10-8-24 #Gatway-24 Daily Log
10-8-24 #Gatway-24 Daily Log
Miraloma Ave
Anaheim, California 92806
Phone (714) 577-8060
Fax (714) 577-8064
www.facilitybuilders.com
Daily Log
Project: Gateway Energy Storage Date: 10/8/2024
Foreman: Shawn Cole Job#: GES-950-24
Weather Conditions:
Subcontractors on Site:
1. FBE 10 6:00AM-4:30PM 6.
2. Bragg 4 6:00AM-4:30PM 7.
3. 8.
4. 9.
5 10.
Equipment on Site:
Rental of Equipment; What? From who? For how long?
(4) 66’ Boom Lifts, (2) 12k Reach Fork, (1) Truss Boom, (1) 3 yard fork bucket, (1) water
truck, PAPE’ Rentals. (1) FBE job trailer, (1) FBE transport trailer, (1) FBE dump hopper. (1)
90 tn. crane, (1) 120 tn. crane, Bragg 9-24-24. (4) 20’ roll off dumpsters, Edco Disposal.
Did you perform work for a subcontractor or material supplier that should be back-
charged?
YES NO
Explain:
Work Accomplished:
Notes:
1. 10-7-24 We have been directed by REV to stop removing the roof decking after two
bays on each side of the roof. After that, they want us to remove all of the mechanical
members hanging below the purlins.
Pending Items:
Scheduled for: 10/9/2024
Visitors:
Inspections: