TDNaupada
TDNaupada
Tender -1
TENDER DOCUMENT
Work Name : Providing labour for Regulating water supply from Gaodevi,
Eternity, Tekadi Bunglow ESR in Naupada Prabhag Samiti Area
(2023-2024).
2024).
INDEX
Providing labour for Regulating water supply from Gaodevi,
Name of work :
Eternity, Tekadi Bunglow ESR in Naupada Prabhag Samiti Area
(2023-2024).
V. Declaration of Contractor 79 79
Tender form and relevant documents are not be sold /issued manually from
offices.
The date and time for online submission of envelopes shall be strictly followed in
all cases. The bidder should ensure that their tender is submitted online before
the expiry of the scheduled date and time. No delay on account of any cause will
be entertained. Tender(s) not submitted online will not be entertained.
If for any reason, any interested bidder fails to complete any online stages during
the complete tender cycle, department shall not be responsible for that and any
grievance regarding that shall not be entertained.
Tender shall be submitted in two Envelopes i.e. Technical Bid in Envelope-1 &
Price Bidin Envelope-2 through e-Tendering procedure only on
http://mahatenders.gov.in portal.
Tenderssubmitted withouttwoBidsystemsandbywithoute-Tendering
(http://mahatenders.gov.in) procedure shall be rejected.
The Two Bids offer must be submitted along withdocument(s) as per the
guidelines given in tender document by e-Tendering procedure only.
For technical bid, bidders has to make sure that there should not be any space or
special character in the file name. All the technical documents should be in .pdf
Or.rar format e.g. “Registration certificate.pdf” “Registration certificate.rar” is
wrong file name.The correct file name would be“registration_certificate.pdf”
“registration_certificate.rar”.
The documents uploaded in the technical bid will be scrutinized by the Evaluation
Authority as per the document asked in the tender notice and tender
document.The decision of the Tender Evaluation Authority shall be final in this
regard.
Do not use cut, copy or paste while data entry into the BOQ sheet.
Before uploading BOQ, kindly confirm that enter detail in BOQ hasbeen saved
correctly.
EMD Payment will be accepted by the E-tendering process only once while
Bidding.
It is important to note that, the bidder has to Click on the ‘Freeze BidButton’, to
ensure that he/she completes the Bid Submission Process.Bids which are not
frozenareconsidered as Incomplete/Invalid bids and shall notbe considered for
evaluation purposes.
For any queries relating to this eProcurement Portal, please call 24 x 7 Toll Free No.
1800-3070-2232.
DISCLAIMER
2. Every effort is being made to keep the Website upto-date and running
smoothly 24x7 by the Thane Municipal Corporation and the Service
Provider. However, Thane Municipal Corporation takes no responsibility,
and will not be liable for the website being temporarily unavailable due to
any technical issue at any point of time.
4. Tenderer must follow the timetable of e-tender in process and get their
activities of e –tender processes done well in advance so as to avoid any
inconvenience due to unforeseen technical problem, if any.
TENDER NOTICE
P a g e |1
PRESSNOTICE
नगर अिभयंता
ठाणे महानगरपािलका,
महानगरपािलका ठाणे.
ठामपा/ पीआरओ/पापु-
City Engineer,
Thane Municipal Corporation, Thane.
TMC/PRO/WS-HQ/163/2023-24
Date : 15/05/2023
Blank tender papers can be downloaded from the official e-tendering website of
TMC, https://mahatenders.gov.in from16.05.2023 to 24.05.2023 upto 16.00
hrs. Online tenders shall be received upto 16.00 hrs. on 24.05.2023 and will be
opened on 26.05.2023 at 16.00 hrs if possible in the presence of the willing
contractors or their representatives.
“Providing labour for Regulating water
1. Name of work :
supply from Gaodevi, Eternity, Tekadi
Bunglow ESR in Naupada Prabhag Samiti
Area (2023 – 2024)".
Electronic Tendering System, the Users may contact the 24 x 7 Toll Free
Telephonic Help Desk Number 1800-3070-2232. Mobile : +91-7878107985,
+91-7878107986 ,+ 91-7878007972 and +91-7878007973
14 All bidders are cautioned that tenders containing any deviation from the
contractual terms and conditions, specifications or other requirements are
liable to be rejected outright as non responsive.
15 The cost incurred by the contractor for preparation and submission of bid
shall not be reimbursed by the Thane Municipal Corporation in any case.
16. Municipal Commissioner, TMC, Thane reserves the rights to accept the
tender in full or in part or reject any or all tenders without assigning any
reason.
18.The Contractor shall pay the monthly wages to the labour as per the “Minimum
Wages Act” as described in the tender document.
19.The Contractor shall pay Bonus,Provident fund Contribution as per the current
Govt.Rules.
23.The Contractor shall fix the labours duty as per schedule given by TMC and it is
mandatory to do valve operation as per shedule.Other than valve operation no
other works shall be allowed to the contract labour or as specified by the
Engineer-in Charge.
City Engineer
Thane Municipal Corporation,Thane
CHAPTER II
DETAILED TENDER
NOTICE
CHAPTER-II
DETAILED TENDER NOTICE
1. NAME OF WORK:
2. INVITATION:
The Cost of Blank Tender form is to be submitted via online modeas per
the Tender Schedule.
7. PERIOD OF COMPLETION :
iv) Earnest Money in the form of Demand Draft, Cheque or any other
Mode other than prescribed above will not be accepted. Tenders of
those contractors who do not deposit Earnest Money online shall be
summarily rejected.
vii) Within seven days from the date of receipt by him of the letter of
having acceptance of his tender, the successful tenderer shall
furnish the required performance security deposit and initial
Security Deposit and attend the office of the City Engineer, Thane
Municipal Corporation, Almeda Road, Pachpakhadi Thane for
execution of the contract document. If the successful tenderer fails
to furnish Security Deposit or to execute the contract his earnest
money deposit shall be forfeited and the tenderer may be
disqualified from tendering for further works in the Thane Municipal
Corporation, Thane.
9. SECURITY DEPOSIT:
The tenderer offering rates lower than the estimated cost put to tender
shall have payAdditional Performance Security as per GR Ref. No. बीडीजी
2016/ . . 2/इमा.2 dated 12.02.2016.(Also refer Ref. No. saIeTI2017/ . .
8/इमा.2 dated 26.11.2018).
2. In case the tenderer offers the rates lower than 10% below the
estimated cost put to tender, tenderer shall have to pay
additional performance security deposit amounting to rebate
offered beyond 10%of the estimated cost of work in additional to
1% of estimated cost of work as per para 1 above.
Note:
1. For details and clarifications regarding Performance Security, GR
Ref. No. saIeTI2017/ . . 8/इमा.2 dated 26.11.2018 shall be referred
Validity of the offer will be 180 days from the date of opening of tender
documents and thereafter unless extended if required to do so, to this
consent will be taken from tederers who wish to do so.
procedure) :
15.1.1
Earnest money deposit of Rs.45,000/-(Rupees Forty five
thousand only) and tender document fees of Rs.2,360/-
(Rs. Two thousand three hundred sixty only) .
15.1.2 Details of other works Tendered for and in hand (as per
Form-I) with value of unfinished works on the date of
submission of this Tender.
15.1.3 List of Machinery and Plants (as per Form II) in position with
the tenderer individually
Technical Bid:
First of all EMD and tender fee submitted by all tenderers on line as per
E-tendering procedure shall be verified
iii) The City Engineer, Thane Municipal Corporation, Thane shall have
the right to revise or to amend the contract documents prior to
the last date of submission
vi) Income Tax, VAT, labourcess, Local Body Tax & other Taxes as
applicable and at the rate in force will be recovered from the
gross amount of each bill, whether for measured or advance
payment of each bill, and/or secured advance.
viii) Ten (10) percent of the total contract cost shall be earmarked for
final bill.
xiii) The City Engineer, Thane Municipal Corporation, Thane shall have
the right to revise or to amend the contract documents prior to
the date of receipt or opening of the tenders.
xiv) The Contractor shall make at his own expenses all preliminary
arrangements including site clearance etc. immediately after the
contract is awarded to him.
xv) Similarly the Contractor will have to make his own arrangement
at his cost for supply of electricity and water for camp and work
site as may be necessary and he will not be entitled to any extra
payment whatsoever in this regard.
FORM-I
Sr. Name Name Place Work in hand Antici Works tendered for Remarks
No. of the and &Cou Ten Cost pated Esti Date Stimulat
work address ndry dere of date mat when ed date
of the d remai of ed decis or
Organisat Cost ning compl cost ion is period
ion of work etion exep of
whom ected complec
the work tion
was done
1 2 3 4 5 6 7 8 9 10 11
FORM-II
FORM - III
FORM -IV
2
Tot
al :
FORM – V
Contractor’s signature
CHAPTER III
GENERAL
AND ADDITIONAL
CONDITIONS OF
CONTRACTS
CHAPTER-III
GENERAL AND ADDITIONAL CONDITIONS OF CONTRACT
The Thane Municipal Corporation has constructed a ESR and Sump. This
work comprises P/S Labour for operating daily valves.
(b) The contractor shall furnish sufficient plant and equipment and
labour as may be necessary to maintain the progress schedule. The
working and shift hours restricted to two shifts a day for operations
to be done under the supervision shall be such as may be approved
by the Engineer Night work which requires supervision shall not be
permitted except when specifically allowed by the Engineer-in-
charge each time, if requested by the Contractor. The Contractor
shall provide necessary lighting arrangements etc. for night work,
as directed by the Engineer-in-charge at it his own cost. The list of
plant & machinery proposed for the work if found inadequate to
meet with target in that case , contractor will have to mobilized
additional plant, equipment & manpower to achieve target. No extra
cost will be paid for such arrangement for the reason because the
contractor has himself assessed equipment to be mobilized for the
work.
(c) Further the contractor shall submit the progress report of work at
intervals of one month or as may be specified by the Engineer-in-
charge
will not alter this position. The handing over by the contractor and taking
over by the Engineer-in-charge or his authorised representative will be
always in writing, copies of which will be going to the Engineer-in-charge
or his authorised representative and the contractor duly signed by both
the parties.
2.13 Co-ordination:
When several agencies for different sub-works or the Project are to work
simultaneously on the project site there must be full co-ordination
and co-operation between different contractors to ensure timely
and smooth completion of the project as a whole. The schedule
dates for completion specified in each contract shall therefore, be
strictly adhered to. No single contractor shall take or cause to take any
steps or action that may cause, disruption discontent or disturbance of
work, labour or arrangements etc. of other contractors in the project
location. Any action by any contractor which the Engineer-in-charge in his
unquestioned discretion may consider as infringement of the above code,
would be considered as a breach of the contract conditions and shall be
dealt with as such.
2.14 Payments:
The contractor must understand clearly that the rates quoted are for
completed work and include all costs due to designs, proof checking,
labour, scaffolding, plant, machinery, supervision, electric charges, water
supply charges, royalties, LBT, VAT and any other tax, and shall also
include all expenses to cover the cost of night work if and when required
and no claim for additional payment beyond the prices or rates quoted will
be entertained.
Contractor will have to submit all relative data like levels, registers etc.,
required test reports, respective cross sections along with procedure of bill
recording. Failing of which claim of payment will not be entertained.
