MS Unit 4 (1)
MS Unit 4 (1)
c. Product Development:
It means increasing sales by improving current products in some way or
developing entirely new products for current markets. For example, Gillette has
modified its razor and named it Vector for Indian consumers. In auto industry,
manufacturers regularly introduce redesigned or new products.
Strategic Management Process - Meaning, Steps and Components
The strategic management process means defining the organization’s strategy.
It is also defined as the process by which managers make a choice of a set of
strategies for the organization that will enable it to achieve better performance.
Strategic management is a continuous process that appraises the business and
industries in which the organization is involved; appraises it’s competitors; and fixes
goals to meet all the present and future competitor’s and then reassesses each
strategy.
Strategic management process has following four steps;
Environmental Scanning
Environmental scanning refers to a process of collecting, scrutinizing and
providing information for strategic purposes. It helps in analyzing the internal and
external factors influencing an organization. After executing the environmental
analysis process, management should evaluate it on a continuous basis and strive to
improve it.
Strategy Formulation
Strategy formulation is the process of deciding best course of action for
accomplishing organizational objectives and hence achieving organizational
purpose. After conducting environment scanning, managers formulate corporate,
business and functional strategies.
Strategy Implementation
Strategy implementation implies making the strategy work as intended or
putting the organization’s chosen strategy into action. Strategy implementation
includes designing the organization’s structure, distributing resources, developing
decision making process, and managing human resources.
Strategy Evaluation
Strategy evaluation is the final step of strategy management process. The key
strategy evaluation activities are: appraising internal and external factors that are the
root of present strategies, measuring performance, and taking remedial / corrective
actions. Evaluation makes sure that the organizational strategy as well as it’s
implementation meets the organizational objectives.
These components are steps that are carried, in chronological order, when
creating a new strategic management plan. Present businesses that have already
created a strategic management plan will revert to these steps as per the situation’s
requirement, so as to make essential changes.
Two essential features are present in every project no matter how simple or
complicated they are. In the first place, all projects must be planned out in advance if
they are to be successfully executed. Secondly, the execution of the project must be
controlled to ensure that the desired results are achieved.
Terminology and Definitions
A project is an interrelated set of activities that has a definite starting and
ending point and results in the accomplishment of a unique, often major outcome.
"Project management" is, therefore, the planning and control of events that, together,
comprise the project. Project management aims to ensure the effective use of
resources and delivery of the project objectives on time and within cost constraints.
An activity or task is the smallest unit of work effort within the project and
consumes both time and resources which are under the control of the project
manager. A project is a sequence of activities that has a definite start and finish, an
identifiable goal and an integrated system of complex but interdependent
relationships.
A schedule allocates resources to accomplish the activities within a timeframe.
The schedule sets priorities, start times and finish times.
Project management
It is the adept use of techniques and skills (hard and soft) in planning and
controlling tasks and resources needed for the project, from both inside and outside
of organisation, to achieve results.
The purpose of project management is to achieve successful project completion with
the resources available. A successful project is one which:
✓ has been finished on time
✓ is within its cost budget
✓ performs to a technical/performance standard which satisfies the end user.
Features of projects
➢ Projects are often carried out by a team of people who have been assembled
for that specific purpose. The activities of this team may be co-ordinated by a
project manager.
➢ Project teams may consist of people from different backgrounds and different
parts of the organisation. In some cases project teams may consist of people
from different organisations.
➢ Project teams may be inter-disciplinary groups and are likely to lay outside
the normal organisation hierarchies.
➢ The project team will be responsible for delivery of the project end product to
some sponsor within or outside the organisation. The full benefit of any
project will not become available until the project has been completed.
Net work analysis:
It is refers to a number of techniques for the planning and control of complex
projects. The basis of network planning is the representation of sequential
relationships between activities by means of a network of lines and circles. The idea
is to link the various activities in such a way that the overall time spent on the
project is kept to a minimum.
Features of Network Analysis:
Logical base of planning:
Network analysis is highly applicable at several stages of project management
right from early planning stage of selecting right option from various alternatives to
scheduling stage and operational stage.
