_Introduction-to-Case-Study-A---Quantitative-Risk-Analysis
_Introduction-to-Case-Study-A---Quantitative-Risk-Analysis
STUDY A – QUANTITATIVE
RISK ANALYSIS
TABLE OF CONTENTS
Introduction 1
A5. Risk Calculation for the Baseline Scenario in the Current Situation and 2050 Horizon 8
Acronyms 10
INTRODUCTION
The objective of this reading is to introduce the case study that we will work with in this section. The
objective includes a quantitative risk analysis based on a proposed risk model, for the current and future
situation, as well as the assessment of the risk impact of design improvement measures.
1
Case Study A involves the analysis of a flood control infrastructure project in the design phase that
could be susceptible to hydrological and geotechnical hazards. The city under study is located in one
of the most vulnerable areas to natural hazards in Latin America and the Caribbean. This is an area with
the highest natural disaster risk in the country.
The selected failure mode corresponds to the overtopping of the projected protection levee
failure mode. Figure 1 shows the description and summary resulting from the failure mode identification
phase.
Description
In the hydrological scenario, a high level of water is produced in the river, spilling over the crest of one of the projected protection
levees and overtopping the levee. In addition, the slope of the protection levee is damaged by lack of maintenance, so the flow of
water causes rapid erosion of the body of the levee, increasing the flow of discharge into urban areas and the consequences of this
flood in urban areas.
Diagram
2 1
3
1 Levee deterioration 2 Overtopping over 3 Erosion of the body Levee failure due to
4
due to lack of the body of the of the levee erosion of its body
maintenance levee
2
Factors That Increase Risk Factors That Decrease Risk
There is a problem with the development of informal No factors have been identified in this regard.
settlements in areas that are close to the river, which are
also built with low-quality materials.
In order to analyze both the current situation before carrying out projected protection works and their impact on
risk, we need two architectures for the quantitative risk analysis.
SEASON
FLOODS
Season Node: This node enables the model to allow for the differences that
would occur if the flood happened in summer or in winter because, depending on
the season, the duration of day and night considered may be different (e.g., due
to differences in the length of the work day between summer and winter months).
In addition, the population could vary considerably in either case (e.g., if the city
were a holiday destination and its population were to increase in a given season).
Day\Night Node: This node includes the probabilities of the flood occurring
during the day or at night, considering these two options when estimating
consequences for the population and taking into account that the population may
change during the day due to daily variations (e.g., labor reasons, cities that are
“sleeping quarters” for residents who normally work outside the area, etc.).
3
Floods Node: This node enables the discretization of the entire range of return
periods contemplated for floods in the channel, covering a range of 1 to 200 years
for the return period.
Damages Node: This node includes estimation results regarding the economic
consequences that may stem from the flood.
Figure 3 shows the CaseStudyA_Works risk model proposed for the quantitative analysis after
considering the existence of the protection works and the potential failure of the planned levee.
SEASON
FATALITIESF DAMAGESF
DAY\NIGHT Q RIVER
FAILURE
FATALITIESNF DAMAGESNF
FLOODS WL RIVER
River Water Level (WL River) Node: Based on the discharges due to any
floods that may occur, this node incorporates the level that the river channel
would reach associated with each of these discharges.
4
FatalitiesF Node: This node includes estimation results regarding the
consequences to the population in the event of a levee failure due to
overtopping, stemming from the resulting flood.
For the above two nodes of economic consequences (in monetary units) and social consequences (in
potential fatalities), both for the baseline scenario and for the different scenarios to be analyzed, input
values are the product of the following processes:
5
A4. Main Risk Model Input Data
In the following tables we will describe the information incorporated into the model at each node. This
input data is introduced using Excel files that can be downloaded from the course platform.
Summer 0.25 Three months of the year correspond to the conditions considered for summer.
Winter 0.75 Nine months of the year correspond to the conditions considered for winter.
6
Season Time Probability Description
1 5 7
5 0/0 0
20 5/2 0.55
45 10 / 5 1.2
It includes summary results of the estimation
70 1.8 of consequences for the population, in number
20 / 8
of potential fatalities and economic costs due
to flooding.