No delay in start or continuation of further work shall be accepted due to
lack of fund or delay in payment to the contractor.
site, leaving the site clear of all materials within the period of 7 days from
the date of completion of work. In case of failure to do so the site office
will be demolish without any intimation to the contractor at the risk and
cost and no request for compensation will be entertained.
3. SAFETY MEASURES AND AMENITIES:
The contractor shall take all necessary precautions for the safety of the
workers and preserving their health while working in such job as require
special protection and precaution. The following are some of the
requirements listed. The contractor shall also comply with directions
issued by the Engineer-in-charge in this behalf from time to time and at
all times.
3.1.3 Taking such normal precaution like providing handrails at the edges of the
floating platform or barges not allowing nails or metal parts or useless
timber to spread around etc.
3.1.4 Supporting workmen with proper belt ropes etc. when working on any
masts, cranes, grabs, hoist, dredgers etc.
3.1.5 Taking necessary step, towards training the workers concerned in the
use of machinery before they are allowed to handle it independently and
taking all necessary precautions in and around the areas where machine
hoists and similar units are working.
3.1.6 Taking necessary precautions for the prevention from live electrical
cables.
3.1.8 Providing sufficient first aid facility at the work site to render immediate
first aid treatment in case of accidents due to suffocations, drowning and
other injuries.
3.1.10 Providing full length gum boots, leather hand gloves with fire proof apron
to cover the chest and back, reaching upto knees and protective goggles
for the eyes to the labourers working with hot asphalt handling, vibrator
in cement concrete and also where use of any or all these items is
beneficial in the interest of health and well being of the labourers in the
opinion of the Engineer.
3.2 Explosives:
The contractor shall at his own expenses construct and maintain proper
magazines, if such are required for the storage of explosives for use in
connection with works, and such magazines being situated, constructed
and maintained in accordance with Government Rules and Relevant legal
provisions applicable in that behalf. The contractor shall at his own
expenses obtain such licence or licences as may be necessary for storing
and using explosives. Notwithstanding that the location etc. for storage
of explosives are approved by the Engineer, the Government shall not
be incurring any responsibility whatever in connection with storage and
use of explosive on the site or any accident or occurrence whatsoever in
connection therewith, all operations in or for which explosives are
employed being at the risk of contractor and upon his sole responsibility
and the contractor hereby gives to government an absolute indemnity in
respect thereof.
3.6 Indemnity:
The Contractor shall indemnify the Thane Municipal Corporation all
actions, suits, claims and demands brought or made against him in
respect of anything done or committed to be done by the Contractor in
execution of or in connection with the work of this contract and against
any loss or damage to the Government in consequence of any Suit or
action being brought against the contractor for anything done or
committed to be done during execution of the work of this contract.
3.7.2 The contractor shall not employ in connection with the works any person
who has not completed his eighteenth year of age.
(2) The number of female workers who have been allowed benefit
under Maternity Benefit Act, 1961 or Rules made thereunder and
the amount paid to them.
3.7.5 The contractor shall pay to the labour employed by him either directly or
through sub-contractor wages not less than fair wages as defined in the
contract labour regulations as contained hereinafter in regards to all
matters provided therein.
3.7.6 The contractor shall comply with the provisions of the payment Wages
Act, 1936, Minimum Wages Act, 1948, Employees Liability Act, 1937,
Workmen’s Compensation Act, 1923, Industrial Disputes Act, 1947 and
the Maternity Benefit Act, 1961, the contract Labour (Regulation &
Abolition) Act, 1970, and the Interstate Migrant workman (Regulation of
employment and conditions of service) Act, 1979, or any modification
thereof or any other law relating thereto and rules made thereunder from
time to time.
3.7.7 The contractor shall indemnify Thane Municipal Corporation payments to
be made under and for the observance of the Regulations aforesaid
without prejudice to his right to claim indemnify from his sub-
contractors.
3.7.8 The decision of the Engineer-in-charge in matters relating to the reports
from the Inspecting Officers, as defined in “Contractor Labour
3.10 Nuisance:
3.10.1 The Contractor shall not at any time do,cause or permit any nuisance on
the site or do anything which shall cause unnecessary disturbance or
inconvenience to owners, tenants or occupants of other properties near
the site and to the public generally.
3.10.2 The contractor shall save, harmless and indemnify the Department in
respect of all claims, demands, proceedings damages, costs, charges and
expenses what so ever arising out of or in relation to any such matters in
so far as the contractor is responsible therefore.
3.13 (I)Number of hours of work, which shall constitute normal working day:
The number of hours, which shall constitute a normal working day for an
adult, shall be 9 hours. The working day for an adult worker shall be so
arranged that inclusive of intervals, if any, for rest shall not spread over
more than twelve hours on any day. When an adult worker is made to
work for more than 9 hours on any day or for more than forty eight hours
Every worker shall be given a weekly day of rest, which shall be fixed and
noticed at least 10 days in advance. A worker shall not be required or
allowed to work on the weekly rest day unless he has or will have a
substituted rest day on one of the five days immediately before or after
the rest, provided that no substitution shall be made which will result in
the worker working for more than 10 days consecutively without a rest
day for a whole day.
Where in accordance with the foregoing provision a worker works on the
rest day and has been given a substitute rest day he shall be paid wages
for the work done on the weekly rest day at the overtime rate of wages.
seventh day or tenth day from the end of the wage period
according as number of workers does not exceed one thousand or
exceeds one thousand, respectively.
(iii) When employment of any worker is terminated by or on behalf of
the Contractor, the Wages earned by him shall be paid before
expiry of the day, succeeding the one on which his employment is
terminated.
(iv) Payment of wages shall be made at the work site on a working day
except when the work is completed before expiry of the wage
period, in which case final payment shall be made at the work site
within 8 hours of last working day and during normal working time.
(b) Deductions for absence from duty i.e. from the place or the places
where by the term of his employment he is required to work. The
amount of deduction shall be proportionate to the period for which
he was absent.
(e) Any other deduction, which the Department may form time to time,
allows.
(iv) The total amount of fines which may be imposed in any one
wage period on a worker shall not exceed an amount due to
him in respect of that wage period.
(vi) The Contractor shall maintain both in English and the local
Indian Language a list, approved by the Chief Labour
Commissioner clearly stating the acts and commission for
which penalty or fine may be imposed on a workmen and
3.22 Enforcement:
(i) The Inspecting Officer shall either on his own motion or on a
complaint received by him carry out investigations and send a
report to the Engineer-in-charge specifying the amounts
representing workers dues and amount of penalty to be imposed on
the Contractor for breach of these Regulations, that have to be
recovered from the Contractor, including full details of the
recoveries proposed and the reasons therefore. It shall be
obligatory on the part of the Engineer-in-charge on receipt of such a
report to deduct such amounts from payments due to the
Contractor.
(ii) The penalty for every default and breach of these Regulations shall,
however be a sum not exceeding Rs.5000/-. In the event of the
Contractor’s default continuing in this respect, the penalty may be
enhanced to Rs. 50/- per day for each day default subject to
maximum of one percent of the estimated cost of the work
put to tender.
3.28 Amendments:
Thane Municipal Corporation may from time to time add to or amend
these regulations and issue such directions as it may consider necessary
for the proper implementation of these regulations or for the purpose of
removing any difficulties which may arise in the administration thereof.
FORM - I
REGISTER OF WORKMEN
(Regulation - 7)
v) Duration of the :
Contract
Sr. Name & Age Father’s/ Nature of Permanent Home
No. Surname & Husband’s Employment / Address of
of the Sex Name Designation Employees
Worker
1 2 3 4 5 6
FORM - II
EMPLOYMENT CARD
(Regulation - 8)
i) Name and sex of worker :
ii) Father's/ Husband's Name :
iii) Address :
iv) Age and Date of Birth :
v) Identification Marks :
Particular's of next of kin (wife/husband) and children, if any, or of dependant
next of kin in case the worker has no wife/husband or child.
Name :-
Full address of Dependants :
(Specify village,District& State)
N.B. For a worker employed at one time on piece work basis and at another on
daily wages relevant entries in respect of each of employment should be made
separately.
FORM - III
REGISTER OF WAGES CUM MUSTER ROLL
(Regulation)
Basic D.A. & Basic D.A. & Date No. Overtime paid
8 9 10 11 12 13 14 15
es sion of
worker
16 17 18 19 20 21 22 23 24
FORM - IV
(Regulation 9)
ii) Place :
_________________________________________________________
________________
2) Nature of Employment :
3) Wage period :
7) Overtime wages :
3.30 Definitions:
(a) Work Place: “Work Place” means a place at which on an average 20
or more workers are employed.
(b) Large workplace: “Large Work Place” means a place at which on
average 500 or more workers are employed.
At large work places where hospital facilities are not available within easy
distance of the works, first-aid posts shall be established and be run by a
trained compounder.
Where large work places are remotely situated and far away from regular
hospitals indoor wards shall be provided with one bed for every 250
employees.
Where large work places are situated in cities, towns or in their suburbs
and no bed are considered necessary owing to the proximity of city to
town hospitals, suitable transport shall be provided to facilitate removal of
urgent cases to those hospitals. At other work places some conveyance
facilities shall be kept readily available to take injured person or persons
suddenly taken seriously ill, to the nearest hospital.
A reliable pump shall be fitted to each covered well, the trap door shall be
kept locked and opened only for cleaning or inspection which shall be
done at least once a month.
No. of Seats
(a) Where number of persons does not exceed 50. 2
(b) Where number of persons exceeds 3
The Contractor shall, at his own expenses, carry out all instructions issued
to him by tile Engineer-in-charge to effect proper disposal of excreta and
other conservancy work in respect of contractor’s work people or
employees on the site. The contractor shall be responsible for payment of
any charges which may be levied by municipal authority for execution of
such work on his behalf
3.40 Crèches:
At a place at which 20 or more women workers are ordinarily employed,
there shall be provided at least one hut for use of children under the age
of 6 years, of such 1 woman. Huts shall not be constructed of a standard
lower than that of thatched roof, mud floor and walls with wooden planks
spread over mud floor and covered with matting.
Huts shall be provided with suitable and sufficient opening for light and
ventilation. There shall be adequate provision of sweepers to keep the
places clean. There shall be two “Dais” in attendance. Sanitary utensils
shall be provided to the satisfaction of local medical, health and municipal
or cantonment authorities. Use of huts shall be restricted to children, their
attendants and mothers of children.
Where the number of women workers is more than 25 but less than 50,
the Contractor shall provide at least one Hut, one Dai to look after the
children of women workers, size of the crèche (s) shall vary according to
the number of women workers employed. Creche(s) shall be properly
maintained and necessary equipment like toys etc., provided.
3.41 Canteen :
A cooked food canteen on a moderate scale shall be provided for the
benefit of Workers wherever it is necessary.
3.42 Planning sitting and erection of the above mentioned structures shall be
approved by the Engineer-in-charge and the whole of such temporary
accommodation shall at all times during the progress of the works be kept
tidy and in a clean and sanitary condition to the satisfaction of the
Engineer-in-charge and at the Contractor’s expenses. The Contractor
shall confirm Generally to sanitary requirements of local medical, health
and municipal or cantonment authorities and at all times adopt, such
precautions as may be necessary to prevent soil pollution of the site. On
completion of the works the whole such temporary structures shall be
cleared away, all rubbish burnt, excreta or other disposal pits ortrenches
filled in and effectively scaled off and the whole of site left clean and tidy
to the entire satisfaction of the Engineer-in-charge at the Contractor’s
expenses.
