RFSM2000-Installation of Monolithic Refractories
RFSM2000-Installation of Monolithic Refractories
PIP RFSM2000
Installation of Monolithic Refractories
PURPOSE AND USE OF PROCESS INDUSTRY PRACTICES
In an effort to minimize the cost of process industry facilities, this Practice has
been prepared from the technical requirements in the existing standards of major
industrial users, contractors, or standards organizations. By harmonizing these technical
requirements into a single set of Practices, administrative, application, and engineering
costs to both the purchaser and the manufacturer should be reduced. While this Practice
is expected to incorporate the majority of requirements of most users, individual
applications may involve requirements that will be appended to and take precedence
over this Practice. Determinations concerning fitness for purpose and particular matters
or application of the Practice to particular project or engineering situations should not
be made solely on information contained in these materials. The use of trade names
from time to time should not be viewed as an expression of preference but rather
recognized as normal usage in the trade. Other brands having the same specifications
are equally correct and may be substituted for those named. All Practices or guidelines
are intended to be consistent with applicable laws and regulations including OSHA
requirements. To the extent these Practices or guidelines should conflict with OSHA or
other applicable laws or regulations, such laws or regulations must be followed.
Consult an appropriate professional before applying or acting on any material
contained in or suggested by the Practice.
This Practice is subject to revision at any time by the responsible Function Team and will
be reviewed every 5 years. This Practice will be revised, reaffirmed, or withdrawn.
Information on whether this Practice has been revised may be found at www.pip.org.
PIP will not consider requests for interpretations (inquiries) for this Practice.
PRINTING HISTORY
PIP RFSM2000
Installation of Monolithic Refractories
Table of Contents
4.6 Water-Contaminated Refractory........ 5
1. Introduction................................. 2 4.7 Preparation for Lining Installation...... 6
1.1 Purpose ............................................. 2 4.8 Application Conditions ....................... 7
1.2 Scope................................................. 2 4.9 Mixing of Castable Refractory ........... 8
4.10 Dry Gunning .................................... 11
2. References .................................. 2 4.11 Wet Gunning.................................... 15
2.1 Process Industry Practices (PIP)....... 2 4.12 Casting ............................................ 18
2.2 Industry Codes and Standards.......... 2 4.13 Ramming ......................................... 20
4.14 Interruption of Application................ 22
3. Definitions ................................... 3 4.15 Curing .............................................. 23
4.16 Heat Dryout ..................................... 25
4. Requirements.............................. 4 4.17 Repairs ............................................ 26
4.1 General .............................................. 4 4.18 Shipping and Storage ...................... 27
4.2 Monolithic Refractory Lining Appendix A – Lining Thickness
Anchors.............................................. 4 Tolerance......................................... 29
4.3 Surface Preparation and Coating ...... 4 Appendix B – Dryout Guidelines for
4.4 Prequalification of Materials and Monolithic Castable and Plastic
Installation Personnel ........................ 5 Refractories (Notes 1 and 2) ........... 30
4.5 Water Quality and Testing ................. 5
1. Introduction
1.1 Purpose
This Practice provides the requirements for the installation of monolithic refractory
linings.
1.2 Scope
This Practice provides the requirements for the installation of monolithic refractory
linings in process equipment and piping. Installation methods include preparation,
application, curing, and repair of the linings. This Practice also covers heat dryout of
newly installed or repaired linings.
2. References
Applicable parts of the following Practices, industry codes and standards, and references shall
be considered an integral part of this Practice. The edition in effect on the date of contract
award shall be used, except as otherwise noted. Short titles will be used herein when
appropriate.
