceiling Panel Skim 7 days Mon 21-10-24 Sun 27-10-24 129 0% Column/Drop/Ceiling Panel Skim

131 Plastering 7 days Mon 21-10-24 Sun 27-10-24 129 0% Plastering

132 Painting work 7 days Thu 24-10-24 Wed 30-10-24 131SS+3 days 0% Painting work

133 Plaster Ceiling 7 days Sun 03-11-24 Sat 09-11-24 132FS+3 days 0% Plaster Ceiling

134 Floor & Wall Tiles 7 days Thu 31-10-24 Wed 06-11-24 132 0% Floor & Wall Tiles

135 Level 19 & 20 33 days Tue 22-10-24 Sat 23-11-24 0%


146 Level 21 & 22 33 days Thu 21-11-24 Mon 23-12-24 0%
157 Level 23 & 24 33 days Thu 05-12-24 Mon 06-01-25 0%
168 Level 25 & 26 33 days Thu 19-12-24 Mon 20-01-25 0%
179 Level 27 & 28 33 days Thu 30-01-25 Mon 03-03-25 0%
190 Level 29 & 30 33 days Tue 11-02-25 Sat 15-03-25 0%
201 Level 31 & 32 33 days Sun 23-02-25 Thu 27-03-25 0%
212 Level 33, 13 & 14(remaining) 33 days Fri 07-03-25 Tue 08-04-25 0%
223 Level 11 & 12 33 days Wed 19-03-25 Sun 20-04-25 0%
234 Level 09 & 10 33 days Mon 31-03-25 Fri 02-05-25 0%
235 AAC Block & Door & Window Frame 12 days Mon 31-03-25 Fri 11-04-25 224 0% AAC Block & Door & Window Frame

236 Waterproofing 3 days Sat 12-04-25 Mon 14-04-25 235 0% Waterproofing

237 Ponding Test 4 days Mon 07-04-25 Thu 10-04-25 226 0% Ponding Test

238 Façade work 2 days Fri 11-04-25 Sat 12-04-25 237 0% Façade work

239 Ponding Test 2 days Tue 15-04-25 Wed 16-04-25 236 0% Ponding Test

240 Screeding 6 days Mon 07-04-25 Sat 12-04-25 235SS+7 days 0% Screeding

241 Column/Drop/Ceiling Panel Skim 7 days Sun 13-04-25 Sat 19-04-25 240 0% Column/Drop/Ceiling Panel Skim

242 Plastering 7 days Sun 13-04-25 Sat 19-04-25 240 0% Plastering

243 Painting work 7 days Wed 16-04-25 Tue 22-04-25 242SS+3 days 0% Painting work

244 Plaster Ceiling 7 days Sat 26-04-25 Fri 02-05-25 243FS+3 days 0% Plaster Ceiling

245 Floor & Wall Tiles 7 days Wed 23-04-25 Tue 29-04-25 243 0% Floor & Wall Tiles

246 MILESTONE 2 COMPLETED 0 days Sat 12-04-25 Sat 12-04-25 238 0% MILESTONE 2 COMPLETED 12-04

Page 3
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
247 Other Finishes 60 days Tue 04-03-25 Fri 02-05-25 0%
248 Swimming Pool 45 days Wed 19-03-25 Fri 02-05-25 244FF 0% Swimming Pool

249 Door & Window installation 60 days Tue 04-03-25 Fri 02-05-25 248FF 0% Door & Window installation

250 Glass frame & glass installation 60 days Tue 04-03-25 Fri 02-05-25 249SS 0% Glass frame & glass installation

251 Sanitary Fittings & Wares 60 days Tue 04-03-25 Fri 02-05-25 249SS 0% Sanitary Fittings & Wares

252 Toilet Cubicle 30 days Tue 04-03-25 Wed 02-04-25 249SS 0% Toilet Cubicle

253 Glazing Work 60 days Tue 04-03-25 Fri 02-05-25 249SS 0% Glazing Work

254 Vanity Counter Top 45 days Wed 19-03-25 Fri 02-05-25 249SS+15 days 0% Vanity Counter Top

255 Ironmongeries 30 days Tue 04-03-25 Wed 02-04-25 249SS 0% Ironmongeries

256 Staircase Railing 30 days Thu 03-04-25 Fri 02-05-25 250FS-30 days 0% Staircase Railing

257 Signanage Work 30 days Wed 19-03-25 Thu 17-04-25 249SS+15 days 0% Signanage Work

258 Floor Finishes 45 days Wed 19-03-25 Fri 02-05-25 249SS+15 days 0% Floor Finishes

259 M&E 246 days Sun 29-09-24 Sun 01-06-25 0%


260 Power Energization 131 days Thu 02-01-25 Mon 12-05-25 0%
261 Document Submission 70 days Thu 02-01-25 Wed 12-03-25 169 0% Document Submission

