Chapter 6 - Facility Layout Models II
Chapter 6 - Facility Layout Models II
Line Balancing
Line Balancing
1 2 3
4 minutes 4 minutes 4 minutes
6
Example
Workstation Workstation Workstation Workstation
1 2 3 4
Tasks A B, C D, E F
Time 60 120 90 90
7
Calculating Production Rate From
Cycle Time
1
Production rate
cycle time
1
3,600 sec./hr.
120 sec./unit
30 units/hr.
8
Calculating Idle Time
9
Calculating Unit Labor Cost
The total labor cost for eight hours is
(8 hours/shift) (4 workers/shift) ($20/hour),
or $640/shift.
11
Line Balancing Procedure
1. Draw and label a precedence diagram
2. Calculate desired cycle time required for line
3. Calculate theoretical minimum number of workstations
4. Group elements into workstations, recognizing cycle
time and precedence constraints
5. Calculate efficiency of line
6. Determine if theoretical minimum number of
workstations or an acceptable efficiency level has been
reached. If not, go back to step 4.
Number of Workstations
N
M 1 / C ti
i 1
n
LE 1 / MC ti (100)%
i 1
4
5 3 2
2 5
1 1 7 8
2
4
3 4
3 6
Desired production rate = 12/hour
• Will examine three algorithms that differ in the way tasks are
17
Ranked Positional Weight
• Tasks are ordered for assignment in terms of decreasing ranked
positional weight.
• The positional weight for each task is the sum of the task
completion times for the task in question and all tasks that follow
8 2 2 4 1 6
7 3 5 3 3 13
6 4 4 2 5 15
5 4 9 1 2 24
Example
Algorithm proceeds by assignment of tasks in order of descending
1 2 24 4 1 6
2 5 15 7 3 5
3 3 13 6 4 4
5 4 9 8 2 2
Example
Assign tasks to workstations using the following format:
Cumulative Cumulative
Station Task Time Cumul. Time Station Task Time Cumul. Time
1 1 2 2 4 7 3 3
3 3 5 8 2 5
2 2 5 5 5 6 4 4
3 5 4 4
4 1 5
Example
Ranked Ranked
1 1 4 7
2 2, 3 5 6, 8
3 5, 4
Region Approach - Example
• As station is “closed out,” alternative assignments (still feasible
with respect to assignment restrictions) are evaluated to improve
station efficiency.
Cumulative Cumulative
1 1 2 2 4 7 3 3
3 3 5 8 2 5
2 2 5 5 5 6 4 4
3 5 4 4
4 1 5
Region Approach - Example
40
Example
41
Example ‐‐ Continued
cacity
PR
H
6,000 units/wk.
40 hrs./wk.
150 units/hr.
1
C
PR
1
150 units/hr.
1
3,600 sec./hr.
150 units/hr.
24 sec./unit
n
ti
N i1
C
107 sec.
24 sec./stati on
4.46 or 5.0 stations 42
Balanced Line for the
Medical Kit Problem
Time remaining
Task Available Task Assigned at the Station
to be Scheduled Selected to Station (Seconds)
A A 1
B,C,D B 1 0
C,D D 2
C C 2
E E 2 3
F,G,H F 3
G,H G 3 0
H H 4 43
I I 4 7
Example
idle time
Balance delay (percent idle time) (100)
time available in the line
n
(m)(C ) t i
i 1
(100)
(m)(C )
(5 stations)(24 sec./stations) 107 sec.
(100)
(5 stations)(24 sec./station)
10.8%
44
©
Thank you for your attention… 2012