3. Definitions
With the exception of the terms listed in PIP RFSM1000 and PIP RFTM1000, terms used in
this Practice are defined in accordance with ASTM C71 and API RP 936 (Section 1.2 and
Appendix A). If a definition, as used in this Practice, differs from the one listed in the
reference documents, the modified definition is included in the following:
low cement: Refractory castable containing 1% to 2.5% total lime (CaO) on a calcined basis
lubricant: Bentonite clay or a polymer-based additive used to promote low friction flow of
refractory castables during wet gunning. The lubricants are water-based admixtures that have
minimal effect on the physical properties of the applied materials.
no cement: Refractory castable containing 0% to 0.2% total lime (CaO) on a calcined basis
owner: Party who owns the facility wherein the refractory lining is to be used
purchaser: Party who awards the contract to the supplier. The purchaser may be the owner or
the owner’s authorized agent.
retardant: Chemical compounds used to prevent flash setting of the material and possible
damage to the equipment or delivery system
rigidizing agent: Chemical compounds used to promote controlled rapid setting of wet gun
refractories. The rigidizing agent, also known as an accelerant, is delivered in a dry form,
mixed onsite in the original container, and added to the refractory at the wet gun nozzle.
ultra-low cement: Refractory castable containing 0.2% to 1% total lime (CaO) on a calcined
basis
4. Requirements
4.1 General
4.1.1 Conflicts, Exceptions, Substitutions, and Deviations
4.1.1.1 All conflicts between the referenced documents and this Practice
shall be submitted in writing to the purchaser for clarification and
resolution before proceeding.
4.1.1.2 All exceptions, substitutions, and deviations to the requirements of
this Practice and in referenced documents shall be approved by the
purchaser.
4.1.2 Regulations and Material Safety Data Sheets (MSDSs)
4.1.2.1 Refractory materials shall comply with all applicable federal, state,
and local codes and regulations on storage, handling, safety, and
environmental requirements.
4.1.2.2 Latest issue of the refractory manufacturer's product data sheets,
application instructions, and MSDSs shall be available at the
installation site and complied with during the installation of
monolithic refractory linings.
4.1.3 Notification
Purchaser’s inspector(s) shall be given adequate notice before the start of all
work and hold points, so the inspector(s) can witness the work.
4.1.4 Preinstallation
A refractory installation procedure including surface preparation, curing, and
heat drying of the completed lining system shall be submitted to the
purchaser for review and approval before the start of installation. This
procedure shall constitute an inspection hold point in accordance with
PIP RFTM1000-F.
4.7.6 Overspray
4.7.6.1 All anchors shall be cleaned of spatter and overspray before
refractory is installed.
4.7.6.2 For multilayer linings, anchors for the hot-face layer shall be
protected and free of all backup refractory material before
application of the hot-face layer.
4.7.7 Anchor Tips
If anchor tip coverings as defined in PIP RFSA1000 are required, placement
of the coverings shall be confirmed immediately before refractory placement.
This shall constitute an inspection hold point in accordance with PIP
RFTM1000-F.
4.7.8 Equipment Cleaning
4.7.8.1 Mixers, guns, conveyors, hoses, and all other equipment shall be
thoroughly cleaned before use.
4.7.8.2 Equipment shall be cleaned at each material change, shift change,
and more often if buildup of castable takes place.
4.7.8.3 Cleaning is required between each mix of Type 9 refractory
(PIP RFSM1000, Appendix A).
4.7.8.4 For low-moisture (low-cement) mixes and other refractories sensitive
to water content, the mixer shall be thoroughly washed and excess
water removed after each batch. For other mixes, the cleaning
interval shall be such as to prevent buildup of refractory materials on
the mixer internals (including the drum).
4.7.8.5 All tools used in mixing, transporting, and applying the refractory
lining shall be cleaned after each batch and kept free of all
deleterious materials.
4.7.9 Site
Work area shall be kept clean and protected to ensure that lining installation
can proceed in an orderly manner without incorporating dirt, debris, rain, or
other deleterious material into the lining.
8. Shot Boards
a. Use of shot boards to define the extent and thickness of each
area to be lined (e.g., band) may be allowed if approved by
the owner.
Comment: Use of shot boards is to define the top of each
band (the previous band defines the bottom) and
the starting point for gunning. If shot boards are
used, proper gunning technique is critical to
avoid rebound entrapment or voids in the
difficult-to-gun areas of shot boards.
b. Shot boards shall be placed between anchors and held in
place to ensure that nothing (wire, bolts, etc.) projects into or
becomes embedded in the lining, and a smooth lining surface
is produced.
