0% found this document useful (0 votes)
6 views4 pages

DPR 13-Dec-2024

Format of DPr

Uploaded by

ABE Akola
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
6 views4 pages

DPR 13-Dec-2024

Format of DPr

Uploaded by

ABE Akola
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

Projcct Management Services for Development /Re-Development /Major Upgradation of Ghaziabad Railway Station under Dellhi Division of Northern

Railway
Daily Progress Report as on Date :- 13-12-2024
SCOPE
Previous Progress Balance to be
Labour Details dated 13-12 - 2024
Location Description of work Unit Work o Cumulative Previous day Activities
No. done Total
Done 12.12.24 Today Activities Skilled Un-Skilled Labour
2 4 6 9 10 12 13 14

Retaining Wall Ist lit Rmt 547 342.3 0 342.3 204.7 No Activity No Activity
Retaining Wall 2nd lift Rmt 547 306 0 306 241 No Activity No Activity
Column Ist Lift Nos 112 52 0 52 60 Column reinforcement work Column reinforcement work
Column 2nd Lift Nos 112 50 50 62 Column reinforcement work Column reinforcement work
293
Backfilling work is under Backfilling work is under
Outer Retaining VVall Casting Rmt 115 0 115 178
Sation Building progress. progress.
14 22 36
(City Side) De-Shuttering of Partl& De-Shuttering of Part I &
Basement Slab Sqm 4216 1100 0 1100 3116 staging work of Part 2with staging work of Part 2 with
Ground slab is in Progress. Ground slab is in Progress.

Ground Floor Column 1st lift Nos 102 24 0 24 78 |24/25 Column (PART-1) |24/25 Column (PART-1)
Ground Floor Slab Sqm 3850 3850 |Staging &shuttering work is Staging &shuttering work is
under Progress under Progress
Retaining Wall 1st lift Rnt 533 522 |522 11 No Activity No Activity

Retaining Wall 2nd lift Rmt S33 430 430 103 No Activity No Activity

Retaing wall Final lift Rmt $33 220 0 220 313


Casting of Retaining of STP Casting of Retaining of STP
Portion With Walkway Slab. Portion With Walkway Slab.

Column 2nd Lift Nos 62 39 39 23 No Activity No Activity

Fire & Raw Water Tank Slab Sqm 170 170 0 170 0 |Completed. |Completed.
Sation Building 20 35
(Vijay Nagar Side) De-Shuttering of Basement De-Shuttering of Basement
Slab (Part-l) & Staging of Slab (Part-l) & Staging of
Basement Slab Sqm 3015 850 850 2165 lPart-2 ) with Shuttering &(Part-2 ) with Shuttering &
Reinforcement work is in Reinforcement work is in
progress. progress.
14/16 Column (PART-1) 14/16Column (PART-1)
14 37
Remaning Column Remaning Column
Ground Floor Column lst lift Nos 14
Shuttering &Reinforcement Shuttering &Reinforcement
work is progress work is progress

1
13h1224
Project Vianagement Services for Development /Re-Development /Major l pgradation of Ghaziabad Raifway Station under Delhi Divísion of Northern Railway
Daily Progress Report as on Date :- 13-12-2024
sCOPE Previous Progress Balance to be Labour Details dated 13-12 - 2024
Location Description of werk Unit Work On Cumulative Previous day Activities Total
No. done Skilled L-Skilled
Done 12.12.24 Today Activities Labour
1 11 14

|4/16 Column (PART-) 14/16Colurmn (PART- I)


Nos
Remaning Column Remaning Column
Ground Floor Column 2nd lin 51 11 11 40
Shuttering &Reinforcement Shuttering &Reinforcement
work is progress work is progress
Outer Plaster work in Outer Plaster work in
Plaster work Sqm 18000 17980 17980 20
Progress Progress
AAC Block Cum 1160 1146.5 1146.5 13.5 No Activity No Activity
STTC Hostel Floor Tile $940 3825 No Activity No Activity 19 16 26
Sqm 2115 2115

Painting 1st coat Sqm 18000 7780 200 7980 10020 Putty Ist Coat Putty Ist Coat

Railing Nos 80 65 0 65 15 No Activity No Activity


6th Floor Slab Casted on 6th Floor Slab Casted on
Slab Sqm 630 490 490 140
16.09.2024 16 09 2024

Column & Shear wall


27/50 7th Floor Column Shuttering work is under
Nos 449 375 375 74
Casted Remaning progress
Staff Quarter Type-III 2
Tower-1

