Survey Stm
Survey Stm
Hydronic Systems
Pr e - I n s t a l l a t i o n
Survey and
Checklist for
Steam Systems
INSTALLATION SURVEY – STEAM
GRAVITY
RETURN 8"
Start-up Condensate Main
Vent
28" 14"
Pressure
Difference
A
Pitch up
1" per 10 ft
6"
Return Line Loss A Water Line
Boiler
Note: Return line loss includes safety factor Maximum Main
Length 100 ft
1
INSTALLATION SURVEY – STEAM
3. Gravity Return System – condensate returns to the b) Parallel Flow Downfeed systems have a steam main
boiler only due to gravity flow. A gravity return system at the top of the system. Steam is delivered to the
works like a U-tube manometer. The pressure at the branches through downfeed risers.
boiler is higher than at the end of the steam main. And
the condensate loses pressure to friction as it flows 4. Pumped Return System – condensate is returned to
through the returns. So condensate backs up into the the boiler with a condensate unit, boiler feed unit or
return riser(s) until the weight of the water column is vacuum unit. Pumped return is used on one-pipe and
enough to balance the pressure difference and push the two-pipe systems.
condensate into the boiler. See Figure 1. 5. Vacuum System – a vacuum pump pulls a suction on
Examples of One-Pipe Gravity Return Systems: the condensate return lines, pulling air and condensate
through and pulling a vacuum on the system. Vacuum
● Counterflow (Figure 2) systems are always two-pipe.
● Parallel Flow (Figures 3 and 4)
6. Vapor System – a two-pipe gravity return system which
● Parallel Flow Upfeed (Figure 5) pushes air out and doesn’t let it back in. This causes the
● Parallel Flow Downfeed (Figure 6) system to drop to a very low pressure (from 0 to ½ psig
usually) as the steam condenses in the radiation.
a) Counterflow, Parallel Flow and Parallel Flow Upfeed
systems all have a steam main near the bottom of the
system.
Riser Riser
Main Main
Vent Vent
Main
Vent
Main
Pitch down
1" per 20 ft Vent
Air
Supply Supply
Vent
A
A Riser
Valve
Main
Figure 3: Parallel Flow Gravity, Wet Return Figure 5: Parallel Flow Upfeed Gravity
Supply Main
Main
Vent
Air
Supply Vent
Valve
Pitch down
Main
1" per 20 ft
Vent
Riser
Supply Main Downfeed
A Water Line
Riser Vent
Riser
Main
Vent
Risers A
Figure 4: Parallel Flow Gravity, Dry Return Figure 6: Parallel Flow Downfeed Gravity
Characteristics of Parallel Flow Systems:
● Steam main pitched downward away from boiler (minimum 1 inch per 20 feet)
● Condensate flows with steam, returning through risers to dry or wet return
● Steam main taken off top of boiler header between equalizer and last boiler riser
2
INSTALLATION SURVEY – STEAM
C. Gravity Return Systems 5. The steam main (and each riser) needs a Main Vent
installed near the end. ( Never install the Main Vent on a
1. Figure 1 shows how a gravity system works. The 28 inch tee at the end of the steam main. It will be quickly
dimension for the back-up of water in the returns allows destroyed by water hammer. See Figure 12. ) Use smaller
for a system steam pressure loss of ½ psig. Make sure to capacity vents on the radiators. Venting the radiators too
add additional height allowance if the system pressure fast will cause water hammer in the radiators because the
drop is more than ½ psig. condensate can’t get out past the rushing steam.
2. The height of the lowest steam carrying pipe (main or 6. The air vents must be working for the building to heat
branch) above the boiler water line is called Dimension properly. The Main Vents on the steam main and risers
A. Make sure that Dimension A is always at least 28 are important for uniform heat in the building. If they
inches on a gravity return system. If it is less, condensate don’t work, the radiator vents have to try to remove the
may back into the steam main or branches, causing water air from the steam lines. This will cause the radiators near
hammer, no-heat problems and boiler water level the boiler to heat much sooner than those further away.
problems. Make sure you pipe the new boiler so this So some areas will be hotter than others. See Figure 12
dimension is maintained. for the correct location of the Main Vents.
