Government-Extension-to-the-PMBOK-Guide
Government-Extension-to-the-PMBOK-Guide
br/government-extension-pmbok/
Government Extension
to
EXPOSURE DRAFT
October 2001
CONTENTS
Contents ........................................................................................................................................... i
Preface............................................................................................................................................. 1
1. Introduction............................................................................................................................. 3
2. The Project Management Context .......................................................................................... 7
3. Project Management Processes............................................................................................... 9
4. Project Integration Management........................................................................................... 10
5. Project Scope Management................................................................................................... 13
6. Project Time Management.................................................................................................... 15
7. Project Cost Management ..................................................................................................... 17
8. Project Quality Management ................................................................................................ 20
9. Project Human Resource Management................................................................................. 23
10. Project Communications Management ................................................................................. 27
11. Project Risk Management ..................................................................................................... 31
12. Project Procurement Management........................................................................................ 37
Glossary ........................................................................................................................................ 43
Appendix A. Government Extension Team.................................................................................. 45
Appendix B: Notes........................................................................................................................ 47
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
PREFACE
Appendix E of A Guide to the Project Management Body of Knowledge (PMBOK® Guide – 2000 Edition)
recognizes that there are generally accepted best practices for particular types of projects. It suggests that application
area extensions be written for each project type. This is the exposure draft of an application area extension for
government projects.
Please note that this is strictly an extension to the PMBOK® Guide – 2000 Edition. This means that there are limits
on what can be included. These are:
A. INTRODUCTION: Describe features of the chapter's subject that are peculiar to government projects.
B. LEVEL 4 ITEMS: Apart from the introductions, changes to Chapters 4 through 12 should be at level 4.
(Examples: The first level 4 item in Chapter 4 is 4.1.1.1 “Other Planning Outputs.” The last level 4 item in Chapter
12 is 12.6.3.2 “Formal Acceptance and Closure.”) You may add to the discussion of an existing level 4 item,
describing features that are peculiar to government projects. You may also add new level 4 items that are peculiar to
government projects. And you may state that particular level 4 items in the PMBOK® Guide – 2000 Edition do not
apply to government projects.
A project work breakdown structure was prepared in September 1999, and the PMI Standards Member Advisory
Group approved a project charter in January 2000.
The team began to assemble in August 1999, mainly in response to articles in the SIG newsletter. Team members
are listed in Appendix A. All team members are volunteers, and they come from eight countries. The team includes
project managers from all levels of government—national, regional, and local. They manage projects in several
fields, including agriculture, education, energy, health and human services, labor, and transportation.
Each team member was asked to join one or more of the twelve chapter teams, and a lead author was assigned to
each chapter. Lead authors were responsible for the successful completion of a particular chapter and wrote the first
draft of the chapter. Co-authors contributed ideas and text to the chapter.
Draft 1 of each chapter was submitted to the full team as it was completed. This took place between July and
November 2000. Team members responded with 123 recommended amendments. The team evaluated these
proposed amendments, approved ninety-one, and decided that thirty-two were unpersuasive. Draft 1 with the ninety-
one amendments became Draft 2.
In December 2000, Draft 2 was submitted to all the members of the Government SIG with known email addresses.
SIG members responded with 173 recommended amendments. A core team evaluated these proposed amendments,
approved 153, and decided that ten were unpersuasive. Draft 2 with the 153 amendments became Draft 3. After
editorial corrections Draft 3 became the exposure draft.
Draft 3 was submitted to a panel of Subject Matter Experts in July 2001. The panel reviewed the draft, gave it a
generally positive review and recommend that it proceed to the exposure draft. Panel members proposed thirteen
specific amendments, and the team incorporated eleven of these into the document.
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
1. INTRODUCTION
A Guide to the Project Management Body of Knowledge1 (PMBOK® Guide – 2000 Edition) describes the principles
of project management that are generally accepted for all types of projects. Throughout this document, A Guide to
the Project Management Body of Knowledge will be referred to as the PMBOK® Guide – 2000 Edition. All
references are to the PMBOK® Guide – 2000 Edition.
This extension is a supplement to the PMBOK® Guide – 2000 Edition. It describes the generally accepted
principles for government projects that are not common to all project types.
This chapter defines and explains several key terms and provides an introduction to the rest of the document. It
includes the following major sections.