Simple in nature:
Net work analysis is straightforward in concept and can be easily explained to
any laymen. Data calculations are simple and for large projects computers can be
used.
Improves coordination and communication:
The graphs generated out of network analysis display simply and direct way
the complex nature of various sub- divisions of project may, quickly perceive from
the graph
Wider application:
The network analysis is applied to many types of projects. Moreover, they
may be applied at several levels within a given project from a single department
working on a sub-system to multi-plant operations within corporation.
Gantt’s bar chart:
A Gantt Chart is a simple technique that can be used to attach a time scale and
sequence to a project.
A Gantt Chart is a form of horizontal bar chart and horizontal bars are drawn
against a time scale for each project activity, the length of which represents the time
taken to complete.
To construct a Gantt Chart the following steps are necessary:
1. Use the horizontal axis to represent time
2. Use the vertical axis to represent activities
3. Represent each activity by a horizontal bar of appropriate length
4. Take activity procedures into account by starting each activity bar to an
appropriate point along the time axis after its preceding activities. Normally
the start point for an activity is the earliest time that it could start after its
preceding activities had finished.
It is possible to enhance the Gantt Chart in several ways. For instance the number of
staff required to do a task can be entered into the bar on the diagram.
Gantt charts, also commonly known as milestone plans, are a low cost means
of assisting the project manager at the initial stages of scheduling. They ensure that:
1. all activities are planned for,
2. the sequence of activities is accounted for,
3. the activity time estimates are recorded; and
4. the overall project time is recorded.
They are therefore a simple, rough and ready means of planning a project and
assessing progress and are sufficient for most simple projects.
However, where projects become complex, it becomes difficult to see relationships
between activities by using a Gantt Chart.
For more complex projects Network Analysis techniques are used.
Gantt charts also provide a summary of the project as a whole and can be
used as a rough and ready means of assessing progress at the project control phase.
At any date, the project manager can draw a dateline through the Gantt chart and
see which activities are on-time, which are behind schedule and generally record
project status against plan.
Gantt charts, named after Henry L. Gantt, one of the pioneers of scientific
management, are a useful means of representing a schedule of activities comprising
a project and enable the operations manager to know exactly what activities should
be performed at a given time and, more importantly, to monitor daily progress of a
project so that corrective action may be taken when necessary.
Before PERT and CPM were developed, Gantt charts and mile stone charts
were used tools to monitor the project progress in complex projects. Gantt chart is a
bar chart, which was developed by Henry Gantt around 1900.
It is consists of two coordinate axes, one represents the time and the other jobs or
activities performed.
The above figure shows job x which contains five activities ABCDE the
different time durations activity A is an independent activity followed by activities
B, activity B is followed by activity C, activities D, E have no such sequence.
Activities C, D and E reach completion together. However the total number o day
taken for completing the job is 14 days.
Limitation of Gantt Chart:
➢ This Gantt bar charts not useful for big projects, consisting of large number of
complex activities
➢ It does not show the relationship between various operations. It is very
difficult to find the sequence of various operations on the Gantt chart or the
most probable date of completion.
➢ Does to indicate the progress of work
➢ It cannot reflect uncertainty or tolerance in the duration time estimated for
various activities
➢ It simply a scheduling technique, but not effective planning tool.
Milestone chart:
Milestone chart is an improvement over Gantt chart. It has becomes a good
line between Gantt chart and PERT and CPM network. Every task represented by a
bar in Gantt‘s bar chart, is subdivided in terms event or point in time.
In the Gantt‘s bar charts bar representing an activity is divided into certain
milestones. They are identified with a major event, and consecutively numbered
such a breakdown enhances the awareness about the inter dependencies among all
milestones.
Network analysis undergone several changes and many variants exist, which
evaluate the randomness due to imperfection in all human and physical systems.
PERT and CPM continue to be very popular, in handling the basic factors like time,
cost, resources, probabilities and combinations of all these factors.
PERT AND CPM:
The two most common and widely used project management techniques that
can be classified under the title of Network Analysis are Programme Evaluation and
review Technique (PERT) and Critical Path Method (CPM). Both were developed in
the 1950's to help managers schedule, monitor and control large and complex
projects.
