0% found this document useful (0 votes)
23 views

isb-itpm-captone-project-part1-

Uploaded by

kawata1209
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
23 views

isb-itpm-captone-project-part1-

Uploaded by

kawata1209
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 8

lOMoARcPSD|37652339

ISB ITPM Captone Project Part1 Nidadavolu Niranjan

BITS WILP M Tech Data Science & Engineering (Birla Institute of Technology and
Science, Pilani)

Scan to open on Studocu

Studocu is not sponsored or endorsed by any college or university


Downloaded by Nnn nnn ([email protected])
lOMoARcPSD|37652339

Date: 19.06.2022

IT PROJECT MANAGEMENT

Assignment PROJECT CHARTER

Project Name ONLINE TIME MANAGEMENT SYSTEM (OTMS)

NIDADAVOLU NIRANJAN
For Internal Use Only Page 1

Downloaded by Nnn nnn ([email protected])


lOMoARcPSD|37652339

PROJECT CHARTER DOCUMENT

PURPOSE OF THE DOCUMENT:

The purpose of this document is to present a detailed description of the Online Time Management
System(OTMS) for NSPIRA Management Service Pvt Ltd to manage their resources well.
The goal of the system is to develop such an application which help people to live a stress-free life
by organizing their daily routine effectively and help managers to monitor the team and improve
the productivity. OTMS will organize the tasks according to the priorities given by the users which
will help to increase their overall productivity at the end of the day.

This document covers high level business needs and objective, scope, time and cost, risks,
constraints of the project, stakeholder involved including the project team and approval
requirements.

Version 1.0
June 19, 2022

For Internal Use Only Page 2

Downloaded by Nnn nnn ([email protected])


lOMoARcPSD|37652339

PROJECT CHARTER

Project Name: Project Number:


Online Time Management System (OTMS) OTMS-2022-0001

Date: 19.06.2022 Revision Number: 0001

1. PROJECT GOALS

Problem Statement
✓ NSPIRA Management Services is a service-based company which provide multiple services like
Education, IT, Infrastructure, etc., It employed 40,000 resources across country and paying a
salary of INR 75 crores every month. The employees are spread across 750 different branches
across country. The organization is managing their employee work hours manually where
tracking of working hours of employees is tedious and challenging. This inefficient system leads
to resource un-utilization. Internal audit team investigated this and suggested to implement
an automated system which can track the working hours of employees. This initiative expected
to bring in employee utilization and cost reduction up to 5% i.e., INR 3.75 Crores every month.
Business Need
✓ The objective is this project is to develop an online time tracking system which is expected to
track the efforts spent for each task and prioritize the task set by the managers.
✓ The software delivers dashboard exhibiting the complete tracking of man hours and reports
to all core stakeholders in the management hierarchy.
✓ The software is compatible to work on Laptops, Desktops and Android Mobile Phones.
✓ Proposed Project budget – INR 3.75 Crores.
✓ The Project is expected to go live by 1st January 2023.
✓ The App should help the management to reach their savings goal by at least 90% (i.e., 90% of
3.75 Crores) from 2023.
✓ Payback period is one year.

2. DELIVERABLES
1. Web Application for Online Time Management Application for users.
2. Mobile Application for Online Time Management Application.
3. Web Application for Admin to create master data and create users and access rights.
4. Screens to capture all tasks given to the employee.
5. Screens to capture the priorities set by the managers or employee itself.
6. Services to capture login and logout times automatically.
7. Services to capture the number of hours spent on each task automatically.
8. APIs to support the payroll system to generate salaries end of the month.
9. Reports and dash boards to all levels in reporting hierarchy.

For Internal Use Only Page 3

Downloaded by Nnn nnn ([email protected])


lOMoARcPSD|37652339

3. SCOPE DEFINITION

This Online Time Management System(OTMS) is a multi-functioning system where the team member or the
managers can create list of tasks which will be including simple drag & drop interface to rearrange the tasks as
per the priority. It creates a hierarchy of tasks & subtasks. Once you have added due dates & dependencies, the
application will automatically generate a smart list of actions that require immediate attention. OTMS will suggest
through notifications about how you can complete the left-out tasks throughout week in spare times you have
in a week and according to your response given to the application and through various algorithms that we will be
using system will learn from inputs given every day and will suggest best ways to utilize time in daily routine to
enhance your productivity for the next day. The system should also alert the team member as well as the manager
on underutilization of resources and underperforming resources. This software will be built using HTML, CSS, C#,
Angular JS, MS SQL Server.

The project will include:


1. Development of a web application for Online Time management system.
2. Development of an Android mobile app for Online time management system.
3. APIs to integrate with Payroll System for Salary Generation.
4. The user interface design should have the following:
a. Branch Master
b. Employee Master
c. Reporting Hierarchy mapping
d. Task entry screen
e. Task allocation screen
f. Task prioritization screen
g. A screen to put the task in pause in breaks
h. A screen to hold the task if instructed by the manager
i. A screen to transfer the task to another member
j. Notifications screens
k. Leaves capturing screen
l. Reports & Dash boards ( Self & Reporting team )
m. Database Design
n. Testing Web Application
o. Testing Mobile Application
p. Integration Testing with Payroll System
q. User Training

The project will not include:


1. Mobile app for Apple(iOS) is not part of the scope.
2. Performance Testing is not part of the scope.
3. Load Testing is not part of the scope.

