Rcd by Tc Chapter 3 Cc & Boq
Rcd by Tc Chapter 3 Cc & Boq
CONSTRUCTION CONTRACTS
AND CONTRACT DOCUMENTS
1
CONSTRUCTION CONTRACT
Contract is a signed document between two
parties (client & contractor) that binds the
contractor to do the job with the specified
requirements and the client to pay for it.
Contract in Construction industry may be
grouped in two categories:
A. competitive bid contracts
B. Negotiated contracts
2
COMPETITIVE BID CONTRACTS
Competitive Contracts are:
– Unit Price Contracts
– Lump sum contracts
Unit price Contracts
Total cost = estimated quantity X unit price in bid
(Bid is based on the price per unit of work)
Advantages
▪ Payment can be calculated easily
▪ freedom to alter the work of construction
▪ tenderers prices are on exactly the same basis
▪ plans & specifications do not need to be completed
in detail
3
Lump Sum Contract
• Bidding is done on a total amount of the works
specified.
• Drawings and specifications need to be completed in
every detail.
• Bill of quantities is provided not for pricing but to list
the activities to be done.
Advantages
• Avoid a lot of detailed accounting & measurement
• Owner does know the exact cost of the work
• The work is straightforward for the contractor and he
will try to complete it as early as possible to increase
his profit.
4
Disadvantages of Lump sum contracts
• alteration of project during construction causes troubles.
• plans & specifications must be comprehensive and
include every detail.
• contractor tends to use cheaper labour and materials.
5
NEGOTIATED CONTRACT
• It is also known as Cost + Contracts.
• Price = Cost + Profit
• profit is professional fee, subject to bidding and
negotiations.
• These contracts are useful when:
– complete plans & specifications are not available
– there is uncertainty to exact cost of the
construction
– possible wishes to change the work during
construction.
– in the case of emergency or war
6
TYPES OF NEGOTIATED CONTRACTS
a) Cost + Percentage of Cost Contracts
(outlawed in some countries)
b) Cost + Fixed Fee Contracts
c) Cost + Fixed Fee + Profit Sharing Contracts
d) Cost + Sliding Scale of Fees Contracts
e) Cost + Guaranteed Ceiling Price Contracts
7
a) Cost + percentage of Cost
(outlawed in some countries)
8
c) Cost + Fixed Fee + Contract with a
Profit Sharing
9
d) Cost + Sliding Scale of Fees
• Construction Cost Contractor's fee changes
proportionally to the actual cost of the work with a sliding
scale of fixed fee.
• However, a minimum fee is guaranteed to contractor.
• There is an incentive to the contractor to reduce the cost
of construction.
• It is good and preferable by the clients.
For example,
Construction Cost Contractor Fee
6.0x106 200,000 YTL
5.5x106 220,000 YTL
5.0x106 240,000 YTL
10
e) Cost + Guaranteed Ceiling Price
11
Sources of controversy in (Cost + Contracts)
15
FORMS OF CONSTRUCTION CONTRACTS (continued)
Terms of Contract
• definition of work, estimated cost, & the fee of contractor
• time for completion
• responsibilities of owner, engineer & contractor
• definition of reimbursable direct cost & overhead costs
• labour & material
• provisions for plant rental or purchase
• subcontractors
• method of compensation
• Changes
• Termination
• Accounting method and control
17
SPECIFICATIONS
18
SPECIFICATIONS (continued)
d) Practicability
➢ Use standard sizes and patterns as much as possible.
➢ Un-practicable requirements let the contractor to add
an extra safety factor to protect himself.
e)Preventation of conflicting requirements
➢ they are sources of error.
f) Fairness
➢ don't impose the contractor harsh & unfair conditions
➢ don't cancel difficulties from him.
➢ risk increases the cost of construction.
20
TYPES OF SPECIFICATIONS
1. General Provisions
2. Technical provisions
1. General provisions
➢ related to the whole work, to the standardized
materials.
➢ relate to control of the work & drawing reference.
22
TYPE OF SPECIFICATIONS (continued)
24
b) Specifications for workmanship
➢ specify the result, not the method
➢ specify tolerances on the results
➢ Define construction methods or procedures when
necessary for particular purposes
➢ limitations or restrictions on the contractor's method
for coordination the work.
➢ precautions to protect the work or adjacent property.
➢ methods of inspection and test
To be inserted by contractors
Recommended Method of Preparing BOQ
• Computer aided systems can be based on simple
database software or spreadsheets to sophisticated
softwares.
• Microsoft Excel Templates, Standard software such as
those listed on http://www.bidshop.org/
• Some demo versions of these are freely available from
the web.
• More sophisticated software are available.
Reasons for Bills of Quantities
• All tendering contractors base their prices on the same
information & therefore tenders are strictly comparable
(even if an error exists in the Bill)
• Contractors are saved the costly exercise of each
having to take off quantities for themselves.
• Bills provide a fair basis for valuing variations and
adjustments for the final account.
• Bills may provide a convenient basis for valuation of
certificated stage payments during the contract, before
the accurate re-measurement figures are available.
• Bills provide an approximate checklist for the
contractor to order materials and other resources.
• Bills can provide data for cost analysis for use in cost
planning of future projects.
RECOMMENDED ITEMISING METHOD
➢ For large works divide it into separate groups
➢ Each group is subdivided into various trades such as
Demolition work
Excavation & filling
Pipe laying
Roads
Concrete - insitu
reinforcement
shuttering
precast
Brick work
Masonry
Water proofing works
Steelwork and ironwork
Roofing
Carpentry Electrical work
Joinery Plumbing
Flooring Painting & fencing
plastering Glazing 36
Divide each of them into subdivisions.
For example, a bridge construction may be divided as:
➢ Piers
➢ Abutments
➢ Superstructure
➢ approach roads and surfacings
➢ miscellaneous
• In each item, another grouping is possible for trades
such as:
➢ Excavating
➢ compacting bottom soil
➢ Reinforcement
➢ Shuttering
➢ concreting etc
37
• A sense of proportion must be retained when billing.
( for a large work do not divide the activities in very
much details).
• Ex On a very large road construction project there
are some ancillary road side manholes.
• If they are almost similar, do not divide them into
many items to increase the number of items.
Such as
➢ excavations for manholes
➢ concreting manhole base
➢ brickwork to manhole walls
➢ providing and setting covers
39
COSTING
• Precise costing is almost impossible.
• Cost is just predicted.
• Costing is defined as, finding the cost of
separate classes of work, such as
bricklaying, shuttering etc.
• Costing involves finding charges for
➢ Labour
➢ Material
➢ Plant and
➢ Overhead
40
LABOR COSTING:
• Responsible foremen fills the time sheet showing
hours spent each day by each man on the various
types of work.
• Hours entered for a particular work is priced.
• So the labour cost for a particular work trade is
calculated.
• Difficulties:
• Overhead calculations
• Considering other wage payment, such as
time checker, night watch men, chainman, storekeeper
41
MATERIAL COSTING
42
PLANT COSTING
43
OVERHEADS
Site on costs
44
THANKS FOR YOUR ATTENTION
45
46