Method Of Statement -LIghtning Protection System
Method Of Statement -LIghtning Protection System
PREPARED BY:
Dante CH Wong
CONTENTS:
1.Scope of works
2.Equipment / Tools / Machinery
3. Health & Safety Risk and Control
4. Access / Egress
5. Lightning
6. Plant & Equipment
7. Waste Management
8. Special Control Measurement
9. Procedures
1. Scope of Works
Scope of Activities
Site Procedure
Site mobilization shall be done with real time monitoring the conditions
& progress of builder works. Before commencement of the work, carry
out examination of the physical condition of the area. Photographs
should be taken where necessary, prior to commencement and during
works.
2.Equipment / Tools / Machinery
According to Malaysia standard specification all material shall comply with the
specification such as quality, dimension, strength and others. Sample need to
be submitted to the Consultant for approval. All the material must follow the
specification as per consultant’s approval before any installation.
Care for self, care for others and let others care for you.
Check for colleagues safety conditions and let colleagues care
for you.
5. Lightning
Adequate temporary/task lighting shall be provided if work to be carried at
night or at dark places.
6. Plant & Equipment
S/N Description
1 Centre punch
2 Brace
3 Hammer
5 Diagonal-Cutting Pliers
7 Side-Cutting Pliers
8 Level
9 Shank Screwdriver
*The above machinery & Equipment used quantity will be varied depending
on site conditions and production rate.
7. Waste Management
The Rubbish which would be created from our scope of works will be
disposed to the designated dumping ground.
I. Preparation stage
are
c. Prior to install lightning protection system examine paths to ensure all areas
free
of debris that may interfere with the installation.
e. All the related material should be stored away from high traffic areas.
II. Installation Stage
c. Method and material used for the installation of Lightning protection system
shall
comply BS6651. (Protection of structure against lightning).
d. The earth electrode pits location shall be marked out on site before
commencement
of hammering in electrodes. The earth pits shall be near the location of the
down
conductors.
e. Those earth pits located in the basement shall be provided with seals to
prevent
penetration of the ground slab.
f. Electrodes are hammered into the ground and reading is taken to ensure
that the
resistance is less than 10 ohms per electrode.
Select the correct type of metalwork bond of the application, ie a flat column
face, a circular rainwater pipe or a ribbed reinforcing bar.
Use air terminals in the form of vertical air rod for the protection of
prominent roof top features or equipment. Use strike pads to expose
concealed conductors
p. Air terminal bases: Choose the correct air terminal base. This will ensure
that the vertical air rods are both solidly fixed to the fabric of the structure
and have a low resistance connection to the conductor network.
s. Engineer – in – charge shall arrange and request for inspection with the
Owner’s representative Residential Technical Officer (RTO) using approved
Main con Request for Inspection (RIN) form.