1.1 Purpose of this Document
1.2 What makes Government Projects Unique?
1.3 What is Project Management?
1.4 Relationship to Other Management Disciplines
1.5 Programs of Projects
1.6 Levels of Government
1.7 The PMBOK® Guide – 2000 Edition Processes—Inputs, Tools and Techniques, and Outputs
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
project managers are part of the executive.5 Most project managers report to members of the executive staff. On
large projects or in small governments they may report directly to the chief executive.
1.7 THE PMBOK® GUIDE – 2000 EDITION PROCESSES—INPUTS, TOOLS AND TECHNIQUES,
AND OUTPUTS
The PMBOK® Guide – 2000 Edition describes the inputs, tools and techniques, and outputs of each project
management process. For each process it includes a table that lists these elements. This document includes similar
tables. In each table, the elements have this format:
• Elements that remain unchanged from the PMBOK® Guide – 2000 Edition are shown in plain text.
• New items are shown in Bold Italics.
• Changed elements are shown in Italics.
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
https://analisederequisitos.com.br/government-extension-pmbok/
LIVRO GRÁTIS!
SCRUM
KANBAN E
SCRUMBAN
DOWNLOAD GRÁTIS
Mais livros e conteúdos gratuitos disponíveis em:
https://analisederequisitos.com.br/downloads
MAIS LIVROS GRATUITOS
Engenharia de Requisitos:
software orientado ao negócio
O livro "Engenharia de Requisitos: Software Orientado
ao Negócio" oferece uma abordagem prática e
abrangente para a engenharia de requisitos.
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
10
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
.3 Organizational policies
• Devolved powers. As a general rule, public executive bodies only have such specific powers as the
representative body gives to them. Actions outside these powers are ultra vires (beyond the power). For
example, though a public body may own land on which to carry out its functions, it may not automatically have
the power to sell, or benefit from the sale proceeds, of that land.
• Approval controls. Different branches or tiers of government—local, national, and supra national (e.g. European
Union)—may have separate formal requirements for approval of phases of the project. In principle these are no
different to the financial controls any organization would exert. Project managers should, however, make
certain they understand the potentially diverse requirements for approval.
11
.5 Project management
information system
12
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
5.1 INITIATION
The PMBOK® Guide – 2000 Edition says, “Initiation is the process of formally recognizing that a new project exists
or that an existing project should continue into its next phase (see Section 2.1 for a more detailed discussion of
project phases).”12 It is important to remember that this process is repeated for each phase. An officer in the
executive branch generally initiates the proposal phase. The initiation of later phases is determined by the rules set
by the representative body (see Sections 1.2.1, 1.5, and 2.1).
The PMBOK® Guide – 2000 Edition lists typical reasons for initiating a project.
• A market demand.
• A business need.
• A customer request.
• A technological advance.
• A legal requirement.
• A social need.
Each of these may occur on government projects, but they do not adequately describe the main reasons for
initiating government projects. Government projects are initiated mainly for the health, safety, and welfare of the
constituents.
• Health needs (such as mass immunization, hospitals, sanitation, water purification, research, and food and
pharmaceutical administration).
• Safety needs (such as defense, counter-terrorism, police, fire protection, disaster prevention and mitigation,
prisons, justice, foreign policy, land mine inspection, and drug trafficking control).
• Welfare, socioeconomic, and environmental needs (such as participatory long-range planning projects, poverty
alleviation projects, education and schools, water supply, transportation and roads, energy, social security,
environmental protection, and parks and recreation).
Government projects may be initiated in order to achieve a specific policy goal of the administration, for
example a reduction in budget deficit, or the achievement of essentially political goals, such as the nationalization or
privatization of utility companies.
13
.2 Strategic plan. See Section 5.1.1.2 of PMBOK® Guide – 2000 Edition and the discussion of Quality Policy in
Section 8.1.1.1 of this document.
Scope definition and management is often exceptionally difficult for government projects, since they frequently
have many masters. The scope must not only satisfy the plans and objectives of the performing organization but also
the various regulatory organizations (see discussion in Section 2.2), some of which may provide portions of the
project funds. The goals of these parties are sometimes in conflict. Thus, the project manager must take extra care to
ensure all parties are in agreement, to minimize problems downstream.
.3 Project selection criteria. Section 5.1.1.3 of PMBOK® Guide – 2000 Edition discusses the need to meet
management concerns such as financial return, market share, and public perceptions. Government project selection
criteria are characterized by nonprofit and socially driven characteristics that satisfy the needs and requirements of
the constituents.
