ITP for Slab on Grade
ITP for Slab on Grade
:
INSPECTION AND TEST PLAN Rev. :
Date :
TITLE: CONCRETE SLAB ON GRADE
DISCIPLINE: CIVIL
PROJECT : CONTRACTOR:
INSPECTION
FORMS / RESPONSIBILITIES
Sl. No. ACTIVITY DESCRIPTION REFERENCE DOCUMENTS ACCEPTANCE CRITERIA VERIFYING DOCUMENTS Remarks
CHECKLIST
1 DOCUMENT REVIEW
Conformance to
Material Technical
1.1 Material Submittal (RSB) AES-C-0004 AES-C-0004, - R R/A
Data
Sec. 6.5
AES-C-0004 / Conformance to
Third Party
1.2 Concrete Design Mix RC 03 30 00 AES-C-0004, - R R/A
crushing test report
Approved Mixed Design Sec. 7.6
Conformance to
2.1 Material receiving inspection. AES-C-0004 Material Approval / No Material Certificate - H W
physical damage
3.0 INSTALLATION
Installed filler boards, reinforcement bars, IFC Drawing / Conform to IFC Drawing / Quality Checklist /
3.1.3 AMCC.QF.C002 H W
embedded items and elevations. Approved drawings Approved drawings Survey Report
PROJECT : CONTRACTOR:
INSPECTION
FORMS / RESPONSIBILITIES
Sl. No. ACTIVITY DESCRIPTION REFERENCE DOCUMENTS ACCEPTANCE CRITERIA VERIFYING DOCUMENTS Remarks
CHECKLIST
* For 35 Mpa
Slump Test: 150±25 mm
Fresh Concrete sampling Approved Conc. Temp.: Not exceed 30 ºC Third Party Test perform by approved third
3.2.1 AMCC.QF.C003 H W
(Slump and Temperature) Design Mix * For 20 Mpa Test Report party
Slump Test: 125±40 mm
Temp.: Not exceed 32 ºC
AES-C-0004 /
AES-C-0004 Quality Form / Test perform by approved third
3.2.2 Monitor concrete placement Approved Conc. AMCC.QF.C003 W W
Clause 7.14 Checklist party in laboratory
Design Mix
Minimum Compresive
AES-C-0004 /
Strength Third Party Test perform by approved third
3.3.3 Concrete Compressive Testing (7th & 28th days) Approved Conc. AMCC.QF.C003 W W/R
7th days: 24 Mpa Test Report party in laboratory
Design Mix
28th days: 35 Mpa
3.3 POST CONCRETE
4 PRE-COMMISSIONING