3. When a zone valve or trap is installed between the 7. Set the operating pressure for a gravity return system
steam supply and the condensate return lines, there is no as low as possible, usually around 2 psig or less at the
steam pressure downstream of the valve or trap when it boiler. The older steam systems were generally designed
is closed. for this. And many air vents won’t work correctly at
● So all of the boiler pressure pushes backward on the pressures over 2 psig.
return lines. This raises the condensate level about 30
inches for every psig pressure at the boiler. That would D. Pumped Return Systems
be 5 feet (60 inches) for only 2 psig at the boiler. Think
what would happen if someone cranked up the steam 1. Always install a boiler cock after the pump to allow
pressure to 5 psig or more. reducing the discharge pressure to the boiler. Pumping
● In such cases, the height of the lowest steam carrying at too fast a rate will cause spraying in a Hartford loop
pipe (main or branch) above the boiler water line is and can cause collapse of the boiler water level. The
called Dimension B. Make sure Dimension B is at discharge pressure after the valve should be around 5
least 30 inches for every psi at the boiler. psig higher than the boiler operating pressure. Figure 8
● Figure 7 shows Dimension B for a One-Pipe Gravity
shows a detail of the pump discharge piping.
System. Figure 10 shows Dimension B for a typical 2. When pumping to multiple boilers, always provide a
vapor system. separate feed for each boiler. Otherwise, water levels
won’t be maintained correctly. Either use separate
pumps or provide motorized or solenoid valves on the
feed lines. When using valves, wire the valve to open
when the boiler calls for water. Wire the valve end switch
or a relay to operate the pump when the valve opens.
Zone Valve
Steam Supplies
Vent Line
Float & Thermostatic
Boiler pressure acts on water in returns
Trap
Overflow Line
Water Line
Boiler
Gate Valve
Figure 7: Dimension B – Result of Zoning or Condensate Return Unit
Using Traps on Gravity Systems Square Head or
Check Valve Boiler Feed Unit
Boiler Cock
3
INSTALLATION SURVEY – STEAM
● Air is eliminated through the receiver tank vent. ● Usually includes a Boiler Return Trap (or Alternating
4
INSTALLATION SURVEY – STEAM
❏ compared
Check the height of the new Boiler Water Level
to the old boiler.
If new boiler water level is Higher:
Boiler
Return ● Parallel flow gravity systems – make sure that the
distance from the new water line to the lowest steam
Pipe Cap Slightly
Set In Concrete carrying pipe (Dimension A) will be at least 28 inches.
If Dimension A is less than 28 inches, you may need
to install a condensate unit or boiler feed unit plus a
float and thermostatic trap at the end of the main and
Figure
Figure10:
10:—Typical Vapor System Boiler all riser drips. See Figure 8. On some systems, less than
Figure 0:0—Return Trap and Air Eliminator 28 inches may work, but the risk is that condensate
Figure 0:0—Trap will back into the main or branches and cause water
hammer or lack of heat.
5. Vapor system radiators are equipped with special traps ● If a gravity system is fitted with traps or zone valves,
on the condensate lines to prevent steam from passing the minimum height difference from the boiler water
through. Some vapor systems also use orificed radiator line to the lowest steam carrying pipe is 30 inches per
supply valves. The orifice is sized to allow slightly less psig at the boiler. Set the boiler operating limit only
steam through than the radiator can handle. This makes high enough for the steam to reach the last radiator.
sure all the steam condenses so it can’t pass through to
the condensate line. ● Vapor systems – make sure the distance to the Boiler
Return Trap is still high enough for condensate to
6. Because the radiators have traps on the condensate lines, return by gravity. The height from the boiler water level
the pressure difference between the condensate line and to the bottom of the trap should be at least 6 inches.
the boiler is usually too much for gravity return to ● Pumped return systems – check new water line
overcome. The Boiler Return Trap compensates for against overflow line on receiver vent piping. Some
this. When the condensate backs up high enough to lift vent lines include an overflow tee at the boiler water
the boiler return trap float, a valve opens to allow steam level.
pressure from the boiler to balance the pressure in the
trap chamber. This allows condensate to flow into the If new boiler water level is Lower:
boiler by gravity. When the condensate flows out the float
drops and the cycle starts again. ● Parallel flow gravity systems – check the height of
the lowest dry returns. If any part of a gravity return
7. The Boiler Return Trap is essential to the operation of a wet return line will be above the new boiler water line,
vapor system. Always replace it with the same thing. The mount the boiler on a pedestal if possible to obtain the
only alternative is to repipe the returns, install correct height. If this can’t be done, install a false water
thermostatic traps on all the radiators, drip traps on the line (Figure 11) in order to completely cover the
steam main and risers and install a condensate unit or return. Otherwise, water hammer will occur in the
boiler feed unit. return.
