WEATHER 0 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 0
0 1 2 3 4 5 6 7 8 9 0 1 2 3
Notes
FINE
DRIZZLE
RAIN
0 1 2 3 4 5 6 7 8 9 1 1 1 1 1 1 1 1 1 1 2 2 2 2 0
0 1 2 3 4 5 6 7 8 9 0 1 2 3
LABOUR
SUB-CONTRACTOR PERSON WORK START WORK END TOTAL HOURS
7 08:00 20:00 12
8 08:00 19:00 11
ACTIVITY SUMMARY
ACTIVITY LOCATION STATUS
The subsoil manhole cover has been fabricated Open Fabrication Completed
Yard
Crusher run leveling at 36 meters Covered workshop In Progress
Strengthening work on 23/23 of Gantry completed Gantry Completed
Earth leveling for covered workshop at 42 meters Covered Workshop In Progress
'Z' purlin installation welding shed Completed
Welding the Base of the High Beam for Rail Bound Machinery Open Fabrication In Progress
Workshop Yard
REMARKS:
PREPARED BY CHECKED BY
Name : Guruparan Name : Saravanan
Company : Rexcel Bina Sdn. Bhd. Company : Rexcel Bina Sdn. Bhd.
Designation : Site Engineer Designation : Construction Manager
REXCEL BINA SDN BHD
PICTURES