Notes-1
Notes-1
Interdependent
Scheduling Budgeting
Scheduling is all
about the time
frame!!!
4
How to prepare Project Schedule??
Typical
PERT/CPM formats/methods Gantt
Networks of preparing a Charts
Project Schedule
PERT/CPM Networks
Convenient analytical and visual techniques of project
scheduling which have proven to be extremely valuable in
assisting the PM in managing the projects.
PERT stands for Project Evaluation and Review
Technique developed in late 1950’s by the US Navy. The technique was
developed and used in conjunction with the planning and designing of the
Polaris missile project.
CPM stands for Critical Path Method which was developed (also in
late 1950’s) by DuPont Company and applied first to the construction projects in
the chemical industry.
Difference between PERT/CPM Networks
PERT and CPM are very similar in their approach. However, two
distinctions are usually made:
PERT CPM
In PERT, three estimates are used to
In CPM, there is only one
form a weighted average of the
estimate of duration.
expected completion time, based on
Therefore, CPM is a
a probability distribution of
deterministic tool.
completion times. Therefore, PERT is
considered a probabilistic tool.
PERT is basically a tool for planning CPM can be used to control the time
and control of time, with no ability of and at the same time allows an
cost estimation. explicit estimate of the project cost.
Similarities between PERT/CPM Networks
• Both methods employed networks to schedule and display task
sequences.
• Both methods identified a critical path of tasks that could not be
delayed without delaying the project.
• Both methods identified activities with slack (or float ) that could
be somewhat delayed without extending the time required to
complete the project.
While PERT and CPM used slightly different ways of drawing the
network of activities, anything one could do with PERT, one
could also do with CPM and vice versa. Therefore, in our
syllabus, we use the term “PERT/CPM” when referring to
scheduling network analysis.
The Framework of PERT/CPM
PERT and CPM both follow 6 basic steps:
AOA AON
(activity-on-arrow) (activity-on-node)
• Activity as arrows • Activity as node
• Events as nodes • Arrows only use to show
• Usually associated with PERT, technological link/relationship
therefore AOA a.k.a. ‘PERT • Usually associated with CPM,
Network Diagram’ therefore AON a.k.a. ‘CPM
Network Diagram’
Example 1: Understanding AOA & AON
Question: Draw an AON network and an AOA network for the project below.
Task/ Activity Predecessor
a -
b -
c a
d b
e b
f c, d
g e
S a c F
t i
f n Dummy
a
r d i ending node
t b s or dummy
h activity
e g
Source: Mantel Jr. et al. (2011)
Example 1: Understanding AOA & AON
Question: Draw an AON network and an AOA network for the project below.
Task/ Activity Predecessor
a -
b -
c a
d b
e b
f c, d
g e
Solution 2: AOA network Dummy task
c c
1 3
1 3
f
a f F a
i S F
S
t
n OR t d i
i a n
a 4 i
d s r b
r 2 4 s
t
b 2
h t
e g
h
e g
5 Source: Mantel Jr. et al. (2011)
Exercise
Milwaukee paper Manufacturing Inc. has long been delaying the expense of
installing air pollution control equipment in its facility. The environmental
Protection Agency (EPA) has recently given the manufacturer 16 weeks to
install a complex air filter system. The company has been warned that it may
be forced to close the facility unless the device is installed in the allocated
time. The Plant Manager wants to make sure that installation of the filtering
system progress smoothly on time. He has identified 8 activities that need to
be performed in order for the project to be completed, as in Table below:
Draw a) an AON network diagram and b) an AOA network diagram for the
project
Source: techsci.msun.edu
Solution (AON network diagram)
Source: techsci.msun.edu
Solution (AOA network diagram)
Source: techsci.msun.edu
Finding Critical Path & Critical Time
Activity Predecessor Duration (Days)
a - 5
b - 4
c a 3
d a 4
e a 6
f b,c 4
g d 5
h d,e 6
i f 6
j g,h 4
47
• Does this means that the project needs 47 days to complete activities a to j?
• Then, how do we know how long it will take to complete these activities??
OR
7 11 12 17 17 21
j 4
0 5 5 11 11 17 F
17 21 i
a 5 e 6 h 6 n
a – e – h – j : critical path
i
0 5 5 11 11 17
12 18 s
h
5 8
S i 6
t c 3 8 12
a 15 21
r 8 11 f 4
t
11 15
0 4
b 4
7 11
• Activities on the critical path cannot be delayed, because it
will cause the entire project to be delayed.
What about activities not
on the critical path? Can
they be delayed without
causing delay to the entire
project?
But for any activity NOT on the critical path, LF EF (and LS ES)
This difference causes the activity float or slack
5 9 9 14
d 4 g 5 Critical time
7 11 12 17 17 21
j 4
0 5 5 11 11 17 F
17 21 i
a 5 e 6 h 6 n
a – e – h – j : critical path
i
0 5 5 11 11 17
12 18 s
h
5 8
S i 6
t c 3 8 12
a 15 21
r 8 11 f 4 Float
t 0
11 15
0 4 7
3
b 4 2
0
7 11 3
3
0
Float = Slack = LS – ES = LF - EF 3
0
Exercise
Referring to the AON network diagram drawn in the previous exercise on the
Milwaukee Paper Project, a) calculate the float/ slack for each activity
b) determine the critical path and indicate it on the diagram c) determine the
critical time (project completion time).
Solution for a)
Gantt Chart
• A GANTT chart is a type of bar chart that illustrates a
project schedule.
• After the PERT/CPM analysis is completed, the
following phase is to construct the GANTT chart and
then to re-allocate resources and re-schedule if
necessary.
• GANTT charts have become a common technique for
representing the phases and activities of a project
work breakdown structure.
• It was introduced by Henry Gantt around 1910 –
1915.
Advantages
Simple
Good visual communication to others
Task durations can be compared easily
Good for scheduling resources
Disadvantages
Dependencies are more difficult to visualise
Minor changes in data can cause major changes in the chart