14
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
funding if work moves from one fiscal year into the next. Fortunately, funds are generally appropriated to programs
rather than individual projects (see Section 1.5). Effective program managers can often move funds between projects
to minimize the overall loss of funding. However, some very large projects in terms of their funding levels keep
their budgetary identity and no movement of funds to or from that project can be processed without the clearance of
the elected government or whomever the elected government delegates that authority.
.11 Line-item projects. These projects are added to the budget by the representative body on a project-by-project
basis. They often are not supported by a proposal from the executive (see Section 2.1.1). The representatives set
their schedules and budget. As a result, these projects often have poorly defined scopes, inadequate funding, or
unreasonable schedules. The project manager must expeditiously work with the customer to determine the scope of
work and the appropriate acquisition strategy to accomplish the project within the time constraints.
16
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
• Defined elements of work. Each program bears the cost of its portions of the project.
• Defined contribution. Some programs contribute a fixed amount, with one program funding the balance. The
balance is generally funded by the program with the largest contribution. This program bears the risks
associated with cost overruns or underruns.
• Percentage split. Each program funds a percentage of the project.
To the representative body, defined elements of work appears to be the best choice because they pay only for the
elements that they want. However, this method requires a detailed manual accounting system because an automated
system can seldom discern which elements are being worked on. Such a manual process is prone to inaccuracy. It
requires a large commitment of time for reporting and auditing. The increased cost generally outweighs the slight
increase in the accuracy of charges.
The defined elements of work method also requires a far more detailed work breakdown structure (WBS) than
the other two methods. To capture each program’s portion accurately, the WBS must be defined to a level where
each program’s portion maps uniquely to a set of WBS elements. This level of detail is generally far greater than
what is needed to manage the project.
The defined contribution does not require an amendment to the WBS. Typically, it is established as a
“percentage split.” When the limit is reached for the fixed programs, the split is changed to a 100 percent payment
by the risk-bearing program. If the project is completed within budget, the change never occurs.
Percentage split is the simplest approach. The contribution of each program is estimated at the start of the
project. Based on that estimate each program bears its percentage of the project cost. As programs fund many
projects, variances on one project will probably be counterbalanced by opposite variances on other projects.
.3 Matching funds. Matching funds are a form of split funding by program. When governments “devolve” project
selection to lower representative bodies, they often require those lower bodies to pay a portion of the project cost.
(See the discussion of devolution in Section 1.5). This assures that the lower government is committed to the project.
Matching funds may be apportioned on a percentage basis or as a defined contribution.
.4 Split funding by fiscal year. The annual budget cycle is discussed in Section 6.4.1.6. If a project begins in one
fiscal year and ends in another, it will need funding from the budget of each fiscal year in which there is project
work. This split funding by fiscal year can be decreased through obligations, if the representative body allows them
(see Section 6.4.2.7).
Funding by fiscal year requires that project managers plan their work by fiscal year with great care. This is
particularly true in large governments with many levels of review. In the United States government, for instance, the
President submits a budget to Congress in January for the fiscal year that begins on October 1. Before this, the
executive staff must assemble all the supporting data for the budget. They must also agree on priorities for the
allocation of limited funds. To be included in the January budget, the project manager must have project plans
completed by June of the previous year. This is more than fifteen months before the start of the fiscal year. Once a
budget request is submitted, changes are difficult to effect.
Fortunately, funds are generally appropriated to programs rather than individual projects (see Section 1.5).
Program managers can use funds from projects that underrun their fiscal year budgets to fund the overruns in other
projects. These are fiscal year variances, not variances in the total cost of the project.
Private sector firms could not survive with the government budget process. They must respond quickly to
market challenges from their competitors. Without a quick response, they will lose business and may descend into
bankruptcy. Large private firms therefore delegate the detailed budget decisions to smaller cost centers. The
manager of each cost center has clear performance measures—make a profit, satisfy customers so that the firms gets
return business, and obey the law. In government, there is no profit motive and customers seldom have the option
not to return.
Paradoxically, fiscal year funding can have an effect that is opposite to what is intended. Annual budgets are
intended to establish limits on the executive. In operational areas, they achieve this goal. (For a discussion of
operations and projects, see section 1.2 of the PMBOK® Guide – 2000 Edition.) On projects, they often fail. The
executive must request budgets for each project in fiscal year slices. This focus on fiscal years can draw attention
away from the overall multi-year cost of the project. The representative body may not see this overall cost. Projects
can incur large overall cost overruns without the representative body becoming aware of this fact. Representative
bodies need to be aware of this problem and require multi-year reports. Project managers should provide multi-year
reports to their project sponsors.
