DPR 13-Dec-2024
DPR 13-Dec-2024
Railway
Daily Progress Report as on Date :- 13-12-2024
SCOPE
Previous Progress Balance to be
Labour Details dated 13-12 - 2024
Location Description of work Unit Work o Cumulative Previous day Activities
No. done Total
Done 12.12.24 Today Activities Skilled Un-Skilled Labour
2 4 6 9 10 12 13 14
Retaining Wall Ist lit Rmt 547 342.3 0 342.3 204.7 No Activity No Activity
Retaining Wall 2nd lift Rmt 547 306 0 306 241 No Activity No Activity
Column Ist Lift Nos 112 52 0 52 60 Column reinforcement work Column reinforcement work
Column 2nd Lift Nos 112 50 50 62 Column reinforcement work Column reinforcement work
293
Backfilling work is under Backfilling work is under
Outer Retaining VVall Casting Rmt 115 0 115 178
Sation Building progress. progress.
14 22 36
(City Side) De-Shuttering of Partl& De-Shuttering of Part I &
Basement Slab Sqm 4216 1100 0 1100 3116 staging work of Part 2with staging work of Part 2 with
Ground slab is in Progress. Ground slab is in Progress.
Ground Floor Column 1st lift Nos 102 24 0 24 78 |24/25 Column (PART-1) |24/25 Column (PART-1)
Ground Floor Slab Sqm 3850 3850 |Staging &shuttering work is Staging &shuttering work is
under Progress under Progress
Retaining Wall 1st lift Rnt 533 522 |522 11 No Activity No Activity
Retaining Wall 2nd lift Rmt S33 430 430 103 No Activity No Activity
Fire & Raw Water Tank Slab Sqm 170 170 0 170 0 |Completed. |Completed.
Sation Building 20 35
(Vijay Nagar Side) De-Shuttering of Basement De-Shuttering of Basement
Slab (Part-l) & Staging of Slab (Part-l) & Staging of
Basement Slab Sqm 3015 850 850 2165 lPart-2 ) with Shuttering &(Part-2 ) with Shuttering &
Reinforcement work is in Reinforcement work is in
progress. progress.
14/16 Column (PART-1) 14/16Column (PART-1)
14 37
Remaning Column Remaning Column
Ground Floor Column lst lift Nos 14
Shuttering &Reinforcement Shuttering &Reinforcement
work is progress work is progress
1
13h1224
Project Vianagement Services for Development /Re-Development /Major l pgradation of Ghaziabad Raifway Station under Delhi Divísion of Northern Railway
Daily Progress Report as on Date :- 13-12-2024
sCOPE Previous Progress Balance to be Labour Details dated 13-12 - 2024
Location Description of werk Unit Work On Cumulative Previous day Activities Total
No. done Skilled L-Skilled
Done 12.12.24 Today Activities Labour
1 11 14
Painting 1st coat Sqm 18000 7780 200 7980 10020 Putty Ist Coat Putty Ist Coat
AAC Block Work Cum 712 369 0 369 343 No Activity No Activity
630
8th Floor slab casted on 8th Floor slab casted on
Slab Sqm 630 630
11.12.2024 11.12.2024
Staff Quarter Ty pe-III Column Nos 449 449 449 0 50/50 Terrace Floor Column 50/50 Terrace Floor Column
Tower-2
|Casted Casted
Jaelh
2
Project Management Senices for Development /Re-Development /Major Upgradation of Ghaziabad Railway Station under Delhi Division of Northern Railway
Daily Progress Report as on Date:- 13-12-2024
Lecation Description of work Unit
SCOPE PreviousProgress
Work on Cumulative
Balance to be
Prevlous day Activities
Labour Details dated 13-12 - 2024
Total
No. done Today Activities
Done 12.12.24 SkilledUn-Skilled Labour
9 I4
AAC Block Work Cum 712 161.2 161.2 550.8 No Activity No Activity
Painting Ist coat Sqm 1868 980 0 980 888 No Activity No Activity
Door & Window Nos 20 20 20 No Activity No Activity
Sub Station
(City Side) 0 0
Boundary wall Footing Nos 33 11 11 22 No Activity No Activity
3
(3)
Project \Management Sen ices for Development /Re-Devclopment /Major Ipgradation of Ghaziabad Railway Station under Dellhi Division of Northern Railway
Daily Progress Report as on Date :- 13-12-2024
PreviousProgress Labour Details dated 13-12 - 2024
Location SCOPE Balance to be
Deseription of work Unit Work on Cumulative Previous day Activitles Total
No. done
Today Activities SkilledUn-Skilled
Done 12.12.24 Labour
4 6 12 13 14
IgistrITE Dutung
Foundation Nos 14 0 0 14
Excavation work is under Excavation work is under
|progress. progress.
FOB A ( City Side) 2 2
Pedestal Nos 46 0 0 46 No Activity No Activity
Total 53 75 128