4.12 Casting
4.12.1 General
4.12.1.1 Amount of water used in casting applications shall be within ±5%
of the amount used in the prequalification mockup in accordance
with PIP RFTM1000, Paragraph 4.5.3.2, and shall be within the
water range described in PIP RFSM1000, Paragraph 4.1.5.
4.12.1.2 Water addition shall be based upon the nominal weight marked on
each refractory container. The nominal weight marked shall comply
with the requirements of PIP RFSM1000, Paragraph 4.4.2.3.
4.12.1.3 Refractory shall be deposited in a manner that minimizes the
segregation of materials. The refractory shall be deposited as nearly
as possible to the final position. The vertical free fall shall not
exceed 6 feet (2 meters).
4.12.1.4 Work shall continue until an entire section has been completed.
4.12.2 Forming
4.12.2.1Forms shall be required if installing refractories by casting, vibration
casting, and self-leveling methods.
4.12.2.2Forms shall be fabricated from steel or wood, rigidly constructed,
and watertight.
4.13 Ramming
4.13.1 Thin Erosion-Resistant Linings
4.13.1.1 Thin erosion-resistant linings shall be 1.5 inches (37 mm) thick or
less.
4.13.1.2 Castable
1. Refractories shall be mixed in a reciprocating orbital mixer (e.g.,
Hobart mixer). The mixer shall have stainless steel paddles and
bowls.
2. Metal fiber reinforcement shall be used only if specified, and the
fibers shall be in accordance with PIP RFSA1000.
3. Metal fibers shall be introduced into the mixer immediately
following the introduction of the dry refractory material and
before the addition of any mixing water other than
predampening.
4. Fibers shall be introduced in a manner that ensures uniform
distribution throughout the refractory mix without
agglomeration.
a. Preweighed lots of fibers shall be introduced into the
refractory mix (with the mixer operating) through the use of
a screen or other device to assure that the fibers fall as a rain.
b. If a screen is used, the maximum opening dimension for the
screen shall not exceed 1/2 inch (13 mm) square.
c. Mixer shall operate for 30 seconds to 1 minute after the
metal fibers are added before the addition of water.
5. Mixing shall be strictly in accordance with the manufacturer’s
recommended procedures using water levels determined during
4.14.7 If installation is halted for the day, all openings in the item being lined shall
be covered, closed, and sealed.
4.14.8 Immediately before resuming refractory application, the exposed surface of
the refractory lining to which a bond must be made shall be cleaned of all
loose refractory material, roughened, and thoroughly wetted with water or
coated with a membrane curing compound. Alternatively, a bonding agent
such as a weak phosphoric acid solution or phosphate-bonded mortar may be
used.
4.15 Curing
4.15.1 Curing of Castable Linings
4.15.1.1 Hydraulic and chemically bonded castable linings shall be allowed
to cure at no less than 50°F (10°C) for a minimum of 24 hours
before the initial heating of the lining.
4.15.1.2 Chemically bonded castable refractory lining surfaces shall remain
uncovered and free from contact with moisture during the curing
period.
4.15.1.3 Curing of hydraulically bonded castables shall be performed in
accordance with one of the following methods as approved by the
owner:
1. Membrane-Curing Compound
a. Curing compound shall be a solution of resin and
hydrocarbon base, membrane-forming (nonreactive), and in
accordance with ASTM C309.
b. Curing compound shall be nonflammable and nontoxic, and
shall contain a factory-added pigmentation that allows for
complete visual inspection of coverage.
c. All curing compounds shall be approved by the owner.
d. Curing compound shall be applied to all exposed surfaces
before the surface is dry to touch. No part of the lining shall
be allowed to air dry more than
2 hours before the application of the curing compound.
e. A one-coat application of curing compound of sufficient
thickness to completely cover the exposed surfaces of the
lining shall be used.
f. Curing compound shall be allowed to dry tack free before
lining is installed in an adjoining area.
g. Adequate ventilation shall be provided during the
membrane-curing compound application and curing period.