262 Local Authority Approval 32 days Thu 13-03-25 Sun 13-04-25 261 0% Local Authority Approval

263 Energization 7 days Mon 14-04-25 Sun 20-04-25 262 0% Energization

264 Testing & Commisioning 20 days Wed 23-04-25 Mon 12-05-25 243,263 0% Testing & Commisioning

265 MILESTONE 4 COMPLETED 0 days Mon 12-05-25 Mon 12-05-25 264 0% MILESTONE 4 COMPLETED 12-05

266 Electrical Rough In 246 days Sun 29-09-24 Sun 01-06-25 0%


267 1st Fix ( Conduit Laying) 123 days Sun 29-09-24 Wed 29-01-25 0%
268 Level 21 3 days Sun 29-09-24 Tue 01-10-24 0%
269 Zone A 3 days Sun 29-09-24 Tue 01-10-24 15FF 0% Zone A

270 Level 22 13 days Sun 29-09-24 Fri 11-10-24 0%


271 Zone B 3 days Sun 29-09-24 Tue 01-10-24 18FF 0% Zone B

272 Zone A 3 days Wed 09-10-24 Fri 11-10-24 19FF 0% Zone A

273 Level 23 13 days Wed 09-10-24 Mon 21-10-24 0%


274 Zone A 3 days Sat 19-10-24 Mon 21-10-24 272FS+7 days 0% Zone A

275 Zone B 3 days Wed 09-10-24 Fri 11-10-24 271FS+7 days 0% Zone B

276 Level 24 13 days Sat 19-10-24 Thu 31-10-24 0%


279 Level 25 13 days Tue 29-10-24 Sun 10-11-24 0%
282 Level 26 13 days Fri 08-11-24 Wed 20-11-24 0%
285 Level 27 13 days Mon 18-11-24 Sat 30-11-24 0%
288 Level 28 13 days Thu 28-11-24 Tue 10-12-24 0%
291 Level 29 13 days Sun 08-12-24 Fri 20-12-24 0%
294 Level 30 13 days Wed 18-12-24 Mon 30-12-24 0%
297 Level 31 13 days Sat 28-12-24 Thu 09-01-25 0%
300 Level 32 13 days Tue 07-01-25 Sun 19-01-25 0%
303 Level 33 13 days Fri 17-01-25 Wed 29-01-25 0%
304 Zone A 3 days Mon 27-01-25 Wed 29-01-25 301FS+7 days 0% Zone A

305 Zone B 3 days Fri 17-01-25 Sun 19-01-25 302FS+7 days 0% Zone B

306 2nd Fix (Cable Tray & Trunking) 210 days Tue 08-10-24 Mon 05-05-25 0%
307 L15 7 days Tue 08-10-24 Mon 14-10-24 114 0% L15

308 L16 7 days Tue 15-10-24 Mon 21-10-24 307 0% L16

309 L17 7 days Tue 22-10-24 Mon 28-10-24 308 0% L17

Page 4
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
310 L18 7 days Tue 29-10-24 Mon 04-11-24 309 0% L18