Government accounting standards often fail to recognize the peculiar needs of multi-year projects. Project
managers should keep records on the entire project that are reconciled with the government's official accounts.
18
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
Some governments have begun to adopt performance-based budgeting as an alternative to the rigid annual
budget process. This is discussed in Section 8.1.2.6.
.5 Obligations. Obligations are discussed in Section 6.4.2.7. They are a tool to minimize split funding by fiscal year.
They can be used only where there is a contract with a private sector firm to provide portions of the product.
.6 Counterpart Funding. This is also called “Counterfunding”. It involves funding from the private sector, and is an
option in “developing” countries, which will not have enough funds for many years to meet all the basic
infrastructure needs of their population.
19
20
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
21
22
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
23
hiring is authorized, the process can take several months. Because project managers do not choose their staff, the
project manager must create a viable, performing team from what is given. Project managers need to master
teambuilding skills, understand the different personality types, and motivate these individuals to produce a
functioning team.
.5 Preferences and restrictions. Governments will often give employment preferences to a particular population
group. These may be ethnic groups, people who are deemed to be disadvantaged (e.g., women and disabled people),
people to whom the voters feel indebted (e.g., military veterans), or citizens. There may also be restrictions based on
security requirements.
.6 Freedom of information. Project managers may be constrained in what they may keep confidential. Public
disclosure laws in many countries give citizens the right to view almost all governmental records, with a few non-
absolute exceptions for secrecy and invasion of privacy. Project managers might find themselves required to make
public memos from meetings in which appraisals of staff performance or interpersonal problems were discussed.
24
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
25
• Civil service tenure requires that functional managers must have budgets to pay their staff. This prevents the
project manager from having full control of the project budget.
Collocation is a tool that can overcome many of these problems. It is used in combination with a balanced
matrix organization. Each project has an assigned work area, and employees sit together in that area while they are
working on the project. This ensures that they communicate with other team members, particularly with the full-time
project manager. Although the employee reports to their functional manager and the project manager does not
control their salary, employees clearly identify with the project team and are committed to the success of the project.
Collocation is also called a tight matrix.18 On small projects, a war room can serve some of the functions of
collocation. This is a room where the team congregates and posts schedules, updates and other project data.19
.6 Project Management Office. Section 2.3.4 of the PMBOK® Guide – 2000 Edition introduces the project office.
The terms Project Management Office, Project Office, Program Office, and Program/Project Management Office are
used by different organizations to describe units that provide a variety of support functions to project managers. An
office of this type is particularly in a government organization that is characterized by strong functional structures. It
can be helpful in project and program reporting, integrating the activities of functions, mentoring project managers,
and leading further process improvements.
26
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
27
needs to be identified and mitigated, such as project national culture implications on the project, possible project
team members, the applicable laws of the project country, and so on.
28
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
These are all produced on government projects, and the following output has particular applications in government.
.1 Project records. Project records may include correspondence, memos, reports (written or electronic), recorded
records, presentations of content, and any other document describing and detailing the project. This information may
become available to the public, or be made available via Freedom of Information Act requests (or similar legislation,
depending on the government sponsoring the project).
29
30
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
Government projects follow the same processes, but their focus is on social, environmental, and political risk as
well as on financial risk. Many government projects would be abandoned if they were subjected only to the private
sector risk analysis process. A well-known example is the program to place a man on the Moon and bring him back
again. As a private sector project, this would have been completely unacceptable. It carried immense risks and had
virtually no potential for profit. As a government project, however, it was an enormous success. (Success is judged
by the stakeholders—in this case, the taxpayers and voters in the United States of America and their elected
representatives.)
31
32
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
the NIMBY phenomenon (“Not in my back yard”). National and regional voters may want a facility (e.g., a
solid waste disposal facility), but local voters oppose it.
• Inconsistencies in the will of voters. For instance, voters may want to commute to work alone each day in their
private cars, but also want to have no air pollution.
• Changes over time. Voters may support a project in its early stages, but oppose it later as its effects become
better known.
34
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
35
36
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
37
DOWNLOAD GRÁTIS
https://analisederequisitos.com.br/government-extension-pmbok/
MAIS LIVROS GRATUITOS
Engenharia de Requisitos:
software orientado ao negócio
O livro "Engenharia de Requisitos: Software Orientado
ao Negócio" oferece uma abordagem prática e
abrangente para a engenharia de requisitos.
38
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
• Full and open competition after exclusion of sources. Under this contracting method, agencies are allowed to
exclude one or more sources from competing. A set-aside for a small business or a disadvantaged firm is an
example of this method.