2. Water Mist
a. Exposed surfaces of the lining shall be wetted with a fine
water mist. No part of the lining shall be allowed to air dry
4.16.16 If steaming is observed during any hold period, the hold period shall be
maintained until steaming ceases. The remainder of the heating schedule
shall be followed without any make up of the lost time.
4.17 Repairs
4.17.1 General
4.17.1.1 Areas deemed defective in accordance with PIP RFTM1000,
Section 4.7, shall be repaired.
4.17.1.2 Sections of the lining below the minimum thickness (in accordance
with the applicable lining design data sheets of PIP RFEG2000)
shall be cut out entirely and replaced.
4.17.1.3 In a multilayer lining, the hot face shall be removed without
removing or disturbing the backup.
4.17.1.4 Additional material shall not be placed over previously applied
material to build up to the required thickness.
4.17.1.5 Lining installed over a field joint shall follow the same procedures
as a repair.
Comment: If the refractory used for repair differs from the
refractory of the adjacent lining, the installation
procedure, curing, and dryout requirements also may
differ.
4.17.2 Repair Procedures
4.17.2.1 General
1. All proposed materials and methods of repair shall be approved
by the owners before the repair is made.
2. Immediately before placement of the new refractory, the sound
refractory material adjacent to the repair area shall be cleaned of
debris, roughened, and completely prewetted with potable water,
membrane curing compound, phosphate-bonded mortar, or a
weak phosphoric acid.
3. Anchors and shell shall be cleaned of refractory or other debris
and new caps installed on the anchor tips where applicable.
4. If the anchors or the attachment weld are damaged, the anchor
shall be replaced in accordance with PIP RFSA1000.
4.17.2.2 Monolithic Lining
1. With the exception of surface bubble defects, unacceptable
refractory lining shall be cut at a right angle to the shell and
laterally to the acceptable lining and removed. The shell shall not
be damaged.
2. Any areas removed for repair shall have at least one anchor
completely exposed. If not, a new anchor shall be installed. The
4.18.3 Equipment shall be reinforced using spiders, truing rings, braces, etc. to
maintain the equipment shape and prevent damage to the refractory linings
during handling and shipment.
4.18.4 All openings shall be sealed, and a means shall be provided to keep
refractory linings dry during shipping, storage, and post-erection before the
startup.
4.18.5 Proper supports, external bracing, rigging, and lifting techniques shall be
used to prevent flexing of the equipment during handling, shipping, and
erection.
Tolerance
Component
inch mm
Dry/Wet Gunned -0, +1/4 -0, +6
Handpack ±1/4 ±6
Floor ±1/4 ±6
Notes:
1. Erosion-resistant linings 1.5 inches (37 mm) thick or less
2. Plastic refractory linings greater than 1.5 inches (37 mm) thick
Types 5, 6, 7
Medium/Moderate Weight and 50˚F (28˚C)
Yes Yes 1200˚F (650˚C)
Fused Silica Erosion-Resistant per hour
Castables
Types 8, 9
25˚F (14˚C)
Erosion-Resistant Yes None 1200˚F (650˚C)
per hour
Dense Castables
Type 11
25˚F (14˚C)
Chemically Inert Yes Yes 1200˚F (650˚C)
per hour
Dense Castable
Notes:
1. Dryout guidelines are for single-layer castable or plastic refractories up
to 5 inches (125 mm) thick. Multicomponent or thicker refractories may
require slower heating rates.
2. Dryout rates are based on refractory materials without organic fiber or other
agents that permit faster heating rates.
3. PIP Type refers to monolithic refractory types in accordance with
PIP RFSM1000, Appendix A.
4. All hold times are 1 hour per inch (25 mm) thickness of refractory.
5. If steaming is observed during any hold period, the hold period shall be
maintained until steaming ceases.
6. Use the operating temperature if less than 1200˚F (650˚C).