3.45 Enforcement:
The inspecting Officer or any other officer nominated in this behalf by the
Engineer-in-charge shall report to the Engineer-in-charge all cases of
failure to comply with the provisions of these Rules either wholly or in
part, specifying the penalties to be levied for such breach of these
provisions.
4 DEFINITIONS:
Unless excluded by or repugnant to the context.
(a) The expressions “TMC” and “Owner” as used in the tender papers
shall mean the Thane Municipal Corporation, Thane.
(b) The expression “Department” as used in the tender papers shall
mean the Public Works Department of the Thane Municipal
Corporation, Thane.
(c) The expression “City Engineer” as used anywhere in the tender
papers shall mean City Engineer, of the Public Works Department,
Thane Municipal Corporation Thane who is designated as such for
the time being in whose jurisdiction the work lies or the officer to
whom the function of the Engineer-in-charge may be subsequently
transferred.
(d) The expression Plant as used in the tender papers shall mean every
machinery necessary or considered necessary by the Engineer-in-
charge to execute; construct complete and maintain the works and
used in altered, modified, substituted and additional work, ordered
in the time and manner herein provided and all temporary materials
and special and other articles of appliances of every sort, kind and
description whatsoever intended or used therefore.
(e) “Drawing” shall mean the drawings referred to in specifications and
any modifications Of such drawings approved in writing by Engineer
and such other drawings as may from time to time be furnished or
approved in writing by the Engineer-in-charge.
(f) “City Engineer's Representative” shall mean an assistant of the City
Engineer i.e. rank of City Engineer who will be called as Engineer-
in-charge of work notified in writing to the Contractor by the City
Engineer.
(g) The “Site” shall mean the lands and /or other places on, under, in
or through which the work is to be executed under the contract
including any other lands or place which may be allotted by Thane
Municipal Corporation or used for the purpose of contract.
(h) Part(s) thereof as the case may be and shall include all extra or
additional, altered or substituted works as required for performance
of the Contract.
(i) The “Contract” shall mean the notice of tender, the sealed quotation
and the tender documents including the tender and acceptance
thereof together with the documents referred to therein, and the
accepted conditions with annexure mentioned therein including any
special conditions, specifications, designs, drawings, priced
schedule/bill of quantities and schedule of rates. All these
documents taken together shall be deemed to form one contract
and shall be complementary to one another.
(j) The “Contractor” shall mean the individual or firm or company
whether incorporated or not, undertaking the work and shall include
legal representative of such an individual or persons comprising
such firm or company as the case may be and permitted, assigns of
such individual or firm or company.
(k) The “Contract sum” shall mean the sum for which the tender is
accepted.
(l) A “Day” shall mean a day of 24 hours from midnight to midnight
irrespective of the number of hours worked in that day.
(m) A “Week” shall mean seven consecutive days without regard to the
number of hours worked in any day in that week.
(n) “Excepted Risks” are risks due to riots (otherwise than among
contractor’s employees) and civil commotion (in so far as both
these are un-insurable) war (whether declared or not), invasion, act
of foreign enemies, hostilities, civil war, rebellion, revolution,
insurrection, military or usurped power, any acts of God, such as
earthquake, lightening and un-precedent floods over which the
contractor has no control.
(o) “Temporary works” shall mean all temporary works of every kind
required in or about the execution completion or maintenance of
the works.
(p) “Urgent works” shall mean any measures which, in the opinion of
the Engineer-in-charge, become necessary during the progress of
the works to obviate any risk or accident or failure or which become
necessary for security of the work or the persons working, thereon.
(q) Where the context so requires, word importing the singular number
only also include the plural number and vice-versa.
5 LEVELLING INSTRUMENTS:
If measurements of items of the work are based on volumetric
measurements calculated from levels taken before and after construction
of the item, a sufficient number of levelling instruments, staves, tapes etc.
will have to be kept available by the contractor at road site of work for
this purpose including theodolite. All instruments must be kept at road
site available for use to TMC staff. Lack of such levelling instruments,
staves, tapes etc., in required numbers may cause delay in measurements
and the work. The contractor will therefore to keep sufficient number of
these readily available at site.
6. COLLECTION OF MATERIALS:
(i) The contractor or piece worker shall make his own arrangements to
obtain the material from existing or a new quarries but before
starting collection the quarry shall be got approved by the
Engineer-in-charge or his representatives. The contractor or piece
worker shall pay all royalty charges, compensation etc. No claims
or responsibility on account of any obstructions caused to execution
of the work by difficulties arising out of private owners of land, will
be entertained.
(ii) No material shall be removed from the land touching it without the
written permission of the Engineer-in-charge or his authorised
representative. If any material is obtained unauthorised from such
places, the contractor or piece worker shall have to make good the
7. MISCELLANEOUS
7.1 Rates shall be inclusive of Work Contract Tax, VAT, LBT and all other
taxes etc.
7.2 In case it becomes necessary for the due fulfilment of contract for the
contractor to occupy land outside the department limits, the contractor
will have to make his own arrangements with the land owners and to pay
such rent if any payable as mutually agreed between them.
7.3 The special provision in detailed specifications or wording of any item shall
gain precedence over corresponding contradictory provision, (if any), in
the M.O.R.T.H specifications, IRC Specifications, Maharashtra P.W.D.
Standard specifications where reference to such specifications is given
without reproducing the details in contract.
7.4 It is presumed that the contractor has gone carefully through the
M.O.R.T.H specifications, IRC Specifications, Maharashtra P.W.D. Standard
specifications (Red Book) and the schedule of rate and Studied the site
condition before arriving at rates quoted by him. Decision of the Engineer-
in-charge shall be final as regards interpretation of specification.
7.5 The collection and storage of construction materials at site shall be in such
a manner as to prevent deterioration intrusion, of foreign matter and to
ensure the preservation of their quality, properties and fitness for the
work. Suitable precautions shall be taken by the contractor to protect the
material against atmospheric actions, fire and other hazards. The
materials likely to be carried away by wind shall be stored in suitable
stores or with suitable barricades and where there is likely hood of
subsidence of soil, such heavy materials shall be stored on paved
platforms.
7.6 The contractor shall be responsible for making good the damages done to
the existing property or work during construction by his men.
7.7 If it is found necessary from safety point of view to test any part of the
structure, the test shall be carried out by the Contractor with the help of
the department at his own cost.
7.10 The rates for items shall also include the cost of preparation of designs
and drawings for temporary structures viz. formworks, temporary staging
etc.) and getting the same approved from Thane Municipal Corporation.
7.11 All measurements will be made in accordance with the methods indicated
in the elaborated in the Technical specifications, incorporated in the
tender document.
7.12 The details shown on drawing and all other information pertaining to the
works shall be treated as indicative and provisional only except for the
mandatory provisions.
7.13 Protection of underground telephone cable and aerial telephone wires and
Poles, transmission towers, electrical cables and water supplying lines is
the responsibility of the contractor.
During the execution of work, it is likely that the contractor may meet
with telephone cable, electrical cables, water supply lines, effluent pipe
line, oil pipe line, gas lines etc. it will therefore be the responsibility of the
contractor to protect them carefully. All such cases should be brought to
the notice of the Engineer-in-charge by the contractor and also to the
concerned Department. Any damage whatsoever done to these
cables and pipe lines by the Contractor shall be made good by him
at his cost.
8 LINING OUT:
The Contractor shall provide free of charge all labour and material and
instruments required for lining out, surveying, inspection decided by the
Engineer-in-charge as considered necessary for the proper and systematic
execution of the work.
12. TESTS:
12.1 The contractor shall at his own cost arrange to carry out the all tests of
materials, which are to be used on the work. The tests will have to be
carried out either in the field laboratory or in an approved laboratory
suggested by T.M.C.
12.2 Department will also carry out some of above mentioned tests
independently in Laboratory and testing charges thereof will be borne by
the contractor. Also the work portion where test results are not
satisfactory will have to be removed and redone at the cost of the
contractor.
13 FINAL BILL :
13.1 The contractor should submit final bill within one month after completion
of the work. At least 10% of the contract value shall be earmarked for
final bill. Disputed items and claims, if any shall be excluded from the bill
and settled separately later on.
13.2 Claims for extra work shall be registered within 30 days of occurrence of
the event. However, bills for these claims including supporting
data/details may be submitted subsequently to the Engineer-in-charge.
13.3 Bills for extra work or for any claim shall be paid separately apart from
the interim bills for the main work. The payment of bills for the main work
shall not be withheld for want of decision on the extras on claims not
covered in the stipulation of the contract. The work shall not be hold or
progress of work shall not be slowed down for payment of Bills for extra
work or claims. Appropriate action as per clause no. 2 of B-1 agreement
shall be taken and no claims for compensation on this account shall be
entertained.
14 ELECTRIC POWER:
15 PRELIMINARY ARRANGEMENTS:
15.3 The contractor shall at his own expenses engage watchman for guarding
the materials and plants and machinery and the work during day and
night against any pilferage or damages and also for prohibiting
trespassers or damage to them. Failing, Corporation may engage this
without intimation to contractor and payment will be recovered through
R.A. bills.
15.4 The Contractor shall have to make his own arrangements for water
required for watering the embankment or for any other purpose.
16. INSPECTION:
16.1 The contractor shall inform the Engineer-in-charge in writing when any
portion of the work is ready for inspection giving him sufficient notice to
enable him to inspect the same without affecting the further progress of
the work. The work shall not be considered to have been completed in
accordance with the terms of the contract until the Engineer-in-charge
shall have certified in writing to that effect. No approval of materials or
workmanship or approval of part of the work during the progress of
execution shall bind the Engineer-in-charge or in any way affect him even
to reject the work which is alleged to be completed and to suspend the
issue of his certificate of completion until such alternations and
modifications or reconstruction have been effected at the cost of the
contractor as shall enable him to certify that the work has been completed
to his satisfaction.
16.2 The contractor shall provide at his cost necessary ladders and such
arrangements as to provide necessary facilities and assistance for proper
inspection of all parts of the work at his own cost.
16.3 The contractor after completion of work shall have to clean the site of all
debris and remove all unused materials other than those supplied by the
Department and all plant and machinery, equipment, tools etc., belonging
to him within one month from the date of completion of the work, or
otherwise the same shall be removed by the Department at his cost and
the contractor shall not be entitled for payment of any compensation for
the same.
17 PLANT:
All constructional plant, provided by the contractor shall when brought on
to the site be deemed to be exclusively intended for the construction of
this work and contractor shall not remove the same or any part thereof
(say for the purpose of moving it from one part of the site to another or
the repairs etc.) without the consent in writing of the Engineer-in-charge
which shall not be unreasonably withheld.
therein) subject to the additional specification given for the relevant items
in IRC, P.W.D. specification and in the best workmen like manner.
20.2 While adopting the relevant number and pages for different items
of the M.O.R.T.H specifications for Bridges and Road Works or
P.W.D., Standard Specification Books, due care has been taken to
indicate correct number and page for the various items. However
if for some reasons or other it is noticed that the specification
numbers and pages quoted are not pertinent, the contractor is
bound to carry out the work in accordance with the correct
relevant specifications for the item or items from the standard
specification Book, after taking into account the description of the
items, scope and spirit of the work.