● Vapor systems – water level must be at least as high
F. Installation Checklist as the loop seal pipe at the end of the main. Elevate
the boiler base if needed for this loop seal to be below
❏ Check the System History the boiler water line. If the loop seal is exposed steam
will pass through to the returns, causing water hammer
and no-heat problems.
● If the system has a history of no-heat problems,
check the air vents or traps to make sure they’re
working. Some of them may need to be replaced. The
Main and Riser vents often fail due to water hammer ❏ Lag
Check the system Condensate Return Time
because of being piped too close to the ends of mains ● If the old boiler is still operational, time how long it
or dry returns. See Figure 12. takes for the condensate return line to begin warming
● If the system has a history of water hammer, check when the boiler is started from a cold system. This is
the pipe slopes and check for sags in the steam piping the Condensate Return Time Lag. If the time lag
or concentric reducers. Also make sure drip traps are is over 15 minutes, you will probably need to install a
working. Also check to see if insulation has been boiler feed unit. The storage receiver on the feed unit
removed from steam piping and not replaced. would be sized to be at least the time lag (minutes)
5
INSTALLATION SURVEY – STEAM
Figure
Figure11
11:—Installing False Water Line to
Figure 0:0—Submerge Returns When New
Figure 0:0—Boiler Water Level is Too Low
❏ Check Air Vents and Traps
One-Pipe Systems – Check Main, Riser and
times the boiler steaming rate (GPM) times 1.33 (to Radiator Air Vents
allow for the unused storage in the receiver.
● Always use a boiler feed unit when possible. ● The steam main piping Main Vent is often piped at the
Boiler feed units compensate for large or slow very end of the main on a tee. This can lead to quick
returning systems by providing the water the boiler failure of the vent due to water hammer at the end of
needs until the condensate begins to return. the steam main. Figure 12 shows the correct way
Condensate units and gravity return systems can’t do to install the Main Vent to be sure it will last.
this. If the boiler doesn’t have enough water content ● Make sure the riser vents (at tops of risers on upfeed
to steam until the condensate returns, make-up water systems; on lower part of risers on downfeed systems)
will be added. This will cause flooding and oxygen are working. These should be high capacity vents like
corrosion (because of the oxygen carried in by the the Main Vent on the steam main piping.
fresh water). ● Check radiator air vents. They must be working for
● If you decide to convert a gravity system to pumped the radiators to heat correctly.
return, make sure you can place traps in all the places ● Make sure the radiator supply valves on one-pipe
needed—radiator traps and drip traps on mains and systems are fully open. One-pipe radiators cannot be
risers. regulated by closing down on the radiator supply valve
● If the old boiler is not operational, make a judgment because this will cause water hammer in the radiator
on the size of the system and how long it will take for since condensate has to flow back through the valve
the condensate to come back. When in doubt, against the steam flow.
recommend a boiler feed unit to the owner. A boiler
feed unit is always preferred because it responds to the Two-Pipe Systems – Check Main and Riser Drip
needs of the boiler. Traps
● The steam main and risers are usually provided with
❏ Check the System Piping drip traps, most often float and thermostatic traps.
Thermostatic traps may also be used, piped with a
cooling leg at least 5 feet long on the trap inlet.
● Check steam lines, runouts and branches for ● The drip traps serve to remove condensate from the
right amount of pitch. Lines need to pitch in the main and risers and to allow air to pass on the start of
direction the condensate is supposed to flow. If they the heating cycle and return at the end of the cycle.
don’t, water hammer and no-heat problems may ● A drip trap on the steam main or return main
occur. On counterflow systems, the pipes must pitch needs to be installed as shown in Figure 13. The piping
back toward the boiler. On parallel systems, the lines ahead of the trap provides a column of condensate
must pitch toward the returns. high enough to be sure the trap will drain the
● Check steam lines for sags. Sags allow water to pocket, condensate even with no pressure on the steam line.
causing water hammer when the system starts up. This prevents condensate from backing up in the
● Make sure there are no concentric reducers in any horizontal pipe and causing water hammer.
steam lines except where the pipe size is increasing. ● Riser and main drip traps are important in the quick
Concentric reduces cause water pocketing and water removal of air from the steam lines. They assure that
hammer when used in the wrong places. all radiator branches receive steam at the same time.