311 L19 7 days Tue 05-11-24 Mon 11-11-24 310 0% L19

312 L20 7 days Tue 12-11-24 Mon 18-11-24 311 0% L20

313 L21 7 days Thu 05-12-24 Wed 11-12-24 312,147 0% L21

314 L22 7 days Thu 12-12-24 Wed 18-12-24 313 0% L22

315 L23 7 days Thu 19-12-24 Wed 25-12-24 314 0% L23

316 L24 7 days Thu 26-12-24 Wed 01-01-25 315 0% L24

317 L25 7 days Thu 02-01-25 Wed 08-01-25 316 0% L25

318 L26 7 days Thu 09-01-25 Wed 15-01-25 317 0% L26

319 L27 7 days Tue 11-02-25 Mon 17-02-25 318,180 0% L27

320 L28 7 days Tue 18-02-25 Mon 24-02-25 319 0% L28

321 L29 7 days Tue 25-02-25 Mon 03-03-25 320 0% L29

322 L30 7 days Tue 04-03-25 Mon 10-03-25 321 0% L30

323 L31 7 days Tue 11-03-25 Mon 17-03-25 322 0% L31

324 L32 7 days Tue 18-03-25 Mon 24-03-25 323 0% L32

325 L33 7 days Tue 25-03-25 Mon 31-03-25 324,305,304 0% L33

326 L13 & L14 7 days Tue 01-04-25 Mon 07-04-25 325 0% L13 & L14

327 L11 7 days Tue 08-04-25 Mon 14-04-25 326 0% L11

328 L12 7 days Tue 15-04-25 Mon 21-04-25 327 0% L12

329 L09 7 days Tue 22-04-25 Mon 28-04-25 328 0% L09

330 L10 7 days Tue 29-04-25 Mon 05-05-25 329 0% L10

331 3rd Fix (Fitting Installation) 204 days Mon 21-10-24 Mon 12-05-25 0%
332 L15 3 days Mon 21-10-24 Wed 23-10-24 121FS+4 days 0% L15

333 L16 3 days Mon 28-10-24 Wed 30-10-24 332FS+4 days 0% L16

334 L17 3 days Mon 04-11-24 Wed 06-11-24 333FS+4 days 0% L17

335 L18 3 days Mon 11-11-24 Wed 13-11-24 334FS+4 days 0% L18

336 L19 3 days Mon 18-11-24 Wed 20-11-24 335FS+4 days 0% L19

337 L20 3 days Mon 25-11-24 Wed 27-11-24 336FS+4 days 0% L20

338 L21 3 days Sat 14-12-24 Mon 16-12-24 337FS+4 days,154 0% L21

339 L22 3 days Sat 21-12-24 Mon 23-12-24 338FS+4 days 0% L22

340 L23 3 days Sat 28-12-24 Mon 30-12-24 339FS+4 days 0% L23

341 L24 3 days Sat 04-01-25 Mon 06-01-25 340FS+4 days 0% L24

342 L25 3 days Sat 11-01-25 Mon 13-01-25 341FS+4 days 0% L25

343 L26 3 days Sat 18-01-25 Mon 20-01-25 342FS+4 days 0% L26

344 L27 3 days Sat 22-02-25 Mon 24-02-25 343FS+4 days,319,187 0% L27

345 L28 3 days Sat 01-03-25 Mon 03-03-25 344FS+4 days 0% L28

346 L29 3 days Sat 08-03-25 Mon 10-03-25 345FS+4 days 0% L29

347 L30 3 days Sat 15-03-25 Mon 17-03-25 346FS+4 days 0% L30

348 L31 3 days Sat 22-03-25 Mon 24-03-25 347FS+4 days 0% L31

349 L32 3 days Sat 29-03-25 Mon 31-03-25 348FS+4 days 0% L32

350 L33 3 days Sat 05-04-25 Mon 07-04-25 349FS+4 days,325 0% L33

351 L13 & L14 3 days Sat 12-04-25 Mon 14-04-25 350FS+4 days 0% L13 & L14

352 L11 3 days Sat 19-04-25 Mon 21-04-25 351FS+4 days 0% L11

353 L12 3 days Sat 26-04-25 Mon 28-04-25 352FS+4 days 0% L12

354 L09 3 days Sat 03-05-25 Mon 05-05-25 353FS+4 days 0% L09

Page 5
BTC Mitigation Program Rev.01.mpp
ID Task Name Duration Baseline Start Baseline Finish Predecessors % Complete
May 2024 July 2024 September 2024 November 2024 January 2025 March 2025 May 2025 July 2025
01 June 01 July 01 August01 September
01 October01 November
01 December
01 January01 February
01 March 01 April 01 May 01 June 01 July 01 August
-3 -1 2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 32 34 36 38 40 42 44 46 48 50 52 54 56 58 60 62
355 L10 3 days Sat 10-05-25 Mon 12-05-25 354FS+4 days 0% L10

356 Testing & Commisioning 20 days Tue 13-05-25 Sun 01-06-25 355 0% Testing & Commisioning

357 Cold & Hot Water 246 days Sun 29-09-24 Sun 01-06-25 0%
448 Sanitary & Plumbing 246 days Sun 29-09-24 Sun 01-06-25 0%
539 Fire Protection Services 246 days Sun 29-09-24 Sun 01-06-25 0%
630 Lift Installation 73 days Wed 05-02-25 Fri 18-04-25 0%
631 L09 8 days Wed 05-02-25 Wed 12-02-25 0%
632 Hoistway Preparation 2 days Wed 05-02-25 Thu 06-02-25 10,66 0% Hoistway Preparation