20.3 During the course of the execution, payment for certain items such as
R.C.C. works and the like which are done in stages, shall be made at part
rates which shall be decided by the Engineer-in-charge. Similarly in case if
certain component or components of an item are decided to be deleted,
payment for the remaining parts of the items shall be made at reduced
rates for such items which shall be decided by the Engineer-in-charge,
either on the basis of market rates or schedule rates or accepted tender
rates whichever are lowest for such component or components.
20.4 It is to be definitely and clearly understood that the specification
stipulated shall be rigidly enforced and no relaxation shall be allowed.
Extra charges or claims in respect of extra works shall not be entertained
unless they are clearly outside the scope of the item and its specifications
to which they relate or unless such works are ordered in writing by the
Engineer-in-charge and claimed for in specified manner before the same is
taken in hand.
21.2 Without limiting his obligations and responsibilities under clause 21.2 the
contractor shall insure in the joint name of the Thane Municipal
Corporation and the contractor against all loss or damage from whatever
cause (other than the Excepted Risks) for which he is responsible under
the terms of the contract and in Such manner that the Thane Municipal
Corporation and the contract are covered during the period of construction
of the works for loss or damage arising from a cause occurring prior to the
commencement of the damage caused by the Contractor in the course of
any operation carried Out by him for the purpose of complying with his
obligations under clause 20 of Printed B-1 Tender Form (regarding Defect
Liability).
(i) The works and the temporary works to the full value of such works
executed from time to time.
(ii) The materials, constructional plant and other things brought to site
by the in contractor to the full value of such material, constructional
plant and other things.
21.3 The Contractor shall indemnify and keep indemnified the Thane Municipal
Corporation against all losses and claims for injuries or damages to any
person of contractor & TMC supervising the work or any third party,
property whatsoever which may arise out of or in consequence of the
construction and maintenance of the works and against all claims,
demands, proceedings, damages, accidents, costs, charges and expenses
whatsoever in respect of or in relation thereto provided always that
nothing herein contained shall be deemed to render the contractor liable
for in respect of or to indemnify the Department against any
compensation or damage caused by “EXCEPTED RISKS”.
21.4 Before commencing execution of the work, the contractor shall, without in
anyway limiting his obligations and responsibilities under the conditions,
insure against any damage, loss or injury which may occur to any
property (including that of Department) or to any person (including any
employee of Department) by or arising out of carrying out of the Contract.
21.5 The contractor shall at all times indemnify the Department against all
claims, damages of compensation under the provisions of payments of
wages Act, 1936, Minimum Wages Act, 1948, Employment Liability Act,
1938, Industrial Disputes Act, 1947, and the Maternity Benefit Act, 1961
and Inter State Migrant Workmen (Regulation of Employment and
Conditions of Service) Act, 1979 or any modifications thereof or any other
law relating thereto, any rules made there under from time to time or as a
consequence of any accident or injury to any workmen or other person in
or about the works, whether in the employment of the contractor or not,
save and except where such accident or injury has resulted from any act
of the Department, their agents or servants and also against all costs,
charges and expenses or any suit, action or proceedings arising out of
such accident or injury and against all sum or sums which may with the
consent of the contractor be paid to compromise or compound any such
claim without limiting his obligation and liabilities as above provided the
contractor shall insure against all claims, damages or compensation
payable under the workmen’s Compensation Act, 1923 or , any
modifications thereof any other law relating thereto.
21.6 All the aforesaid insurance policies shall provide that they shall not be
cancelled till the Engineer-in-charge has agreed to their cancellation.
21.8 The Contractor shall ensure that similar insurance policies are taken out
by his sub-contractor (if any) and shall be responsible for any claims or
losses to department resulting from their failure to obtain adequate
insurance protection in connection thereof. The Contractor shall produce
or cause to be produced by his sub-contractors
(if any) as the case may be relevant policy or policies and premium
receipts as and when required by the Engineer-in-charge.
If the Contractor and/or his Sub-contractor (if any) shall fail to effect and
keep in force the insurance referred to above or any other insurance
which he/they may be required to effect under the terms of the contract
then in any such case department may without being bound and to effect
and keep in force any such insurance and pay such premium or premia as
may be necessary for that purpose and from time to time deduct the
amount so paid by the department from any money due or which may
become due to the contractor or recover the same as a debt due from the
contractor.
22 PRESERVATION OF PROPERTY:
The contractor shall take all reasonable precaution for the protection and
preservation of any or all existing road side trees, drains, sewers or other
surface drain pipes, conduits and any other structure under or above
ground which may be affected by the constructions, operations and which
in the opinion of the Engineer shall be continued in use without any
change. Safeguards taken by the contractors in this respect shall be got
approved by him from the engineer. However, if any of these objects is
damaged by reason of the contractor’s negligence, it shall be replaced or
restored to the original condition at his expense.
CHAPTER IV
SPECIAL CONDITIONS
OF CONTRACT
CHAPTER-IV
SPECIAL CONDITIONS OF CONTRACT
3 Documentation of records:
The work is to be executed on busy flyover portion. The bus trafficon the
bridge shall not be diverted during the progress of work. During the work
Necessary traffic signs and boards including provision of traffic cones etc.
for traffic diversion, roadwork in progress, etc. as directed should be
fixed by at the Contractors own cost. Failing which a penalty of
Rs. 5000/- per day shall be levied on contractor.
6 Preparatory arrangements:
7 Transportation of mix:
The bitumen mastic,duly preparedincludingaddition of coarse aggregates
at the manufacturing point, is to be transported over a long
distanceand delivered to the laying site, arrangements for its transport
shall be made in a towed mixer transporter with adequate provision for
heating and stirring so as to keep the aggregates and filler suspended
in the mix till the time of laying.
The contractor shall submit bills for measured quantities duly supported
with joint measurements along with copies of records of test results for
frequency as per specifications, accounts of bitumen purchase, use of
delivery challans of mix from plant to site etc. The City Engineer shall
9 Tenderer should note that, during the execution of works, debries etc.
which is dumped on the work place shall have to be removed
immediately as per direction of Engineer in charge, failing which the
same shall be got removed at the risk and cost of contractor.
10 The work shall have to be carried out under supervision and as directed
by TMC/ Consultant of TMC
11 Contactor shall provide one car (Tata Vista, Maruti Swift or equivalent)
with driver shall be provided execlusively for Supervisory staff of TMC
from the date of work order till completion of work. The running charges
viz. fuel, lubes etc. shall be borne by contractor. No separate of extra
payment shall be made on this account.
CHAPTER V
DECLARATION
OFCONTRACTOR
To,
Dear Sir,
I / We hereby declare that I / We are not black listed in any Govt. / Semi Govt. /
PSU/ ULB / Local Body organization and my / our Earnest Money Deposit / Additional
Performance Security Deposit / Security Deposit was never forfeited by any above
mentioned organisation.
AFFIDAVIT
1. I am liable for action under Indian Penal Code for submission of any false / fraudulent
paper / information submitted in envelope no.1.
2. I am liable for action under Indian Penal Code if during contract period and defect
liability period, any false information, false bill of purchases supporting proof of
purchase, proof of testing submitted by my staff, subletting company or by myself, I will
be liable for action under Indian Penal Code.
3. I am liable for action under Indian Penal Code if any paper are found false / fraudulent
during contract period and even after the completion of contract
(finalisation of final bill ).
(Signature of contractor)
(seal of company)
CHAPTER V
Signature of Contractor(s).
CHAPTER VI
AGREEMENT B-1
TENDER FORM
1. I/We hereby tender for the execution, for the Thane Municipal
Corporation, Thane (hereinbefore and hereinafter referred to as ‘TMC,
Thane’) of the work specified in the underwritten memorandum within
the time specified in such memorandum at*
__________________________________________________________
________________________________________________________
(*in figure as well as in words) percent below/above the estimated rates
entered in schedule “B” (memorandum showing item of works to be
carried out) and in, accordance in all respects with the specifications,
designs, drawings and instructions in writing referred to in rule 1 hereof
and clause 13 of the annexed conditions of contract and agree that when
materials for the work are provided by Dy. City Engineer, TMC, Thane
such materials and rates to be paid for them shall be as provided in
schedule “A” hereto.
MEMORAN DUM
2. I/We agree that this offer shall remain open for acceptance for a
minimum period of 180 days from the date of opening the same and
thereafter until it is withdrawn by me/us by notice in writing duly
addressed to the authority opening the tenders and sent by registered
post A.D. or otherwise delivered, at the office of such authority. The
Earnest Money in form of receipted bank challan No.________ date
_______________ is herewith forwarded. The amount of Earnest Money
shall not bear interest and shall be liable to be forfeited to the TMC,
Thane should I/We fail to (i) abide by the stipulation to keep the offer
open for the period mentioned above or (ii) sign and complete the
contract documents as required by the Dy. City Engineer and furnish the
security deposit as specified in item (d) of the memorandum contained in
para - 1 above within the time limit, laid down in clause (1) of the
conditions of the contract. The amount of earnest money may be
adjusted towards the security deposit or refunded to me/us if so desired
by me/us in writing unless the same or any part thereof has been
forfeited as aforesaid.
3. Should this tender be accepted I/We hereby agree to abide by and fulfill
all the terms and provisions of the conditions of contract annexed hereto
so far as applicable and in default thereof to forfeit and pay to TMC,
Thane the sum of money mentioned in the said condition.
Contractor _____________________________________________
Name & Address _____________________________________________
_____________________________________________
Dated ___________ day of ___________ 2022 ___________
(Witness) _____________________________________________
Name & Address _____________________________________________
_____________________________________________
Occupation _____________________________________________
Officer
__________________________________________________________
Dated _____________________ day of _____________ 2016.
City Engineer
Thane Municipal Corporation, Thane
CHAPTER: VI – (b)
CONDITIONS OF CONTRACT
Security CLAUSE 1 : The person / persons whose tender may be accepted (hereinafter
Deposit
called “the contractor” which expression shall unless excluded by or repugnant to
the context include its heirs, executors, administrators, and assigns) shall (A) within
10 days (which may be extended by the Engineer concerned upto 15 days if he
thinks fit to do so) of the receipt by him of the notifications of the acceptance of his
tender, deposit with the Engineer (if deposited for more than 12 months) of sum
sufficient which will make up the full security deposit specified in the tender or (B)
(Permit T.M.C. at the time of making any payment to him for work done under the
contract to deduct such sum as will amount to five percent of all moneys so payable
such deductions to be held by the T.M.C. by way of security deposit) provided
always that in the event of the contractor depositing a lump sum by way of security
deposit as contemplated at (A) above, then and in such case, if the sum so deposited
shall not amount to five percent of the total estimated cost of the work, it shall be
lawful for T.M.C. at the time of making any payment to the contractor for work
done under the contract to make up the full amount of two and a half percent by
deducting a sufficient sum from every such payment as last aforesaid until the full
amount of the security deposit is made up. All compensation or other sums of
money payable by the contractor to the T.M.C. under the terms of his contract may
be deducted from or paid by the sale of sufficient part of his security deposit or
from the interest arising there from, or from any sums which may be due or may
become due by T.M.C. to the contractor under any other contract or transaction of
any nature on any account securities endorsed as aforesaid, any sum or sums which
whatsoever and in the event of his security deposit being reduced by reason of any
such deduction or sale as aforesaid, the contractor shall, within ten days thereafter,
make good in cash or Government may have been deducted from, or raised by sale
of his security deposit or any part thereof. The security referred to when paid in
cash may at the cost of the depositor, be converted into interest bearing securities
provided that the depositor has expressly desired this in writing.
