Concrete_Work_Method_Statement
Concrete_Work_Method_Statement
This method statement outlines the procedure for all concrete works, including preparation, mixing,
placement, compaction, curing, and quality control to ensure compliance with project specifications
and standards.
---
#### **Materials**
#### **Equipment**
- Concrete batching plant or mixers
- Concrete pumps
---
- Ensure all necessary drawings and specifications are approved and available on-site.
- Inspect and prepare formwork to ensure it is clean, properly aligned, and sufficiently supported to
- Place reinforcement steel as per design and ensure proper spacing, cover, and alignment.
- Verify the quality of cement, aggregates, water, and admixtures by reviewing test certificates and
on-site sampling.
- Ensure materials comply with the approved design mix and relevant standards.
- Conduct a trial mix to verify the workability, strength, and durability of the concrete.
- Confirm the mix design achieves the required slump and compressive strength.
---
- Transport concrete to the site using appropriate equipment (trucks, wheelbarrows, etc.).
---
### 5. **Concrete Placement**
- Place concrete within the formwork in layers not exceeding 300 mm to avoid segregation.
- Begin placement at one end and progress systematically to avoid cold joints.
- Ensure the concrete flows around reinforcement and embedded items without voids.
- Apply surface finishes (e.g., broom finish, float finish) as specified in the project requirements.
---
### 6. **Curing**
- Begin curing as soon as the concrete surface is firm enough to prevent damage.
- Use water curing (ponding or spraying) or curing compounds to maintain adequate moisture.
- Protect the concrete from extreme temperatures and drying winds during the curing period.
- Cure concrete for the period specified in the project documents, typically 7-28 days, depending on
---
- Take concrete cube or cylinder samples for compressive strength testing at 7 and 28 days.
- Identify and repair defects such as honeycombing, cracks, or voids using approved methods.
- Ensure repairs are completed before the final acceptance of the structure.
---
- Provide appropriate PPE (helmets, gloves, goggles, safety boots) for all workers.
- Maintain clear access routes and prevent unauthorized personnel in the work area.
---
- Dispose of concrete waste and wash water responsibly to prevent environmental contamination.
- Minimize dust generation by keeping the work area clean and damp.
- Avoid excessive noise and vibrations that may disturb the surrounding environment.
---
schedules.
- Provide a final report summarizing the work completed and compliance with specifications.