AAC Block Work Cum 712 369 0 369 343 No Activity No Activity

Plaster work Sqm 15000 1236 1236 13764 No Activity No Activity

630
8th Floor slab casted on 8th Floor slab casted on
Slab Sqm 630 630
11.12.2024 11.12.2024

Staff Quarter Ty pe-III Column Nos 449 449 449 0 50/50 Terrace Floor Column 50/50 Terrace Floor Column
Tower-2
|Casted Casted

Block work in progress at Block work in progress at


A4C Block Work Cum 712 403.4 0 403.4 308.6
6th Floor 6th Floor

Jaelh

2
Project Management Senices for Development /Re-Development /Major Upgradation of Ghaziabad Railway Station under Delhi Division of Northern Railway
Daily Progress Report as on Date:- 13-12-2024
Lecation Description of work Unit
SCOPE PreviousProgress
Work on Cumulative
Balance to be
Prevlous day Activities
Labour Details dated 13-12 - 2024
Total
No. done Today Activities
Done 12.12.24 SkilledUn-Skilled Labour
9 I4

Plaster work 15000


Plaster work in progress at Plaster work in progress at
Sqm 966 966 14034
2nd floor 2nd floor
4th Floor Slab Casted on 4th Floor Slab Casted on
Slab Sqm 630 350 3S0 280
|22.09.,2024 22 09 2024
36/50 Sth Floor Column 36/50 Sth Floor Column
Column Nos 449 164 Casted Remaning Column Casted Remaning Column
285 285
Staff Quarter Type-lll shuttering &reinforcement shuttering &reinforcement 1 1 2
Tower-3 work is under progress. work is under progress

AAC Block Work Cum 712 161.2 161.2 550.8 No Activity No Activity

Plaster w ork Sqm 15000 768 768 14232 No Activity No Activity


Slab (Mumty) Sqm 20 0 0 20 No Activity No Activity

Plaster Work Sqm 970 712 712 258 No Activity No Activity


Staff Quarter Type-lV 1 2
AAC Block Work Rmt 60 60 60 Completed Completed
Flooring Sqm 255 0 No Activity leveling work is under
Iprogress.
Staff Quarter Type-\ Flooring Sqm 200 0 0 200 No Activity No Activity 0

Painting Ist coat Sqm 1868 980 0 980 888 No Activity No Activity
Door & Window Nos 20 20 20 No Activity No Activity
Sub Station
(City Side) 0 0
Boundary wall Footing Nos 33 11 11 22 No Activity No Activity

Earthing and Cable laying work Nos 31 23 0 23 8 No Activity No Activity


Sub Station Excavation work is under
Slab Casting Cum 154 154 154 |Completed 1
( ijay nagar Side) progress

Column Nos 22 22 0 22 Completed Completed


Manistrate Rillinn

3
(3)
Project \Management Sen ices for Development /Re-Devclopment /Major Ipgradation of Ghaziabad Railway Station under Dellhi Division of Northern Railway
Daily Progress Report as on Date :- 13-12-2024
PreviousProgress Labour Details dated 13-12 - 2024
Location SCOPE Balance to be
Deseription of work Unit Work on Cumulative Previous day Activitles Total
No. done
Today Activities SkilledUn-Skilled
Done 12.12.24 Labour
4 6 12 13 14
IgistrITE Dutung

Slab Casting Cum 66 66


Slab casting 01 10.2024 No Slab casting 01.10 2024 No
66
Activity |Activity
Plinth Beam Rmt 163 163 0 163 Completed on 24.07.2024 |Completed on 24 07 2024

GRP Building Column above to Slab Nos 25 25 25 Completed Completed 2 3 5

Reinforcement work in Reinforcement work in


Slab Cum 50 0 50
Progress Progress
Plinth Bcam Rmt 183 183 0 183 No Activity No Activity
RPF Building 0
Column above Plinth Nos 29 22 22 No Activity No Activity

Foundation Nos 15 9 9 reinforcement &shuttering Shuttering work is under


work. progress.
FOB A( Vijay Nagar Side) 2 3 5
Pedestal Nos 29 16 20 9 casting work Reinforcement &Shuttering
work in Progress

Foundation Nos 14 0 0 14
Excavation work is under Excavation work is under
|progress. progress.
FOB A ( City Side) 2 2
Pedestal Nos 46 0 0 46 No Activity No Activity

Platform 3&4 Porta Cabin Nos 1 0 0 1 No Activity No Activity 0 0

Lab & Store 1

Miscellaneous Work Shifting, Barricading ,Housekeeping &(RRI Building Panting) 1 1 2

Total 53 75 128

Contractor Representative PMS Representati Ralway Recresentative