Assignment 2- Delay Protocol
Assignment 2- Delay Protocol
In any kind of construction industry it is impossible to prevent any delay or disruptions which can be caused
by employer, contractor or by various other activities. These delays mostly results in loss of time as well as
money and thus their claim from the either parties becomes inevitable which can lead to disputes. Thus in
order to deal with such disputes in orderly and coherent manner Delay Protocol is prepared by Society of
Construction Law for determining extensions of time and compensation for delay and disruptions. It was
published on October 16th 2002. It does need to be included in the contract but acts as a guidance to all
parties to the construction process when dealing with time delay matters. It recognizes that transparency of
information and methodology is central to both dispute prevention and dispute resolution.
Guideline Section 3: It deals with extension of time applications during the course of the project.
Guideline Section 4: Deals with causes and responsibility of delay of the project.
Guidance Section 1
Guidance Section 2
Guidance Section 3
Procedure for granting extension of time-
The EOT ought to be allowed to the degree that the Employer Risk Event is sensibly anticipated to keep
the works being finished by the then prevailing contract completion date.
Contractor should generally submit a sub-network to be inserted into the Updated Programme, which
should be close to the Delay period.
The CA will check if the event is eligible to be considered as Employer Risk Event.
Disagreements on the matters of EOT should be solved immediately and should not be left for the end.
The contractor should inform CA immediately if he disagrees with his decision.
The sub- network should be prepared in the same manner with the same software by which the original
programme was made.
Guidance Section 4
Delay Analysis-
If programme and record were not prepared in accordance with the protocols during the course of work
then delay analysis will be done on the basis of:
The terms of the contract:
Collapse as built, As planned as built and time impact analysis are to be used when contract terms
denotes that contractor can claim liquidated damages or compensation only if Employer Risk Events
causes the delay in completion date of the project. Impacted as planned and time impact analysis can be
used if contractor is to be given compensation for any losses it incurs due to employer’s risk events.
Records available of the contractor:
It means that analysis will be done on the basis of two records:
Planned and updated network diagram.
Records and data available of the works.
Nature of events causing the delay:
It means that delay will be analyzed on the basis of cause of delay i.e. Whether it was contractor delay ,
employee delay , has delay caused the delay of project completion time , whether the activity was
completed or it was in still in planning etc.
Cost of analysis and amount of Dispute:
As the above heading suggest, Delay analysis will be done on the basis of how much damage either parties
have faced due to delay. Thus it depends on the parties that how much detail analysis a party wants to
make and thus can pay the cost of analysis depending on the damages at stake.
Construction Contract Management
CVL-774
Assignment 2
A Brief on the Society of Construction Law Delay
& Distribution Protocol
(October 2002, October 2004 Reprint)
Submitted By-
Anupam Verma - 2015CEC2727
Haris Azeez - 2015CEC2732
Rahul Chauhan - 2015CEC2738