ABSTRACT
ABSTRACT
NAME OF WORK : CONSTRUCTION OF FOUR WHEELER PARKING OVER DRAINAGE AT SECTOR 11,
BEHIND GURUDWARA, KALAMBOLI, UNDER PANVEL MUNICIPAL CORPORATION.
ABSTRACT SHEET
Item
No.
Description UNIT QTY RATE AMOUNT
Detailed geological reports
Providing detailed geological reports of proposed site by maintaining
geotechnical investigation of structure stratification collecting soil, rock and
ground water samples for laboratory tests to arrive the foundation design
1 parameters . Rock properties such as type of rock, jointing fractures, etc.
complete with suggestion about the site foundation and remedies.
Cutting Trees
Cutting down trees including trunks and branches with girths above 270cm to
450cm and stacking the materials neatly with all lifts and lead of 1000m. as
3 directed and earth filling in the depression/pit if any. No. 12 3248.70 38984.40
Soil Excavation
Excavation for foundation in hard murum and boulders including shoring and
strutting, dewatering as necessary and disposing off excavated stuff as
directed etc. complete.
4 a) Upto 1.50m lift Normal Rate CUM 1460.56 300.30 438604.97
b) 1.50m to 3.00m lift, Add 10%
c) 3.00m to 4.50m lift, Add 20%
d) 4.50m to 6.0m lift, Add 30%
PWD SSR 2022-23, PG 91, I-12.06
Dewatering
Dewatering on BHP basis by using water pump including diversion of stream,
providing cofferdams, earthern bunds etc. as may be necessary for foundation
and other parts of the the works and pumping out water during and after
6 excavation as may be required by using 5.0 to 9.0 BHP pump etc. complete. HOUR 150.00 211.05 31657.50
(prior approval of Superintending Engineer will be necessary)
PCC
Providing and laying in situ / ready mix M-20 plain cement concrete of trap
/granite/quartzite/ gneiss metal for cast in citu piers, abutment, returns, wings
etc. including provision of "V" shaped false joints to form suitable panels on
the faces to approve design with compacting by vibrating and curing
complete, including plywood/steel form work centering ( excluding
dewatering by means of pump) and including bailling out water and curing
8 finishing in CM 1:3 etc. complete. as directed by engineer in charge basic CUM 98.00 9567.16 937581.55
rate shall be increased for height above 5..00 m in followinh manners
b) Height upto 5 M. (With Batch Mix Plant)
With fully automatic micro processor based PLC with SCADA enable with
fine agreegates of required specifications ( VSI sand finely washed etc )
i) Height up to 5 m, normal rate.
ii) Height 5 to 7.50 m, add 5 percent extra over basic rate.
iii) Height 7.50 to 10 m, 7.50 percent extra.
PWD SSR 2022-23, PG 142, I-17.43
Foundation Concrete
Providing and laying plain in situ / ready mix M-30 cement concrete of trap/
granite/quartzite/gneiss/crushed stone metal mechanically mixed, placed in
foundation and compacted by vibration including necessary bailing out water,
curing curing concrete batch mix plant / pan mixer with fine agreegates of
9 required specifications ( VSI sand finely washed etc ) (excluding dewatering CUM 346.00 8718.72 3016676.17
by pump) for 14 days RCC Grade.With Concrete Mixer
Pier
Providing and laying in situ / ready mix M-30 cement concrete of trap
/granite/quartzite/ gneiss metal for cast in citu R.C.C. solid piers,column etc .
including provision of V shaped false joints to form suitable panels on the
faces to approve design with compacting by vibrating and curing complete.
Including plywood/steel formwork, centering ( excluding dewatering by
10 means of pump) and including bailling out water and including CM 1:3 CUM 386.60 9246.92 3574828.62
curing complete.
a) Height upto 5 M. (With Concrete Mixer)
i) Height up to 5 m, normal rate.
ii) Height 5 to 7.50 m, add 5 percent extra over basic rate.
iii) Height 7.50 to 10 m, 7.50 percent extra.
iv) Over 10 m Height, add 10 percent extra for every 2.50m rise.
PWD SSR 2022-23, PG 144, I-17.49
Deck Slab
Providing and laying in situ / ready mix M-30 controlled cement concrete of
trap/ granite/ quartzite/ gneiss metal for RCC work in solid/ deck slab etc.
including ramming, vibrating, curing, formwork, centering and finishing in
cement plaster excluding reinforcement etc. complete. (with fully automatic
micro processor based PLC with SCADA enabled concrete batch mix plant /
pan mixer and fine agreegates of required specifications ( VSI sand finely
11 washed etc ) i) Height up to 5 m, normal rate. CUM 413.00 12013.67 4961644.57
Providing & Fixing in position, MS fabrication work using angles, sqr tubes,
c channels etc for various partition frame as per Design & Instructions &
Complete in all aspects . including all materials labour,finishing etc complete
13 KG 1320.00 89.25 117810.00
Junior Engineer