6
INSTALLATION SURVEY – STEAM
❏ toPlanthethesteam
Near-Boiler Piping and its connection
main
Figure
Figure12
12:—Correct Piping of Main Vent to ● The boiler steam header must be at least 24 inches
Figure 9: —Prevent Water Hammer Damage above the normal boiler water line (center of the gauge
glass).
● Vapor systems – check the thermostatic trap
between the end of the steam main and the return ● On boilers with multiple risers, the system steam
main. This trap allows air to flow to the condensate take-off(s) should be between the last boiler
return line and out the Air Eliminator trap. riser and the equalizer line. When the piping is
installed correctly, as shown in Figure 14, water is
Two-Pipe Systems – Check Radiator Traps separated from the steam as the steam turns up into
the take-offs. The figure also shows how water pools
● If any radiator traps have failed open, steam can under the take-off if it is between the boiler risers,
enter the condensate lines. This will cause a no-heat causing water carryover to the system.
problem on radiators higher in the system because the
pressure in the condensate lines prevents the other ● Use the number of risers off the boiler in the locations
traps from passing air and condensate. shown in the manual. Reducing the number of
risers or incorrectly placing them will cause
● If radiator traps need to be replaced, all defective the water level to be sloped inside the boiler.
traps should be replaced at the same time, and This can cause overheating of the sections and result
with the system cold. Otherwise, the new traps in cracks.
could be damaged by water hammer caused by steam
passing into the returns.
● Bear in mind that the radiators that aren’t heating may
not have defective traps. Their traps may just be
prevented from working because traps lower in the
system are allowing steam to enter the condensate
lines. When a trap fails open, its radiator usually heats,
but other radiators above it don’t.
● Thermostatic traps can be tested by checking the
temperature of the condensate line after the trap. The
outlet temperature of a thermostatic trap should be at
least 10o F cooler than the steam. If the outlet of the
trap is too hot, either the trap tested is bad or one near Static Head
it is bad. This temperature method can be done with
thermal markers (such as Tempilstiks). This method
may work in most cases, but the best way to test the
trap elements is in a separate testing station. The
stations can be piped off the steam line in boiler room.
7
INSTALLATION SURVEY – STEAM
● The boiler header must be offset to provide ● The near-boiler piping must be done as shown
swing joints. The swing joints prevent the expansion in these instructions. This piping is designed to
and contraction of the header from damaging the assure dry steam is provided to the system. Undersized
boiler. pipes and steam take-offs in the wrong locations can
cause large amounts of water to be carried into the
● Size the boiler equalizer line as recommended in these system (Figure 14). The result would be water hammer
instructions. This assures the most stable water level and damage to system traps and vents. It will also
possible and prevents water from spraying up into the cause make-up water to be added to the system due
header. to frequent low water conditions in the boiler.
● We recommend the use of a Hartford loop even on ● Vapor systems – the two check valves below the
pumped return as an added precaution against water Boiler Return Trap are essential to the system. They
leaking back through the check valve into the receiver must be piped as required for the system and must be
tank. The equalizer sizes recommended should be working correctly. Maintain the correct positions of the
adequate for pumped return, provided the pump rate Boiler Return Trap and Air Eliminator Trap relative to
is not excessive. the boiler water line.
EQUALIZER
Water separates when the
Wate
steam turns upward
HEADER CONNECTIONS
FOR MULTIPLE BOILER RISERS EQUALIZER
Wate
Water pools under the steam
take-off, causing heavy carryover
of water to the system
Figure14:—LLocation
Figure 14: One-Pipeof
Pumped
Steam Return System
Take-Off on Multiple Riser Boiler
8
Steam Survey
Hydronic Systems
Pr e - I n s t a l l a t i o n
Survey and
Checklist for
Steam Systems
PB HEAT, LLC
131 S. CHURCH STREET • BALLY, PA 19503