If the amount of the security deposit to be paid in a lump sum within the period
specified at (A) above is not paid, the tender / contract already accepted shall be
considered as cancelled and legal steps taken against the contractor for recovery of
the amounts. The amount of the security deposit lodged by a contractor shall be
refunded after the completion of defect liability period (DLP) which is 24(
TwentyFour) months for this work i.e. up to which the contractor has agreed to
maintain the work in good order is over. In the event of the contractor failing or
neglecting to complete rectification work within the period upto which the
contractor has agreed to maintain the work in good order then subject to provision
of Clause 17 and 20 hereof the amount of Security Deposit retained by T.M.C. shall
be adjusted towards the excess cost incurred by the T.M.C. on rectification work.
Compensation CLAUSE 2 : The time allowed for carrying out the work (including monsoon
for delay
period) as entered in the tender shall be strictly observed by the contractor and shall
be reckoned from the date on which the order to commence work is given to the
contractor. The work shall throughout the stipulated period of the contract be
proceeded with all due diligence (time being deemed to be of the essence of the
contract on the part of the contractor) and the contractor shall pay as compensation
an amount equal to one percent or such smaller amount as the City Engineer
(whose decision in writing shall be final) may decide, of the amount of the
estimated cost of the whole work as shown by the tender for every day that the
work remain un-commenced, or unfinished, after the proper dates. And further to
ensure good progress during the execution of the work, the contractor shall be
bound, in all cases in which the time allowed for any work exceeds one month to
complete.
Action when CLAUSE 3 : In any case in which under any clause of this contract the contractor
whole of
shall have rendered himself to pay compensation amounting to whole of his
security
deposit is security deposit (whether paid in one sum or deducted by installments) or in case of
forfeited.
abandonment of the work owing to serious illness or death of the contractor or any
other cause the Chief Engineer on behalf of the M.C of T.M.C., shall have power to
adopt any of the following courses as he may deem best suited to the interest of the
T.M.C..
a) The rescind the contract (for which decision notice in writing to the contractor
under the hand of Chief Engineer shall be conclusive evidence) and in that case the
security Deposit of the contractor shall stand forfeited and be absolutely at the
disposal of T.M.C..
b) To carry out the work or any part of the work departmentally debiting the
contractors with cost of the work, expenditure incurred on tools and plant and
charges on additional supervisory staff including the cost of the work charges
establishment employed for getting the unexecuted part of the work completed and
crediting him with the value of the work done departmentally in all respects in the
same manner and at the rates as if it had been carried out by the contractor under
the terms of this contract. The certificate of the Engineer as to the cost and other
allied expenses so incurred and to the value of the work so done departmentally
shall be final and conclusive as against the contract.
c) To order that the work of the contractor be measured upto date such part thereof as
shall be unexecuted out of his hands and to give it to another contractor to complete
in which case all expenses incurred on advertisement for fixing new contracting
agency, additional supervisory staff including the cost of work charged
establishment and cost of the work executed by the new contract agency will be
debited to the contractor and the value of the work done or executed through the
new contractor shall be credited to the contractor in all respects and in the same
manner and at the same rates as if it had been carried out by the contractor under
the terms of this contract. The certificate of the Engineer as to all the cost of the
work and other expenses incurred as aforesaid for or in getting the unexecuted
work done by the new contractor and as per the value of the work so done be final
and conclusive against the contractor.
In case the contract shall be rescinded under Clause (a) above the contractor shall
be entitled to recover or be paid any sum for any work therefore actually performed
by him under this contract unless and until the Engineer shall have certified in
writing the performance of such work and the amount payable to him in respect
thereof and he shall only be entitled to be paid the amount so certified, in the event
of either of the course referred to in Clause (b) or (c) being adopted and the cost of
the work executed departmentally. Or through a new contractor and other allied
expenses exceeding the value of such work credited to the contractor, the amount
of excess shall be deducted from any money due to the contractor by T.M.C. under
the contract or otherwise however for, from his Security Deposit or the sale
proceed thereof provided however the contractor shall have no claim against
T.M.C. even if certified cost of such work and allied expenses, whichever of three
courses mentioned in Clauses (1), (b) or (c) is adopted by the Engineer the
contractor shall have no claim to compensation for any less sustained by him by
reasons of his having purchased procured any materials or entered into any
Action when CLAUSE 4 : If the progress of any particular portion of the work is
the progress of
unsatisfactory, the Engineer shall notwithstanding that the general progress of the
any particular
portion or the work is in accordance with the conditions mentioned in Clause 2, be entitled to take
work is
action under Clause 3 (b) after giving the contractor 10 days notice in writing. The
unsatisfactory
contractor will have no claim for compensation, for any loss sustained by him
owing to such action.
Contractor CLAUSE 5 : In any case in which any of the powers conferred upon the Chief
remains liable
Engineer by Clause 3 and 4 hereof shall have become exercisable and the same
to pay
compensation shall not constitute a waiver of any of the conditions hereof and such powers shall
if action is not
notwithstanding be exercisable in the event any future case of default by the
taken under
Clause 3 & 4 contractor for which under any clause or clauses hereof he is declared liable to pay
compensation amount to the whole of his security deposit and the liability of the
contractor for past and future compensation shall remain unaffected. In the event
of the Chief Engineer taking action under sub-clause (a) or (c) of Clause 3, he may,
Power to take
possession of if he so desires, take position of all or any tools, land, materials and stores in or
required
upon the work or the site thereof or belonging to the contractor, or procured by him
removal of or
sale of and intended to be used for the execution of the work or any past thereof paying or
contractor’s
allowing for the same in account at the contract rates or in the case of contract
plant.
rates not being applicable at current market rates, to be certified by the Engineer
may, after giving notice in writing to the contractor or his clerk of the work, or
foreman or other authorized agent require him to remove such tools, plant,
materials or stores from the premises within a time to be specified in such notice
and in the event of the contractor failing to comply with any such requisition the
Engineer may remove them at the contractor’s expense or sell them by auction or
private sale on account of the contractor and at his risk in all respects, and the
certificate of the Engineer as to the expense of any such removal and the amount of
the proceeds and expense of any such be final and conclusive against the
contractor.
Extension of CLAUSE 6 : If the contractor shall desire an extension of the time for
time
completion of work on the ground of his having been unavoidably hindered in its
execution or on any other ground, he shall apply in writing to the Engineer before
the expiration of the period stipulated in the tender or before the expiration of 30
days from the date of which he was hindered as aforesaid or on which the cause for
asking for extension occurred, whichever is earlier and the Engineer, may if in his
opinion there was reasonable grounds for granting an execution, grant such
extension as he thinks necessary or proper. The decision of the Engineer in this
matter be final.
Final Clause 7 : On completion of the work the contractor shall be furnished with a
Certificate
certificate by the Engineer (hereinafter called the Engineer) of such completion but
no such certificate shall be given nor shall the work be considered to be complete
until the contractor shall have removed from the premises on which the work shall
have been executed all scaffolding, surplus materials and rubbish, and shall have
cleaned off the dirt from all wood work, doors, windows, walls, floor or other parts
of any building in or upon which the work has been executed or of which he may
hand possession for the purpose of executing the work nor until the works shall
have been measured by the Engineer or where the measurement have been take by
his subordinates until they have received the approval of the Engineer, the said
measurements being binding and conclusive against the contractor. If the
contractor fails to comply with the requirements of this clause as to the removal of
scaffolding, surplus materials and rubbish and cleaning of dirt on or before the date
fixed for the completion of the work the Engineer may at the expense of the
contractor remove such scaffolding, surplus materials and rubbish and dispose off
the same as he thinks fit and clean off such dirt as aforesaid and the contractor
shall forthwith pay the amount of all expenses so incurred, but shall have no claim
in respect of any such scaffolding or surplus materials as aforesaid except for any
sum actually realized by the sale thereof.
Payments on CLAUSE 8: No payment shall be made for any work, estimated to cost less than
intermediate
rupees one thousand till after the whole of the work shall have been completed and
certificates to
be regarded as a certificate of completion given. But in the case of works estimated to cost more
advances
than rupees one thousand, the contractor shall on submitting a monthly bill
therefore, be entitled to receive payment proportionate to the part work then
approved and passed by the Engineer, whose certificate of such approval and
passing of the sum so payable shall be final and conclusive against the contractor.
All such intermediate payments shall be regarded as payments by way of advance
against the final payments only and not as payments for works actually done and
completed, and shall not preclude the Engineer from requiring any bad, unsound,
Payment at CLAUSE 9: The rates for several items of works estimated to cost more than
reduced rates
Rs.1,000 agreed within, shall be valid only when the item concerned is accepted as
on account of
items of work having been completed fully in accordance with the sanctioned specifications. In
not accepted
cases where the items of work are not accepted as so completed the Engineer may
as completed
to be at the make payment on account of such items at such reduced rates as he may consider
discretion of
reasonable in the preparation of final or on account bills.
Engineer
Bill to be CLAUSE 10: A bill shall be submitted by the contractor each month on or before
submitted
the date fixed by the Engineer for all work executed in the previous month and the
monthly
Engineer shall take or cause to be taken the requisite measurement for the purpose
of having the same verified and the claim, so far as it is admissible, shall be
adjusted if possible within 10 days from the presentation of the bill. If the
contractor does not submit the bill within the time fixed as aforesaid, the Engineer
may depute a subordinate to measure up the said work in the presence of the
contractor or his duly authorized agent whose counter signature to the measurement
list shall be sufficient warrant, and the Engineer may prepare a bill from such list
which shall be binding on the contractor in all respects.
Bill to be on CLAUSE 11: The contractor shall submit all bills on the printed forms to be had
printed forms
on an application at the office of the Engineer. The charges to be made in the bills
shall always be entered at the rates specified in the tender or in the case of any extra
work ordered in pursuance of these conditions, and not mentioned or provided for
in the tender, at the rates hereinafter provided for such work.
Store supplied CLAUSE 12 : If the specification or estimate of the works provides for the use of
by T.M.C.
any special description of materials to be supplied from the store of the T.M.C. or if
it is required that the contractor shall use certain stores to be provided by the
Engineer (such material and stores and the prices to be charged therefore as
hereinafter mentioned being so far as practicable for the convenience of the
contractor but not so as in any way to control the meaning or effect of this contract
specified in the schedule or memorandum hereto annexed) the contractor shall be
supplied with such materials and stores as may be required from time to time to be
used by him for the purposes of the contract only, and the value of the full quantity
of the materials and stores so supplied shall be set off or deducted from any sums
thank due or thereafter to become due to the contractor under the contract, or
otherwise, or from the security deposit, or the proceeds of sale thereof if the
security deposit is held in government securities the same or a sufficient portion
thereof shall in that case be sold for the purpose. All materials supplied to the
contractor shall remain the absolute property of T.M.C. and shall on no account be
removed from the site of the work and shall at all times be open to inspection by
the Engineer. Any such materials unused and in perfectly good in writing given
under his hand but the contractor shall not be entitled to return any such material
except with consent of the Engineer and he shall have no claim for compensation
on account of any such material supplied to him as aforesaid but remaining unused
by him or for any wastage in or damage to any such materials.