• Other than full and open competition. This is used when there is only a single contractor that can accomplish
the work, by reason of experience, possession of specialized facilities, or technical competence, in a time-frame
required by the government. This type of contract is also known as “sole-source” and requires a written
justification to be approved by an authorized executive.
6. Eminent domain. This is a particular form of sole-source or other than full and open competition. It has been in
use for thousands of years, and is probably the oldest form of government procurement. The government may take
possession of private property when this is in the best interests of the public. Eminent domain is used most often to
take possession of real property. The government is generally required to pay just compensation for the property.
Such compensation is required in Roman Law, the Magna Carta, the Code Napoleon, and the Fifth Amendment of
the United States Constitution.
.7 Multiple award schedules. In many jurisdictions, this type of contract is fairly new. It often requires specific
legislation. It is used when there is a generally accepted “reasonable price” for a good or service. Contractors submit
their schedule of rates to the government procurement office. If these are approved, government agencies may buy
goods and services at the published rates without a separate competition. This method is often adopted in response to
W. Edwards Deming’s fourth point for management, “End the practice of awarding business on the basis of price
tag. Instead, minimize total cost. Move toward a single supplier for any one item, on a long-term relationship of
loyalty and trust.”27
.8 Degrees of qualification. All government contracts require that the contractor have minimum qualifications that
are listed in the solicitation documents. Once these minimum qualifications are met there are several degrees of
qualification that can be considered. There are some common approaches.
• Lowest qualified bidder. This is probably the most common approach. Contractors’ proposals are evaluated to
ensure that they meet minimum qualifications. Then the cost proposals of the qualified contractors are opened
and the lowest qualified bidder is accepted. The level of qualification may vary. On construction contracts, the
minimum qualification is generally a contractor’s license and a performance bond. On professional service
contracts, there is generally a more detailed evaluation of the contractors’ qualifications.
• Weighted price and qualifications. This process is similar to the lowest qualified bidder for professional
services. Contractors are evaluated against several factors, with a pre-determined weight assigned to each
factor. A weight is also assigned to the contractor’s bid price. The contract is awarded to the contractor that has
the best weighted score. This is also known as a “best value” qualification.
• Qualifications-based selection. This approach is most often used on design contracts, where the design cost is a
small fraction of the construction cost. Increased attention to design can result in large construction savings.
Contractors’ qualifications are evaluated, the contractors are ranked, and a contract is negotiated with the most
qualified firm. If the government and the contractor cannot agree on a reasonable price, the government
terminates the negotiations and begins negotiating with the second-ranked firm. Once negotiations are
terminated they cannot be re-opened.
12.3 SOLICITATION
39
40
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
These are all used on government projects. In addition, the following techniques are particularly useful on
government projects.
.5 Proposal opening and rejection of proposals. The sealed proposals are publicly opened. The bidders are
informed of the time and location of the opening of the proposals. Governments reserve the right to reject any or all
proposals received. Proposals become the property of the government. Potential sellers whose proposals are not
accepted are notified in writing after the award of the contract.
.6 Mandatory requirements. Most contracts have minimum mandatory requirements. The proposals must include
evidence that they meet these requirements. Proposals that do not meet the mandatory requirements are excluded
from further evaluations. Examples of mandatory requirements include:
• Compliance with drug-free workplace policy.
• Format of the proposal.
.7 Demonstrations and oral presentations. Demonstrations and presentations are often included as part of the
solicitation process. When they are included, they may be either mandatory or optional. Potential sellers demonstrate
their proposed package and clarify or explain unusual or significant elements of their proposed package. Potential
sellers are not allowed to alter or amend their proposals after submission. Potential sellers are not allowed to conduct
negotiations during the interview process. A “best business practice” calls for each panelist to prepare their list of
questions so that the same questions are asked of each potential seller.
.8 Award and preference laws. Representative bodies often use preferences in procurement to achieve social and
economic goals. Preferences may be a percentage weighting or an absolute restriction. Some preferences include:
• Regional preference. In some cases, a resident seller has preference over a non-resident. This preference may be
applied by a national government, giving preference to their own nationals, or a regional or local government
giving preference to regional or local firms.
• Population groups. Governments will often give preference to a particular population group. These may be
ethnic groups, people who are deemed to be disadvantaged (e.g., women and disabled people), or people to
whom the voters feel indebted (e.g., military veterans).
• Small business preferences.