105 50 / 20 2.6
Table 6. Input Data for the River Water Level (WL River) Node.
1 138 138.2
5 139.2 139.3
7
Table 7. Input Data for the Failure Node.
141.5 0
141.6 0.2 It includes probability values based on the fragility curve considered for an
embankment levee, in which failure probability is estimated at 100% for
overtopping heights equal to or greater than 0.5 m above the levee.
141.7 0.5
142 1
Fatalities Fatalities
Channel Level (Failure) (No Failure) Description
(m.a.s.l.) [Number of [Number of
People] (Day/ People] (Day/
Night) Night)
141.5 15 0
It includes summary results of the estimation of
economic consequences, in millions of US$, in
the event of a flood by levee breakage (failure),
141.6 18 0.25 including US$4 million in reconstruction costs
and the damage resulting from flooding due to
the breach in the levee. It also includes the costs
141.7 20 0.6 of flooding by overtopping without failure (no
failure), which are much lower because there is
no breach in the levee.
142 28 1.2
Once all the information has been incorporated, we execute the baseline model to estimate the risk in the current
(2020) scenario, the future (2050) scenario, and the scenario after implementing the planned works (2022). Results
obtained are shown in Table 10.
8
Table 10. Risk Results for the Current Scenario (2020), Future Scenario (2050), and the Scenario with
Planned Works (2022).
Results can be represented with F-N or F-D curves, in which F is the cumulative annual exceedance probability
of the level of consequences corresponding to loss of life (N) or to economic costs (D). As an example,
the curves below include the current scenario and the scenario after contemplating the projected works.
They show that the works reduce frequent flooding events (most likely, moving the curve downwards),
but there may be events associated with failure that shift the curve to the right (low probability – higher
consequences). However, the total area under the curve is smaller in the scenario with protective works
(social and economic risk is lower than the current one).
___ ___
___
CASE STUDY A: 2022 WORKS
___
CASE STUDY A: 2022 WORKS
100 100
ANNUAL ECONOMIC DAMAGE PROBABILITY ≥ D, F
_
10-1 10-1
ANNUAL LOSS-OF-LIFE PROBABILITY ≥ N, F_
10-2 10-2
10-3 10-3
10-4 10-4
10-5 10-5
10-6 10-6
10-7 10-7
10-8 10-8
10-9 10-9
10-10
100 101 102 103 104 100 101 102 103 104 105
LOSS OF LIFE, N ECONOMIC DAMAGE (EC_UNITS), D
Figure 4. F-N and F-D Curves for the Current Scenario vs. the Scenario for Designed Protection Works.
For this case study, we will consider three additional scenarios for performing calculations. Participants can
obtain them from the case model with projected works (CaseStudyA_Works, Figure 3):
9
Scenario with Design Improvement Measures (Modified Design): To
assess the impact on risk of design changes with which to reduce the risk
of overtopping the levee (the improvement consists of changing the crest
elevation and taking it to 141.75 m.a.s.l.) and a reinforcement on the levee’s
berm to reduce the erosion of the body of the levee in the event of overtopping.
It involves changes to the Failure node and the Fatalities and Damages nodes.
Given the architecture of the proposed risk model, the results obtained for the current situation, and
the scenarios presented in the previous section, please answer the following questions:
1) If we change the selection of input data for the WL River node (“Works and 2050 Scenario”
sheet), what would be the resulting risk for the 2050 scenario if floods for the trend scenario are
taken into account? How do the F-N and F-D curves change when compared with the current
scenario? Would the planned design be appropriate considering future risk?
2) If we change the selection of input data for the Failure, FatalitiesF, FatalitiesNF, DamagesF,
and DamagesNF nodes (“Improved Design” sheets), what would be the risk resulting from
implementing the design improvement measures? How do the F-N and F-D curves change
when compared with the current scenario? Would design improvements be justified in terms
of risk reduction?
3) If we change the selection of input data for the FatalitiesF and FatalitiesNF nodes (“Warning
Improvements” sheets), what would be the risk resulting from implementing nonstructural
measures to improve the warning systems for the population?
ACRONYMS
FM FAILURE MODE
10