Works to be CLAUSE 13: The contractor shall execute the whole and every part of the work of
executed in
the most substantial and workman like manner and both as regards materials and in
accordance
with every other respect in strict accordance with specifications. The contractor shall
specifications,
also confirm exactly fully and faithfully to the designs, drawings and instructions in
drawings,
orders etc. writing relating to the work signed by the Engineer and lodged in this office to
which the contractor shall be entitled to have access for the purposes of inspection
such office or on the site of work during office hours. The contractor will be
entitled to receive three sets of contract drawings as well as one certified copy of
the accepted tender along with the work order free of cost. Further copies of the
contract drawings and other working drawings, if required by him, shall be
supplied at Rs.1000/- per set.
Alternative in CLAUSE 14 : The Engineer shall have power to make any alteration in or
specification
additions to the original specifications, drawings, designs and instructions that may
and designs
not to appear to him to be necessary or advisable during the progress of the work, and the
invalidate
contractor shall be bound to carry out the work in accordance with any instructions
contracts.
in this connection which may be given to him in writing signed by the Engineer and
such alteration shall not invalidate the contract and any additional work which the
contractor may be directed to do in the manner above specified as part of the work
shall be carried out by the contractor on the same conditions in all respects on
which he agreed to do the main work, and at the same rates as are specified in the
tender for the main work. And if the additional and altered work includes any class
of work for which no rate is specified in this contract then such class of work shall
be carried out at the rates entered in the Schedule of Rates of the Division or at the
rates mutually agreed upon between the Engineer and the contractor, whichever are
lower, if the additional or altered work for which no rate is entered in Schedule of
Rates of Division, is ordered to be carried out before the rates are agreed upon then
the contractor shall, within seven days of the date of receipt by him of the order to
Rates for
works not carry out the work, inform the Engineer of the rate which it is his intention to
entered in
charge for such class of work, and if the Engineer does not agree to this rate he
estimate, for
schedule of shall by notice in writing be at liberty to cancel his order to carry out such class of
rates of the
work, and arrange to carry it out in such manner as he may consider advisable,
district.
provided always that if the contractor shall commence work or incur expenditure in
regard thereto before the rates shall have been mentioned as lastly herein before
mentioned, then in such case he shall only be entitled to be paid in respect of the
work carried out or expenditure incurred by him prior to the date of the
determination of the rate as aforesaid according to such rate of rates as shall be
fixed by the Engineer. In the event of a dispute, the decision of the Engineer of the
T.M.C. will be final.
Where, however, the work is to be executed according to the designs, drawings and
specifications recommended by the contractor and accepted by the competent
authority the alterations above referred to shall be within the scope of such designs,
drawings and specifications appended to the tender.
Extensions of The time limit for the completion of the work shall be extended in the proportion
time in
that the increase in its cost occasioned by alterations of additions bears to the cost
consequence
of additions or of the original contract work, and the certificate of the Engineer as to which
alterations
proportion shall be conclusive.
No claim to CLAUSE 15 : (1) If at any time after the execution of the contract documents,
any payment
the Engineer shall for any reason whatsoever (other than default on the part of the
or
compensation contractor for which the T.M.C. is entitled to rescind the contract) desire that the
for alteration whole or any part of the work specified in the tender should be suspended for any
in or
period or that the whole part of the work should not be carried out at all he shall
restriction of
work give to the contractor a notice in writing of such desire and upon the receipt of such
notice the contractor shall forthwith suspend or stop the work wholly or in part as
required, after having due regard to the appropriate stage at which the work should
be stopped or suspended so as not to cause any damage or injury to the work
already done or endanger the safety thereof provided that the Engineer as to the
stage at which the work or any part of it could be or could have been safely stopped
or suspended shall be final and conclusive against the contractor. The contractor
shall have no claim to any payment or compensation whatsoever by reasons of or in
pursuance of any notice as aforesaid, on account of any suspension, stoppage or
curtailment except to the extent specified hereinafter.
(2) Where the total suspension of the work ordered as aforesaid continued for a
continuous period exceeding 90 days the contractor shall be at liberty to
withdraw from the contractual obligation under the contract so far as it pertains
to the un-executed part of the work by giving a 10 days prior notice in writing
to the Engineer, within 30 days of the expiry of the said period of 90 days of
such intention and requiring the Engineer to record the final measurements of
the work already done and to pay the final bill. Upon giving such notice the
contractor shall be deemed to have been discharged from his obligation to
complete the remaining un-executed work under this contract. On receipt of
such notice the Engineer shall proceed to complete the measurements and make
such payment as may be finally due to the contractor within a period of 90 days
from the receipt of such notice in respect of the work already done by the
contractor. Such payment shall not in any manner prejudice the right of the
contractor to any further compensation under the remaining provisions of this
clause.
(3) Where the Engineer requires the contractor to suspend the work for a period in
excess of 30 days at any time or 60 days in the aggregate, the contractor shall be
entitled to apply to the Engineer within 30 days of the resumption of work such
suspension of payment of compensation to the extent of pecuniary loss suffered
by him in respect of working machinery rendered idle on the site or on account
of his having had to pay the salary or wages of labour engaged by him during
the said period of suspension, provided always that the contractor shall not be
No claim to It shall be open to the contractor, within 90 days from the service of (i) the notice
compensation
of stoppage of work or (ii) the notice of withdrawal from the contractual
on account of
loss due to obligations under the contract account of the continued suspension of work or (iii)
delay of
notice under Clause 14 (1) resulting in such curtailment to produce to the Engineer
materials by
T.M.C. satisfactory documentary evidence that he had purchased or agreed to purchase
materials for use in the contracted work, before receipt by him of the notice for
stoppage, suspension or curtailment and required the T.M.C. to take over on
payment, such materials at the rates determined by the Engineer. The T.M.C. shall
thereafter take over the material so offered, provided the quantities offered are not
in excess of the requirements of the un-executed work as specified in the accepted
tender and are of quality and specification approved by the Engineer.
CLAUSE 15-A : The contractor shall not be entitled to claim any compensation
from T.M.C. for the loss suffered by him on account of delay by T.M.C. in the
supply of materials, entered in Schedule-A where such delay is caused by -
i) Difficulties relating to the supply of railway wagons.
ii) Force Major
iii) Act of God
iv) Act of enemies of the State or any other reasonable cause beyond the control of
T.M.C..
In the case of such delay in the supply of materials T.M.C. shall grant such
extension of time for the completion of the works as shall appear to the Chief
Engineer to be reasonable in accordance with the circumstance of the case. The
decision of the Chief Engineer as to the extension of time shall be accepted as final
by the contractor.
Notice to be CLAUSE 19 : The contractor shall give not less than seven days notice in
given before
writing to the Engineer or his subordinate in charge of the work before covering up
work is
covered up or otherwise placing beyond the reach of measurement any work in order that the
same is so covered up or placed beyond the reach of measurement any work
without the consent in writing of Engineer or his subordinate in charge of the work,
and if any work shall be covered up or placed beyond the reach of measurement
without such notice having been given or consent obtained the same shall be
uncovered at the contractor’s expense, and in default thereof no payment or
allowance shall be made for such work or for the materials with which the same
was executed.
Contractor CLAUSE 20 : If during the period of twelve months from the date of
liable for
completion as certified by the Engineer pursuant to Clause 7 of the contract if in
damage done,
and the opinion of the Engineer, the said work is defective in any manner whatsoever,
imperfection
the contractor shall forthwith on receipt of notice in that behalf from the Engineer
duly commence execution and completely carry out at his cost in every respect all
the work that may be necessary for rectifying and setting right the defect specified
therein including dismantling and reconstruction of unsafe portions strictly in
accordance with and in the manner prescribed and under the supervision of the
Engineer in the event of the contractor failing or neglecting to commence execution
of the said rectification work within the period prescribed thereof in the said notice
and / or to complete the same as aforesaid as required by the said notice. The
Engineer get the same executed and carried out departmentally or by any other
agency at the risk on account and at the cost of the contractor. The contractor shall
forthwith on demand pay to the T.M.C. amount of such costs, charges and expenses
sustained or incurred by the T.M.C. of which the certificate of the Engineer shall be
final and binding on the contractor. Such costs, charges and expenses shall be
deemed to be arrears of land revenue and in the event of the contractor failing or
neglecting to pay the same on demand as aforesaid without prejudice to any other
rights and remedies of the T.M.C.; the same may be recovered from the contractor
as arrears of land revenue. The Government shall also be entitled to deduct the
same from any amount which may then be payable or which may thereafter
become payable by the T.M.C. to the contractor either in respect of the said work
or any other work whatsoever or from the amount of security deposit detained by
T.M.C..
Contractor to CLAUSE 21 : The contractor shall supply at his own cost all materials (except
supply plant
such special materials, if any, as may, in accordance with the contract, be supplied
ladders,
scaffolding from the T.M.C. stores), plant, tools, appliances, implements, ladders, cordage,
etc.
tackle scaffolding, temporary works requisite or proper for execution of the work,
whether the original, altered or substituted form, and whether included in
specifications, or other documents forming part of the contract or referred to in
these conditions or not and which may be necessary for the purpose of satisfying or
And is liable
complying with the requirements of the Engineer as to pay matter as to which
for damages
arising from under these conditions he is entitled to be satisfied, or which he is entitled to
non-provisions
require together with carriage therefore and from the work. The contractor shall
of lights,
fencing etc. also supply without charge the requisite number of persons with the means and
materials necessary for the purpose of setting out works, and counting, weighing
and assisting in the measurement or examination at any time and from time to time
of the work or the materials. Failing this the same may be provided by the
Engineer at the expense of the contractor and the expenses may be deducted from
any money due to the contractor under the contract or from his security deposit or
the proceeds of sale thereof, or of a sufficient portion thereof. The contractor shall
provide all necessary fencing and lights required to protect the public from
accident, and shall also be bound to bear the expenses of defense of every suit,
action or other proceedings, that may be brought by any person for injury sustained
owing to neglect of the above precautions and to pay any damages and costs which
may be awarded in any such suit, action or proceedings to any such person or
which may with the consent of the contractor be paid for compromising any claim
by any such person.
CLAUSE 21-A : The contractor shall provide suitable scaffold and working
platforms gangways and stairways and shall comply with the following regulations
in connection herewith -
a) Suitable scaffolds shall be provided for workmen for all works that cannot be
safely done from a ladder or by other means.
b) A scaffold shall not be constructed, taken down, or substantially altered except -
i) under the supervision of a competent and responsible person;
and
ii) as far as possible by competent worker possessing adequate
experience in this kind of work.
c) All scaffolds and appliances connected therein and all ladders shall -
i) be of sound material;
ii) be of adequate strength having regard to the leads and strains to
which they will be subjected, and
iii) be maintained in proper condition.
d) Scaffolds shall be so constructed that no part thereof can be displaced in
ii) every working platform and gangway shall have adequate width, and
iii) every working platform, gangway, working place and stairway shall be
suitably fenced.
k) Every opening in the floor of a building or in a working platform shall except
for the time and to the time and to the extent required to allow the excess of
persons or the transport or shifting of material; be provided with suitable means
to prevent the fall of persons or materials.
l) When persons are employed on a roof where there is a danger of falling from a
height exceeding suitable precaution shall be taken to prevent the fall of persons
or materials.
m) Suitable precautions shall be taken to prevent persons being struck by article
which might fall from scaffolds or other working places.
n) Safe means of access shall be provided to all working platforms and other
working places.
o) The contractor shall have to make payment to the labourers as per minimum
wages act.