.9 Protest and grievance procedures. Each governing body has administrative procedures for sellers to file
grievances and protests related to an award. Each issue identified by a seller is communicated in writing to the
agency. The agency sends a written response to the seller. If the response from the agency has not satisfied the firm,
meetings are scheduled. However, final decisions are the agency’s responsibility. The seller must exhaust the
administrative process before proceeding through the court system.
.10 Best and final offers. In some instances, government agencies have the authority to ask the top-rated candidates
for “best and final” offers if none of the submitted bids is acceptable as is. When this option is available, it can be a
powerful tool for getting a contract more closely meeting an agency’s needs.
These are all used on government projects. In addition, the following tools are particularly significant on
government projects.
.5 Cost and payment schedule. The seller submits progress payment invoices on dates that are specified in the
contract. Most government agencies have “prompt payment” rules that require them to pay invoices in a prompt
manner.
.6 Claims. If the government agency rejects a change requested by the contractor, this creates a potential claim. The
project manager is responsible for ensuring the prompt negotiation and settlement of claims. Government agencies
generally have a structured dispute resolution process. It can take many years before a final determination is made.
42
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
GLOSSARY
Best Value Qualification. See weighted price and qualifications.
Civil Service System. A system in which government employees hold office from one administration to another.
Their positions are protected provided that they remain politically neutral. See spoils system.
Constructive Demotion. Assigning a civil servant to a position that is perceived to be inferior.
Defined Contribution. Split funding by program where some programs contribute a fixed amount, with one
program funding the balance.
Defined Elements of Work. Split funding by program where each program bears the cost of its portions of the
project.
Devolution. Delegation of work or power by a national government to a regional or local government; or by a
regional government to a local government.
Devolve. See devolution.
Eminent Domain. A process that allows the government may take possession of private property when this is in the
best interests of the public. It is used most often to take possession of real property. The government is
generally required to pay just compensation for the property.
Encumbrance. See obligation.
Full and Open Competition After Exclusion of Sources. A process in which agencies are allowed to exclude one
or more sources from competing for a contract. A set-aside for a small business or a small disadvantaged
firm is an example of this method.
Full and Open Competition. A process in which all responsible sources are allowed to compete for a contract.
Government Transfer Payment. See obligation.
Hybrid Staff. A mixture of civil service and contracted staff.
Indefinite Delivery Indefinite Quantity Contracts (IDIQ). Contract that states the type of service to be delivered,
gives a length of time in which the service can be requested (generally five years), and the minimum and
maximum contract amount, but no specific project information.
Line-Item Projects. Projects are added to the budget by the representative body on a project-by-project basis.
Local Government. The government of a small portion of a country or region. There are often overlapping local
governments with different duties. Local governments include counties, cities, towns, municipalities,
school boards, water boards, road boards, sanitation districts, electrification districts, fire protection
districts, and hospital districts. They are governed by elected boards. This election distinguishes them from
local branches of regional or national governments.
Lowest Qualified Bidder. A contracting process in which the lowest bid is accepted. Contractors’ proposals are
evaluated to ensure that they meet minimum qualifications. The level of qualification may vary. On
construction contracts, the minimum qualification is generally a contractor’s license and a performance
bond. On professional service contracts, there is generally a more detailed evaluation of the contractors’
qualifications.
Matching Funds. A form of split funding by program. When governments “devolve” project selection to lower
representative bodies, they often require those lower bodies to pay a portion of the project cost. Matching
funds may be apportioned on a percentage basis or as a defined contribution.
Multiple Award Schedules. A contracting process sometimes used when there is a generally accepted “reasonable
price” for a good or service. Contractors submit their schedule of rates to the government procurement
office. If these are approved, government agencies may buy goods and services at the published rates
without a separate competition.
National Government. The government of an internationally recognized country. The country may be a
confederation, federation, or unitary state.
Obligation. A process that places funds for a contract into a separate account that can be used only for the specific
contract. The funds remain available for two to five years, depending on the rules set by the representative
body. This avoids the need to vote funds in each fiscal year.
On-Call Contracts. See indefinite delivery indefinite quantity contracts.
Opposition Stakeholders. Stakeholders who perceive themselves as being harmed if the project is successful.
43
Other Than Full and Open Competition. A process in which there is only a single contractor that can accomplish
the work, by reason of experience, possession of specialized facilities, or technical competence, in a time-
frame required by the government.
Percentage Split. Split funding by program where each program funds a percentage of the project.