For Internal Use Only Page 4

Downloaded by Nnn nnn ([email protected])


lOMoARcPSD|37652339

4. PROJECT MILESTONES

S.No Task Delivery Date


1 Project Kick off 01.07.2022
2 Requirement gathering 10.07.2022
3 Architecture & Design 30.07.2022
4 Web App Development 30.09.2022
5 Mobile App Development 30.09.2022
6 Admin App Development 30.09.2022
7 QC Testing 15.10.2022
8 UAT 30.10.2022
9 Bug fixing identified in UAT 10.11.2022
10 Regression Testing 20.11.2022
11 Go Live 01.12.2022
12 User Training 10.12.2022
13 Project Closure 01.01.2023

5. ASSUMPTIONS, CONSTRAINTS & DEPENDENCIES

Assumptions:
1. Resources are onboarded on or before Project start date by the HR team.
2. Required IT infrastructure and development environment is ready.
3. Software successfully works in older Android versions.
4. Technical team is ready with Architecture design, Development (for both Web & Mobile) and Testing.
5. Business team will allocate time as and when required.
6. Technologies, Tools, and Servers are ready by start date of Project.
7. Training plan is prepared and informed to business to schedule their works accordingly.

Constraints:
1. Inhouse resources cannot be expected to work overtime.
2. Current lead time in getting Angular resources is more than 3 months.
3. Financial constraint in releasing funds to partners during Pandemic situation.
4. Skill gap of the existing resources in the latest technologies may delay the project.

Dependencies:
1. Dependency on Infrastructure components.
2. Dependency on Tools and software licenses.
3. Integration with Payroll is dependent on Payroll Development team.
4. Dependency on availability of business team on requirements gathering.
5. UAT is dependent on business team.

6. RISK

1. Lower productivity as resources work from home due to Pandemic outburst.


2. Unavailability of resources due to unplanned sickness ( Covid ).

For Internal Use Only Page 5

Downloaded by Nnn nnn ([email protected])


lOMoARcPSD|37652339

3. Un expected resignations of team members.


4. Infrastructure imports may get delay due to pandemic.
5. New government regulations may impact the scope.

7. RELATED DOCUMENTS

1. Business Requirements Document (BRD)


2. Software Requirement Specifications Document (SRS)
3. Technical Requirements Document (TRD)
4. Request for Proposal (RFP)
5. RFI ( for IT Infra )
6. RFQ (for IT Infra )
7. Corporate Process Assets
8. Lessons learned Documents of previous projects
9. Testing Process Documentation
10. Change Management Plan Document
11. Architecture & Design Documents

8. APPROVAL REQUIREMENTS

1. Sponsor should agree & approve the business requirements given by the business.
2. SME must approve the business requirements of the project.
3. HR Head or Product Owner should approve the business requirements of the project.
4. Finance Head or The Sponsor should approve the budget for Human Resources.
5. Finance Head or The Sponsor should approve the budget for IT Infrastructure, Software
Licenses, Tools.
6. CTO must approve Technical Requirements, Software Specifications and Technical
Architecture of the project.
7. Project manager must approve the business requirements of the Project.
8. Any deviations in the budget should go to Finance Head for approval.
9. Any deviations in the time should go to Sponsor for approval.

10. BUDGET & DATES

Project Start Date 01.07.2022

Project End Date 30.11.2022 Project Budget INR 3.75 Crores

Go Live Date 01.12.2022

11. PROJECT ORGANIZATIONAL STRUCTURE


Function Name Role
Mr.Niranjan
Project Management Project Manager
Nidadavolu
Strategy Mr.Puneet Kothapa Executive Director (ED)
For Internal Use Only Page 6

Downloaded by Nnn nnn ([email protected])


lOMoARcPSD|37652339

Finance Management Mr.Kali Prasad VP Finance


Sponsor (Chief Peoples
HR Management Mr.Showri Reddy
Officer(CPO)
HR Manager Cum SME for
HR Management Mr.Laveen Kumar
Project
Procurement Mr.Rajendra Procurement Manager
Information Technology Mr.Seshu Kumar R Chief Technical Officer (CTO)
Information Technology Mr.Himavantha Rao J Technical Architect
Information Technology Mr.Sudarshana Reddy Development Manager
User Experience Design Mr.Nagaraju UI/UX Designer
Web App Development Mr.Amarendra Senior Software Developer
Web App Development Mr.Venu P Software Developer
Mobile App Development Mr.Ramesh Naidu Software Developer
Testing Mr.Anji Reddy M Software Tester
Testing Mr.Moeed Ahmed Junior Software Tester
Help Desk Mrs.Sandhya Rani Customer Support Associate
Procurement Mr.Mallikarjuna Vendor

12. PROJECT AUTHORIZATION


Approved by: Business Manager: Date:
Mr.Showri Reddy 17.06.2022
Project Sponsor & Chief People’s Officer
at NSPIRA Management Services Pvt Ltd

Approved by: Project Manager: Date:


Niranjan Nidadavolu 17.06.2022

For Internal Use Only Page 7