CLAUSE 21-B : The contractor shall comply with the following regulation as
CLAUSE 21-C : The contractor / contractors will have to make payments to the
labourers as per Minimum Wages Act, (1950).
CLAUSE 22: The contractor shall not set fire to any standing jungle, trees,
brushwood or grass without a written permit from the Engineer.
Measures for When such permit is given and also in all cases when destroying out or dig up
prevention of
trees, brushwood, grass etc., by fire, the contractor shall take unnecessary measures
fire
to prevent such fire spreading to or otherwise damaging surrounding property.
The contractor shall make his own arrangements for drinking water for the labour
employed by him.
Work not to be CLAUSE 26 : The contractor shall not assign or sublet without the written
sublet unless it
approval of the Engineer. And if the contractor shall assign or sublet his contract
is permitted
contract may or attempt so to do or become insolvent or commence any proceedings to get
be rescinded
himself adjudicated an insolvent or make any composition with his creditors, or
and security
deposit attempt to do or if bribed, grateful, gift, loan perquisite, reward or advantage,
forfeited for
pecuniary or otherwise shall either directly or indirectly be given, promised or
subletting it
without offered by the contractor or any of his servants or agents to any public officer or
approval or for
person in the employment of T.M.C. in any way relating to his officer or
bringing a
public officer employment or if any such officer or person shall become in any way directly or
if contractors
indirectly interested in the contract, the Engineer may there upon by notice in
become
insolvent writing rescind the contract, and the security deposit of the contractor shall
thereupon stand forfeited and be absolutely at the disposal of T.M.C. and the same
consequences shall ensure as if the contract had been rescinded under Clause 3
hereof and in addition the contractor shall not be entitled to recover or be paid for
any work therefore actually performed under the contract.
Sum payable CLAUSE 27 : All sums payable by a contractor by way of compensation under
by way of
any of these conditions shall be considered as reasonable compensation to be
compensation
to be applied to the use of T.M.C. without reference to the actual loss or damage
considered as
sustained, and whether any damage has or has not be sustained.
reasonable
compensation
without
reference to
actual loss
Changes in the CLAUSE 28 : In the case of tender by partners any change in the constitution of a
constitution of
firm shall be forthwith notified by the contractor to the Engineer for his
firm to be
notified information.
Work to be CLAUSE 29 : All works to be executed under the contract shall be executed under
under direction
the direction and subject to the approval in all respects of the Engineer of the
of the
Engineer T.M.C. for the time being, who shall be entitled to direct at what point or points
and in what manner they are to be commenced, and from time to time carried on.
CLAUSE 30 (1) : Except where otherwise specified in the contract and subject
to the powers delegated to him by T.M.C. then in force the decision of the Engineer
for the time being shall be final, conclusive and binding on all parties to the
contract upon all questions relating to the meaning of the specifications, designs,
drawings, and instructions, hereinbefore mentioned and as to the quality of
workmanship or materials used on the work or as to any other question, claim,
right, matter or things, whatsoever if any, way arising out of or relating to the
contracts designs drawings, specifications, estimates, instructions, orders or other
conditions or otherwise concerning the works or the execution of failure to execute
the same, whether arising, during the progress of the work or after completion of
abandonment thereof.
CLAUSE 30 (2) : The contractor, may within thirty days of receipt by him of
any order passed by the Engineer as aforesaid, appeal against it to the City
Engineer, T.M.C. provided that –
a) The accepted value of the contract exceeds Rs.50 lakhs (Rupees Fifty Lakhs)
b) Amount of claim is not less than Rs.10.00 lakhs (Rupees Ten lakhs)
CLAUSE 30 (3) : If the contractor is not satisfied with the order passed by the
Additional Metropolitan Commissioner, T.M.C. as aforesaid, the contractor may,
within thirty days of receipt by him of any such order, appeal against it to the
Metropolitan Commissioner who, if convinced that prima-facie the contractor’s
claim rejected by Engineer / Chief Engineer/ Additional Metropolitan
Commissioner, T.M.C. is not frivolous and that there is some substance in the
claim of the contractor as would merit a detailed examination through a suitable
committee appointed for the purpose by the Metropolitan Commissioner if
necessary and in that case decision taken by the committee shall be finalized by the
competent authority and same shall be binding to the contractor.
Stores of CLAUSE 31 : The contractor shall obtain from the T.M.C. all stores and articles
European or
of European or American manufacture which may be required for the work or any
American
manufacturer part thereof or in making up any articles required therefore or in connection
to be obtained
therewith unless he has obtained permission in writing from the Engineer to obtain
from T.M.C.
such stores and articles elsewhere.
The value of such stores and articles as may be supplied to the contractor by the
Engineer will be debited to the contractor in his account at the rates shown in the
Schedule in Form – A attached to the contract and if they are not entered in the said
schedule, they shall be debited to him at cost price which for the purposes of this
contract shall include the cost of carriage and all other expenses whatsoever, which
shall have been incurred in obtaining delivery of the same at the stores aforesaid.
Lump sum CLAUSE 32 : When the estimate on which a tender is made includes lump sum
estimates
in respect of parts of the work, the contractor shall be entitled to payment in respect
of the items of works involved or the part of the work in question at the same rates
as are payable under this contract for each item or if the part of the work in
question is not in the opinion of the Engineer capable of measurement, the
Engineer may at his discretion pay the lump sum amount entered in the estimate,
and the certificate in writing of the Engineer shall be final and conclusive against
the contractor with regard to any sum or sums payable to him under the provisions
of this clause.
Action where CLAUSE 33 : In the case of any class of work for which there is no such
Definition of CLAUSE 34 : The expression “work” where used in these conditions, shall
work
unless there be something in the subject or context repugnant to such construction,
be constructed to mean the work or works contracted to be executed under on in
virtue of the contract, whether temporary or permanent and whether original,
altered, substituted or additional.
Contractor’s CLAUSE 35 : The percentage referred to in the tender shall be deducted from or
percentage
added to the gross amount of the bill before deducting the value of any stock issue.
whether
applied to net
or gross
amounts of
bills
Refund or CLAUSE 36 : All quarry fees, royalties and ground rent for stacking materials,
quarry fees
if any should be paid by the contractor. The contractor shall submit the challans for
and royalties
royalty to TMC. If the challans for the royalty are not submitted, the Thane
Municipal Corporation shall deduct the royalty charges from the Bills of
contractor.
Compensation CLAUSE 37 : The contractor shall be responsible for and shall pay any
under the
compensation to his workman payable under the workmen’s compensation Act,
workmen’s
compensation 1923 (VIII) of 1923 (hereinafter called the said Act) for injuries caused to the
Act
workmen. If such compensation is payable, paid by T.M.C. as principal under sub-
section (1) of Section 12 of the said Act on behalf of the Contractor, it shall be
recoverable by T.M.C. from the contractor under Sub-section (2) of the said
section. Such compensation shall be recovered in the manner laid down in Clause
1 above.
CLAUSE 37-A : The contractor shall provide all necessary personal safety
equipment and first aid apparatus available for the use of the persons employed on
the site, shall maintain the same condition suitable for immediate use at any time
and shall comply with the following regulations in connection therewith.
a) The workers shall be required to use the equipment so provided by the
contractor and the contractor shall take adequate steps to ensure proper use of
Claim for CLAUSE 38 : (1) Quantities in respect of the several items shown in the tender
quantities
are approximate and in respect of any of the items so long as, subject to any special
entered in the
tender or provision contained in the specifications prescribing a different percentage of
estimates
permissible variation, the quantity varies by more than 40 percent or so long as the
value of the excess quantity, at the rate of item specified in the tender, is not more
than 1% of tendered cost, whichever is more, no variation in rate shall be
entertained.
(2) The contractor shall, if ordered in writing by the Engineer so to do, also carry
out any quantities in excess of the limit mentioned in sub-clause (1) hereof on
the same conditions as and in accordance with the specifications in the tender
and the rates (i) derived from the rates entered in the current schedule of rates
and in the absence of such rates, (ii) at the rate prevailing in the market, the said
rates being increased or decreased as the case may be by the percentage which
the total tendered amount bear to the estimated cost of the work as put to tender
based upon the Schedule of Rates applicable to the year in which the tenders
were invited.
(3) Claims arising out of reduction in the tendered quantity of any item beyond 40
percent will be governed by the provisions of Clause 15 only when the amount
of such reduction beyond 25 percent at the rate of the item specified in the
tender is more than 1% of initial contract price.
In view of the rationalization of the provisions of Clause 37 of B-2 and 38 of B-
1 tender from as above, it is necessary to prescribe the manner in which the
claims arising out of reduction in the tendered quantity of any item under
Clause 15 of the tender form should be dealt with. It is decided that Clause 15
should be modified as under :
There is no change in the rate if the excess is less than or equal to 25%. Also,
there is no change in the rate if the quantity of work done is more than 25% of
the tendered quantity, but value of excess work at the tendered rate does not
exceed 1% of the initial contract price.
Employment CLAUSE 39: The contractor shall employ any famine, convict or other labour of a
of famine etc.
particular kind of class if ordered in writing to do so by Engineer.
labour
Claim for CLAUSE 40 : No compensation shall be allowed for any delay caused in the
compensation
starting of the work on account of acquisition of land or in the case of clearance
for delay in the
starting the works, on account of any delay in according sanction to estimates.
work
Claim for CLAUSE 41 : No compensation shall be allowed for any delay in the execution
compensation
of the work on account of water standing in borrow pits or compartments. The
for delay in the
execution of rates are inclusive of hard or cracked soil, excavation in mud, sub-soil water or
work
water standing in borrows and no claim for an extra rate shall be entertained, unless
otherwise expressly specified.
Entering upon CLAUSE 42 : The contractor shall not enter upon or commence any portion of
or
work except with the written authority and instructions of the Engineer or of his
commencing
any portion of sub-ordinate in charge of the work, failing which the contractor shall have no claim
work
to ask for measurements or payment for work.
Minimum age CLAUSE 43 : (i) No Contractor shall employ any person who is under the age of
of persons
14 years.
employed; the
employment of (ii) No contractor shall employ donkeys or other animals with breaching of string
donkeys
or thin rope. The breaching must be at least three inches wide and should be of
and or other
animals and tape (Nawar).
the payment
(iii)No animal suffering from sores, lameness or emaciation or which is immature
of fair wages
shall be employed on the work.
(iv)The Engineer or his Agent is authorized to remove from the work any person or
animal found working which does not satisfy these conditions and no
responsibility shall be accepted by T.M.C. for any delay caused in the
completion of the work due to such removal.
(v) The contractor shall pay fair and reasonable wages to the workmen employed
by him in the contract undertaken by him.