Program. A group of projects managed in a coordinated way to obtain benefits not available from managing them
individually.28
Qualifications-Based Selection. A contracting process in which the contract is awarded to the contractor that is best
qualified among those that offer a price that is reasonable to the government. This approach is most often
used on design contracts, where the design cost is a small fraction of the construction cost. Increased
attention to design can result in large construction savings. Contractors’ qualifications are evaluated, the
contractors are ranked, and a contract is negotiated with the most qualified firm. If the government and the
contractor cannot agree on a reasonable price, the government terminates the negotiations and begins
negotiating with the second-ranked firm. Once negotiations are terminated they cannot be re-opened.
Regional Government. The government of a portion of a large country. In small countries, there are no regional
governments—only a national government and local governments. In confederations and federations, the
regional government has considerable autonomy. In unitary states, the regional government is subject to
control by the national government. Regions are called by many different terms. These terms include states,
provinces, lander, departments, cantons, kingdoms, principalities, republics, regions, and territories.
Regulators. The individuals or organizations that must approve various aspects of the project. Regulators enforce
rules and regulations. They are actively involved in the project, but they generally have no interest in its
success—it will not affect them. Regulators are either agents of a higher government or of another agency
in the same government as the performing organization.
Representative Body. A group of people, elected by the voters, who meet, deliberate, and set rules. They may call
these rules by several names. They include laws, statutes, ordinances, regulations, and policies.
Sole Source Contract. See other than full and open competition.
Split Funding by Fiscal Year. The process of funding a single project from several annual budgets.
Split Funding by Program. The process of funding a single project from more than one program.
Spoils System. A system in which each new administration can replace government employees. See civil service
system.
Tight Matrix. A system in which each project has an assigned work area, and employees sit together in that area
while they are working on the project, even though they do not report to the same supervisor.
Use It or Lose It. Provisions in an annual budget that require funds to be spent, or obligated, by the end of the fiscal
year.
Weighted Price and Qualifications. A contracting process in which contractors are evaluated against several
factors, with a pre-determined weight assigned to each factor. A weight is also assigned to the contractor’s
bid price. The contract is awarded to the contractor that has the best weighted score.
44
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
PROJECT MANAGER
Nigel Blampied
CHAPTER TEAMS
Each chapter was written by a chapter team, consisting of a lead author and several co-authors. Lead authors
were responsible for the successful completion of a particular chapter and wrote the first draft of the chapter. Co-
authors contributed ideas and text to the chapter.
Chapter 1: Introduction—Lead Author: Nigel Blampied; Co-authors: Ted Aho, Curt Bramblett, Nicolle Goldman,
Ronald Lester, Bongani Matomela, Jack McDaniel, and Roykumar Sukuram.
Chapter 2: Context—Lead Author: Nigel Blampied; Co-authors: Ted Aho, Curt Bramblett, Nicolle Goldman,
Ronald Lester, Jack McDaniel, Larry Sieck, and Roykumar Sukuram.
Chapter 3: Processes29—Lead Author: Nigel Blampied; Co-authors: Ted Aho, George Belev, Curt Bramblett,
Nicolle Goldman, Ronald Lester, and Larry Sieck.
Chapter 4: Project Integration Management—Lead Author: Adrian Hayward; Co-authors: Ted Aho, Nigel
Blampied, Curt Bramblett, Dawn Daugherty, Peter Heffron, Jeff Romanczuk, Kazuo Shimizu, Larry Sieck, and
Roykumar Sukuram.
Chapter 5: Project Scope Management—Lead Author: Roykumar Sukuram; Co-authors: Ted Aho, Nigel
Blampied, Nicolle Goldman, Adrian Hayward, Peter Heffron, Ronald Lester, Linda Salac, and Larry Sieck.
Chapter 6: Project Time Management—Lead Author: Nigel Blampied; Co-authors: Ric Albani, George Belev,
Dawn Daugherty, Nicolle Goldman, Ronald Lester, Jack McDaniel, Larry Sieck, and Roykumar Sukuram.
Chapter 7: Project Cost Management—Lead Author: Nigel Blampied; Co-authors: Ted Aho, Curt Bramblett,
Nicolle Goldman, Ronald Lester, Jack McDaniel, and Larry Sieck.
Chapter 8: Project Quality Management—Lead Author: Nigel Blampied; Co-authors: Larry Sieck, Roykumar
Sukuram, and Dale Woolridge.
Chapter 9: Project Human Resources Management—Lead Author: Dale Woolridge; Co-authors: Ted Aho, Nigel
Blampied, Curt Bramblett, Dawn Daugherty, and Larry Sieck.