CPM was first used in 1957 to assist in the development and building of
chemical plants within the DuPont corporation. Independently developed, PERT
was introduced in 1958 following research within the Special Projects Office of the
US Navy. It was initially used to plan and control the Polaris missile programme
which involved the coordination of thousands of contractors. The use of PERT in this
case was reported to have cut eighteen months off the overall time to completion.
The PERT/CPM Procedure
There are six stages common to both PERT and CPM:
➢ Define the project and specify all activities or tasks.
➢ Develop the relationships amongst activities. Decide upon precedence’s.
➢ Draw network to connect all activities.
➢ Assign time and/or costs to each activity.
➢ Calculate the longest time path through the network: this is the "critical path".
➢ Use network to plan, monitor and control the project.
Finding the critical path (step 5) is a major in controlling a project. Activities on
the critical path represent tasks which, if performed behind schedule, will delay the
whole project. Managers can derive flexibility by identifying the non-critical
activities and replanning, rescheduling and reallocating resources such as manpower
and finances within identified boundaries.
PERT and CPM differ slightly in their terminology and in network construction.
However their objectives are the same and, furthermore, their project analysis
techniques are very similar.
The major difference is that PERT employs three time estimates for each activity.
Probabilities are attached to each of these times which, in turn, is used for computing
expected values and potential variations for activity times.
CPM, on the other hand, assumes activity times are known and fixed, so only one
time estimate is given and used for each activity.
PERT and CPM can help to answer the following questions for projects with
thousands of activities and events, both at the beginning of the project and once it is
underway:
➢ When will the project be completed?
➢ What are the critical activities (i.e.: the tasks which, if delayed, will effect time
for overall completion)?
➢ Which activities are non-critical and can run late without delaying project
completion time?
➢ What is the probability of the project being completed by a specific date?
➢ At any particular time, is the project on schedule?
➢ At any particular time, is the money spent equal to, less than or greater than
the budgeted amount?
➢ Are there enough resources left to complete the project on time?
➢ If the project is to be completed in a shorter time, what is the least cost means
to accomplish this and what are the cost consequences
PERT:
Programme evaluation and review technique (PERT) is a tool to evaluate a
given programme and review the progress made in it from time to time. A
programme is also called a project.
A project is defined as a set of activities with a specific goal occupying a
specific period. It may be a small or big project, such as construction of a college
building, roads, marriage, picnics etc.
It is concerned with estimating the time for different stages in such a
programme or a project and find out what the critical path is, which consumes a
maximum resources.
CPM:
Critical path method assumes that the time required to complete an activity
can be predicted fairly accurately, and thus, the costs involved can be quantified
once the critical path has been identified. Since time is an important factor, CPM
involves a trade-off between costs and time.
It involves determining an optimum duration for the project, that is, a
minimum duration that involves the lowest overall costs.
Application of PERT and CPM:
Construction of projects such as building, highways, houses or bridges:
Preparation of bids and proposals for large projects such as multipurpose
projects
Maintenance and planning of oil refineries, ship repairs and other such as
large operations
Development of new weapon systems and new products and services
Manufacture and assembly of large items such as aeroplanes or ships repairs
and other such as large operations
Simple projects such as home remodeling housekeeping or painting and so
on.
Activity: Every project consists of number of job operations or tasks which are called
activity.
Classification of activities:
1. Critical activity
2. Non-Critical activity
3. Dummy activity
Critical activity:
In a network diagram critical activities are those which if consume more than
their estimated time, the project will be delayed. It is shown with thick arrow.
Non-critical activity:
Such activities have a provision of float or slack so that, even if they consume
a specified time over and above the estimated time.
Dummy activity:
When two activities start at the same instant of time like A and B the head
event are joined by dotted arrows and this is known as dummy activity.
CPM Basic terminology:
Critical Path:
Critical path is that path which consumes the maximum amount of time or
resources. It is that path which has zero slack value.