633 Guilde rail installation 2 days Fri 07-02-25 Sat 08-02-25 632 0% Guilde rail installation

634 Landing Door 2 days Sun 09-02-25 Mon 10-02-25 633 0% Landing Door

635 Electrical & Control System 2 days Tue 11-02-25 Wed 12-02-25 634 0% Electrical & Control System

636 L10 3 days Sun 09-02-25 Tue 11-02-25 633SS+2 days 0% L10

637 L11 3 days Tue 11-02-25 Thu 13-02-25 636SS+2 days 0% L11

638 L12 3 days Thu 13-02-25 Sat 15-02-25 637SS+2 days 0% L12

639 L13 3 days Sat 15-02-25 Mon 17-02-25 638SS+2 days 0% L13

640 L14 3 days Mon 17-02-25 Wed 19-02-25 639SS+2 days 0% L14

641 L15 3 days Wed 19-02-25 Fri 21-02-25 640SS+2 days 0% L15

642 L16 3 days Fri 21-02-25 Sun 23-02-25 641SS+2 days 0% L16

643 L17 3 days Sun 23-02-25 Tue 25-02-25 642SS+2 days 0% L17

644 L18 3 days Tue 25-02-25 Thu 27-02-25 643SS+2 days 0% L18

645 L19 3 days Thu 27-02-25 Sat 01-03-25 644SS+2 days 0% L19

646 L20 3 days Sat 01-03-25 Mon 03-03-25 645SS+2 days 0% L20

647 L21 3 days Mon 03-03-25 Wed 05-03-25 646SS+2 days 0% L21

648 L22 3 days Wed 05-03-25 Fri 07-03-25 647SS+2 days 0% L22

649 L23 3 days Fri 07-03-25 Sun 09-03-25 648SS+2 days 0% L23

650 L24 3 days Sun 09-03-25 Tue 11-03-25 649SS+2 days 0% L24

651 L25 3 days Tue 11-03-25 Thu 13-03-25 650SS+2 days 0% L25

652 L26 3 days Thu 13-03-25 Sat 15-03-25 651SS+2 days 0% L26

653 L27 3 days Sat 15-03-25 Mon 17-03-25 652SS+2 days 0% L27

654 L28 3 days Mon 17-03-25 Wed 19-03-25 653SS+2 days 0% L28

655 L29 3 days Wed 19-03-25 Fri 21-03-25 654SS+2 days 0% L29

656 L30 3 days Fri 21-03-25 Sun 23-03-25 655SS+2 days 0% L30

657 L31 3 days Sun 23-03-25 Tue 25-03-25 656SS+2 days 0% L31

658 L32 3 days Tue 25-03-25 Thu 27-03-25 657SS+2 days 0% L32

659 L33 3 days Thu 27-03-25 Sat 29-03-25 658SS+2 days 0% L33

660 Lift Car Installation 14 days Tue 04-03-25 Mon 17-03-25 646 0% Lift Car Installation

661 Counterweight Rail Installation 14 days Fri 14-03-25 Thu 27-03-25 660SS+10 days 0% Counterweight Rail Installation

662 Testing & Commisioning 20 days Sun 30-03-25 Fri 18-04-25 659,661 0% Testing & Commisioning

663 Completion 70 days Wed 09-04-25 Tue 17-06-25 0%


664 Dismantle Tower Crane 14 days Sat 26-04-25 Fri 09-05-25 248FS-7 days,662 0% Dismantle Tower Crane

665 Final Touch Up 45 days Wed 09-04-25 Fri 23-05-25 664FF+14 days 0% Final Touch Up

666 BOMBA Inspection 7 days Sat 24-05-25 Fri 30-05-25 664,665 0% BOMBA Inspection

667 JKKP inspection 7 days Sat 24-05-25 Fri 30-05-25 664,665 0% JKKP inspection

668 CCC Issuance 14 days Wed 28-05-25 Tue 10-06-25 665SS+10 days,667SS+4 days
0% CCC Issuance

669 CPC issuance 7 days Wed 11-06-25 Tue 17-06-25 668 0% CPC issuance

Page 6

You might also like