Chapter 10: Project Communications Management—Lead Author: Jeff Romanczuk; Co-authors: Emmanuel
Abegunrin, Nigel Blampied, Curt Bramblett, Nicolle Goldman, Jack McDaniel, and Larry Sieck.
Chapter 11: Project Risk Management—Lead Author: Nigel Blampied; Co-authors: Ted Aho, Nicolle Goldman,
Ronald Lester, Larry Sieck, Roykumar Sukuram, and Dale Woolridge.
Chapter 12: Project Procurement Management—Lead Authors: Dawn Daugherty and Linda Salac; Co-authors:
Ted Aho, Nigel Blampied, Nicolle Goldman, Adrian Hayward, Ronald Lester, Jack McDaniel, James McGee, Brad
Poeckes, Larry Sieck, and Steven Schafer.
45
46
https://analisederequisitos.com.br/government-extension-pmbok/
Government Extension to
A Guide to the Project Management Body of Knowledge
Exposure Draft © 2001 Project Management Institute
APPENDIX B: NOTES
1
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute.
2
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 3.
3 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 181.
4
This principle dates back at least to the Magna Carta and, in some countries, probably earlier. Article 12 of the
Magna Carta, signed in 1215 by King John of England, says, “No scutage or aid shall be imposed in our realm
unless by the common counsel of our realm.”
5
This is true even if the project manager works in the legislative branch of a government (e.g., the project manager
may be responsible for managing audits for the legislative branch). Within the legislative branch, there are executive
officers responsible for day-to-day operations. The project manager would be part of this executive-within-the-
legislature.
6
Such abuses are most likely in places where there are severe limitations on voting rights (most often limitations
based on ethnicity or length of residence).
7
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown, PA: Project Management Institute, page 10. This definition is quoted from Turner, J.
Rodney. 1992. The Handbook of Project-Based Management. New York, N.Y.: McGraw-Hill.
8
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown, PA: Project Management Institute, page 11.
9
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown, PA: Project Management Institute, page 16.
10 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 29.
11 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 51.
12 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 53.
13
For countries that use English law, the annual budget originates from the English Declaration of Rights. William
III and Mary II signed this in 1689. It prevented the king from maintaining an army without the consent of
Parliament. Its goal was to prevent the king from using the army against the people, as Charles I had done in the
Civil War. Parliament began to pass six-month "Mutiny Acts" to permit the king to keep his army. They were later
changed to annual acts.
The United States adopted a version of the British limit. Article 1, Section 8 of the U.S. Constitution says that,
“[The congress shall have power] to raise and support armies, but no appropriation of money for that use shall be for
a longer term than two years.” Article 1, Section 9 adds, “No money shall be drawn from the treasury, but in
consequences of appropriation made by law.”
14
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 95.
15
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 98. This is a quotation from the
International Organization for Standardization. ISO 8402. 1994. Quality Management and Quality Assurance.
Geneva, Switzerland: ISO Press.
16
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 98.
17
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 107.
47
18 For a discussion of the tight matrix, see Stuckenbruck, Linn C., and David Marshall. 1996. Team Building for
Project Managers. The Principles of Project Management. Newtown Square, PA: Project Management Institute,
page 152.
19 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 115.
20 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 117.
21
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 119.
22
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 122.
23
Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide) –
2000 Edition. Newtown Square, PA: Project Management Institute, page 125.
24 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 127.
25 Project Management Institute. 2000. A Guide to the Project Management Body of Knowledge (PMBOK® Guide)
– 2000 Edition. Newtown Square, PA: Project Management Institute, page 147.
26
ENR (Engineering News Record). 2000. July 24/July 31, page 51.
27 W. Edwards Deming. 2000. Out of the Crisis. Cambridge, Mass: The MIT Press, page 23. (Originally published:
48
https://analisederequisitos.com.br/government-extension-pmbok/
LIVRO GRÁTIS!
SCRUM
KANBAN E
SCRUMBAN
DOWNLOAD GRÁTIS
Mais livros e conteúdos gratuitos disponíveis em:
https://analisederequisitos.com.br/downloads
MAIS LIVROS GRATUITOS
Engenharia de Requisitos:
software orientado ao negócio
O livro "Engenharia de Requisitos: Software Orientado
ao Negócio" oferece uma abordagem prática e
abrangente para a engenharia de requisitos.
https://analisederequisitos.com.br/government-extension-pmbok/