Slack:
Slack means the time taken to delay a particular event without affecting the
project completion time. If a path has zero slack that means it is the critical path.
Slack = LFT – EFT
Earliest Start Time (EST):
It is the earliest possible time at which an activity can start, and is calculated
by moving from first to last event in the network diagram.
Earliest Finish Time (EFT):
It is the earliest possible time at which an activity can finish
EFT = EST + Duration of activity
Latest Start Time (LST):
It is the latest possible time by which an activity can start without delaying
the date of completion of the project.
LST = LFT – Duration of the activity
Latest Finish Time (LFT):
It is the latest time by which the activity must be completed. So that the
scheduled date for the completion of the project may not be delayed. It is calculated
by moving backwards.
Float:
Floats in the network analysis represent the difference between the maximum
time available to finish the activity and the time required to complete it.
The basic difference between slack and float times is a slack is used with reference to
event, float is use with reference to activity.
Floats are three types:
1) Total float
2) Free float
3) Independent float
Total float:
It is the additional time which a non critical activity can consume without
increasing the project duration. However total float may affect the floats in previous
and subsequent activities.
Total float = LST – EST or LFT – EFT
Free float:
Free float refers to the time by which an activity can expand without affecting
succeeding activities.
Free float = EST of Head Event – EST of Trail Event – Activity
duration
Independent float:
This the time by which activity may be delayed or extended without affecting
the preceding or succeeding activities in any away.
Independent float = EST of Head event – LFT of Trail event – Activity
duration (OR) Total Float – Free Float
Problems:
1)A small engineering project consists of 6 activities namely ABCDE & F with
duration of 4, 6, 5, 4, 3 and 3 days respectively. Draw the network diagram and
calculate EST, LST, EFT, LFT and floats. Mark the critical path and find total project
duration.
Note:
LST = LFT – activity duration LFT = EST + activity duration
Total float = LST – EST or LFT – EFT
Free float = EST of Head Event – EST of Trail Event – Activity duration
Independent float = EST of Head event – LFT of Trail event – Activity duration
Project crashing:
In this chapter, we will discuss the concepts of direct and indirect costs, the
relationship between project time and project cost, the concept of cost slope and how
the optimum cost and optimum duration are ensured for a given projects while
crashing.
Project costs:
Costs associated with any project can be classified into two categories
a) Direct cost:
These costs are those, which are directly proportional to the number of activities
involved in the project Ex: Raw material cost
b) Indirect cost:
In direct cost are those costs that are determined per day. Some of examples
for indirect costs are supervisory personnel salary, supplies, rent, interest an
borrowings, ads, depreciation. These costs are directly proportional to the number of
days of the duration of the project. If the project duration is reduced the indirect cost
also comes down.
Normal cost (Nc):
It is the lowest cost of completing an activity in the minimum time, employing
normal means i.e. not using overtime or other special resource. Normal time (NT): It
is the minimum time required to achieve the normal cost
Crash cost (CC):
It is the least cost of completing an activity by employing all possible means
like overtime, additional machinery, proper materials etc.
Crash time (CT):
It is the absolute minimum time associated with the crash cost.
Cost Slope:
Cost Slope is the amount that has to be spent over and above the normal
direct cost for reducing the duration by one unit of time (day, week etc.).
Cost slope is defined as the additional cost for reducing one unit of time,
assuming a given rate of increase in direct cost with a decrease in one unit of time.
Crashing of Network:
After identifying the critical path, it is necessary to identify the priority to
crash the activities by calculating the cost slope.
For reducing the duration extra expenditure to be incurred, but to save resources,
organizations keep this extra expenditure at a minimum.
When the direct cost (A) decrease with an increase in time, as the project
duration increase, the indirect cost (B) like overheads, depreciation, insurance etc.
increases. The total cost (A+B) curve is a flat U-shaped curve, with implies that only
up to a particular point (O) the crashing is economical, not beyond. The time
duration, which involves the least total cost, is the optimum duration at optimum
cost. Crashing the duration of a project may not be possible beyond a particular
point.
Problems:
1) Given the following data, work out the minimum duration of the project and
corresponding cost
Solution: