10-8-24 #Gatway-24 Daily Log

wateway

Uploaded by

betopapymolina
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

3940 E.

Miraloma Ave
Anaheim, California 92806
Phone (714) 577-8060
Fax (714) 577-8064
www.facilitybuilders.com

Daily Log
Project: Gateway Energy Storage Date: 10/8/2024
Foreman: Shawn Cole Job#: GES-950-24

Day: Monday Tuesday Wednesday Thursday Friday Saturday Sunday

Weather Conditions:

Temperature at 6:00am – 63 degrees Temperature at 2:30pm – 76 degrees


Clear Mist Rain Overcast Wind 10-20 (MPH)

Accidents or Safety Issues Today: YES NO XX


If yes is checked, attach copy of accident report or safety violation

Subcontractors on Site:
1. FBE 10 6:00AM-4:30PM 6.
2. Bragg 4 6:00AM-4:30PM 7.
3. 8.
4. 9.
5 10.

Equipment on Site:
Rental of Equipment; What? From who? For how long?

(4) 66’ Boom Lifts, (2) 12k Reach Fork, (1) Truss Boom, (1) 3 yard fork bucket, (1) water
truck, PAPE’ Rentals. (1) FBE job trailer, (1) FBE transport trailer, (1) FBE dump hopper. (1)
90 tn. crane, (1) 120 tn. crane, Bragg 9-24-24. (4) 20’ roll off dumpsters, Edco Disposal.

Contractual Items/ Delays to Schedule:


 Were you prevented from doing work on any part of the project due to circumstances
beyond your control?
YES NO
Explain:

 Were you required to do work outside the requirements of the project?


YES NO
Explain:

Did you perform work for a subcontractor or material supplier that should be back-
charged?
YES NO
Explain:

List all Erectors on the jobsite:


1. Shawn Cole (Foremen)
2. Jaime Avina (Foremen)
3. Juan Godoy
4. Johnathan Gonzalez
5. Gabriel Livas
6. Donovan Toliver
7. Bodie Johnson
8. Guilibaldo Diaz
9. Edgar Melgarejo
10. Ceaser Hernandez

Work Accomplished:

1. Attend the REV morning safety briefing.


2. Remove the middle girt from the South two bays on the West wall.
3. Work on removing the Novec pipes, light fixtures, and A/C ducting from the south two
bays.
4. Finish removing the two bays of roof decking on the Southeast side of the roof.
5. Remove half of the Southeast A/C curb.
6. Water down the dirt parking lot with the water truck.
7. Dispose all of the removed metal and trash in the designated dumpsters.
8. Clean up all the working areas.

Notes:

1. 10-7-24 We have been directed by REV to stop removing the roof decking after two
bays on each side of the roof. After that, they want us to remove all of the mechanical
members hanging below the purlins.

Pending Items:
Scheduled for: 10/9/2024

FBE Erectors: 10 men

Visitors:

1. Holli with Veolia was onsite today.

Inspections:

Signature: Shawn Cole