In the event of any dispute arising between the contractor and his dispute
arising between the contractor and his workmen on the grounds that the wages
paid are not fair and reasonable the dispute shall be referred to workmen on the
grounds that the wages paid are not fair and reasonable the dispute shall be
referred without delay to the Engineer, who shall decide the same. The
decisions of the Engineer shall be conclusive and binding on the contractor, but
such decision shall not in any way effect the conditions in the contract
regarding the payment to be made by T.M.C. at the sanctioned rates.
(vi) Contractor shall provide drinking water facilities to the workers. Similar
amenities shall be provided to the workers engaged on large work in urban
areas.
CLAUSE 47: The price quoted by the contractors shall not in any case exceed the
control price, if any, fixed by Government or reasonable price which it is
permissible for him to change a private purchaser for the same class and
description, the controlled price of the price permissible under Hoarding and
Profiteering Ordinance 1943 as amended from time to time. If the price quoted
exceeds the controlled price or the price permissible under Hoarding and
Profiteering Prevention Ordinance, the contractor will specifically mention this fact
in this tender along with the reasons for quoting such higher prices. The purchaser
at his discretion will in such ease exercise the right of revising the price at any
stage so as to conform to the controlled price on the permissible under the
Hoarding and Profiteering Prevention Ordinance. The discretion will be exercised
without prejudice to any other action that may be taken against the contractor.
CLAUSE 48 : The contractor shall employ at least 80 percent of the total number
of unskilled labour to be employed by him on the said work from out of the persons
ordinarily residing to the district in which site of the said work is located.
“Provided, however, that if the required number of unskilled labour from that
district is not available, the contractor shall in the first instance employ such
number of persons as is available and thereafter may with the previous permission
in writing of the Engineer of the said work, obtain the rest of his requirement of
unskilled labour from outside the district”.
CLAUSE 49 : In case of materials that may remain surplus with the contractor’s
from those issued for the work contracted for the date as containment of the
materials being surplus will be taken as the date of sale for the purpose of sales tax
and the sales tax will be recovered on such sale.
CLAUSE 52: “A contractor shall comply with the provision of the Apprentice
Act, 1961 and the rules and orders issued there-under from time to time if he fails
to do so, his failures will be breach of the contract and the Engineer may in his
direction cancel the contract. The contractor shall also be liable for any pecuniary
liability arising on account of any violation by him of the provision of the Act”.
CLAUSE 53: The contractor shall duly comply with all the provisions of the
Central Government (Regulation and Abolition Act, 1970 (37 of 1970) and the
Maharshtra Contract Labour (Regulation and Abolition) Rules, 1971 as amended
from time to time and all other relevant statutes and statutory provisions
concerning payment of wages particularly to workmen employed by the contractor
and working on the site of the work. In particular the contractor shall pay wages to
each worker employed by him on the site of the work at the rates prescribed under
the Maharshtra Contract Labour (Regulation and Abolition) Rules, 1971. If the
contractor fails or neglects to pay wages at the sates or makes short payment and
the T.M.C. makes such payment of wages in full or part thereof less paid by the
contractor as the case may be, the amount so paid by the T.M.C. to such workers
shall be deemed to arrears of land revenue and the T.M.C. shall be entitled to
recover the same as such from the contractor or deduct the same from the amount
payable by the T.M.C. to the contractor hereunder or from any other amounts
payable to him by the T.M.C..
CHAPTER VII
SCHEDULE 'A'
CHAPTER- VII
SCHEDULE ‘A’
Daily operating of valves
Schedule showing (approximately) the materials to be supplied from the
T.M.C.’s Stores for works contracted to be executed and the rates at which
NIL
Note : 1) The person or firm submitting the tender should see that the
rates in the above schedule are filled up by the Engineer on the
issue of the form prior to the submission of the tender.
CHAPTER VIII
SCHEDULE 'B'
CHAPTERVIII
SCHEDULE "B"
Name Of Work :- “Providing labour for Regulating water supply from Gaodevi,
Eternity, Tekadi Bunglow ESR in Naupada Prabhag Samiti Area (2023 – 2024)”.
ABSTRACT
It. Description of Item Quantity Rate Unit Amount
No
(In words Rs. Forty four lacs ninety thousand nine hundred twenty eight only).
I / We ready to carry out the above said work % above / below the estimated cost
CHAPTER IX
ITEMWISE
SPECIFICATIONS
CHAPTER IX
ITEMWISE SPECIFICATIONS
CHAPTER X
FORMS
Form – 1
(On stamp paper as Per Stamp Duty Act)
FORM OF AGREEMENT
WHEREAS the Employer is desirous that certain works should be executed viz.,
(Name of the contract………………………………..) and has accepted a Tender by the
Contractor for the execution, completion and guarantee of such works NOW THIS
AGREEMENT WITNESSETH as follows :
The cost of this work is Rs ……………………( In word Rs...............................................)
1. In this Agreement words and expression shall have the same meaning as are
respectively assigned to them in the Conditions of Contract hereinafter referred
to.
2. The following documents shall be deemed to form and be read and construed as
part of this Agreement, viz.,
a) All tender Documents as issued by the Employer for this work.
b) All amendments to the tender documents as issued by the Employer prior to
submission of the bids.
c) Acceptance letter issuied by the Employer vide No. _________ and all
correspondence exchanged between the Employer and the Contractor upto
the date of issue of acceptance letter as specifically referred to in the said
acceptance letter.
In consideration of the Thane Municipal Corporation (hereinafter called “the Employer”) having agreed
to exempt …………………... (hereinafter called " the Contractor ") from depositing with the Thane
Municipal Corporation in cash the sum of Rs…………… (Rupees… …………………………only ) being
the amount of Performance Security payable by the Contractor to the Thane Municipal Corporation
under the terms and conditions of the Agreement dated the ……………….. Day of ………………..
2006 and made between the Thane Municipal Corporation of the one part and the Contractor of the
other part (hereinafter referred to as " the said Agreement ") for ……… as security for due
observance and performance by the Contractor of the terms and conditions of the said Agreement, on
the Contract furnishing to the Thane Municipal Corporation a Guarantee in the prescribed form of a
Schedule Bank in India being in fact these presents in the like sum of Rs…………………… (Rupees
……………………. ……………………………………………………………………Only).
2. Undertake to pay to the Thane Municipal Corporation on demand and without dispute or disputes
raised by the Contractor(s) in any suit or proceeding field in any court of tribunal relating thereto
the said sum Rs……………… (Rupees ……… only) or such lesser sum as may be demanded by
the Thane Municipal Corporation from us our liability hereunder being absolute and unequivocal
and agree that -
3. a) The guarantee herein contained shall remain in full force and effect during the subsistence of
the said Agreement and that the same will continue to be enforceable till all the dues of the
Thane Municipal Corporation under or by virtue of the said Agreement have been duly paid
and its claims satisfied or discharged and till the Thane Municipal Corporation certifies that the
terms and conditions of the said Agreement have been fully properly carried out by the
Contractor.
b) We shall not be discharged or released from the liability under this Guarantee by reasons of :
(i) Any change in the constitution of the Bank or the Contractor ;
(ii) Any agreement entered into between the Thane Municipal Corporation and the
Contractor with or without our consent;
(iv) Any variation in the terms, covenants or conditions contained in the said Agreement
(vi) Any other conditions or circumstances under which, in law; a surety would be
discharged.
c) Our liability hereunder shall be joint and several with that of the Contractor as if we were the
principal debtors in respect of the said sum of Rs………………….…………………. (Rupees
……..………………..only).
We shall not revoke this guarantee during its currency except with the previous consent in
writing of the Government.
4) Notwithstanding anything contained herein before our liability under this guarantee is restricted to
Rs______________(Rupees_________) .Our guarantee shall remain in force upto
The common seal of ………………………….….. was pursuant to the resolution of the Board of
Directors of the Company dated the ……………………. Day of …20… herein affixed in the presence
of ……………………….who, in token thereof, have hereto set their respective hands in the presence
of -
1. ……………………………………………………………………………………….
2. ………………………………………………………………………………………
In consideration of the Thane Municipal Corporation Thane (herein after called “TMC
Thane”) having agreed to exempt ___________________________ (herein after referred to
as “the Contractor”) from depositing with the TMC Thane in cash of the sum of
Rs.________________ (Rupees _______________________________ only) being the
amount of security deposit payable by the Contractor or to the TMC Thane under the terms
and conditions of an agreement dated the __________ day _______________ of and made
between the TMC Thane of the one part and the Contractor of the other part (here in refferred
to as "the said Agreement") for ________________ as security for the due observance and
performance by the Contractor of the terms and conditions of the said Agreement, on the
contract furnishing to the TMC Thane a guarantee in to the prescribed form of a Scheduled
Bank in India being in fact those present in the like sum of Rs._____________________
(Ruppes ______________________________________ only). We
_____________________________________________ BANK/LIMITED registered in India
under ____________________________ Act and having one of our local Head Office at
_____________________ ___________________ do hereby :
1) Guarantee to the TMC Thane.
(a) Due performance and observance by the Contractor of the terms, covenants
and conditions on the part of the Contractor contained in the said Agreement
and
(b) Due and punctual payment by the Contractor to the TMC Thane of all sums of
money, losses, damages, cost charges, penalties and expenses payable to the
TMC Thane by the Contractor under or in respect to the said agreement.
2) Undertake to pay the TMC Thane on demand and without demand and not
withstanding any dispute or disputes raised by the Contractor(s) in any suit or
proceeding filed in any Court of tribunal relating there to the said sum of
Rs.__________________ (Rupees _______________________________ only) or
such less sum may be demanded by the TMC Thane from us our liability hereunder
being absolute and unequivocal and agree that.
3) (a) The guarantee herein contained shall remain in full force & effect during the
subsistence of the said agreement and the same will continue to be enforceable till all
the dues of the TMC Thane under or by virtue of the said agreement have been duly
paid and its claims satisfied or discharged and till the TMC Thane certifies that the
terms and conditions of the said agrement have been fully and properly carried out by
the Contractor.
(b) We shall not be discharged or released from the liability under this guarantee
by reasons of
(i) Any change in the constitution of the bank of the Contractor, or
(ii) Any arrangement entered in between the TMC Thane and the
Contractor with or without our consent;
(iii) Any forbearance or indulgence shown to the Contractor;
(iv) Any variation in terms of covenants or conditions contained in
the said agreement;
(v) Any time given to the Contractor;
(vi) Any other conditions or circumstances under which, in law, a surety
would be discharged;
(c) Our liability here under shall be joint and several with that of the Contractor as
if we were the principal debtors in respect of the said sum of
Rs._____________________ (Rupees_______________________________
_______________________________________________________________
___________________________________________________ only) and
(d) We shall not revoke this guarantee during its currency except with the
previous consent in wr iting of the TMC Thane. IN WITNESS WHERE OF
THE common seal of __________________ has been herein to affixed this
____________ day of ____________________ 201_______ . The common
seal of was pursuant to the resolution of the Board of Directors of the
Company dated the _______________ day of
____________________________________ herein affixed in the presence of
_________________________________ who, in token there of, have here to
set their respective hands in the presence of
(1) (2)
No demand certificate
FORM 4:
To be submitted at the time of submission of final bill
Sample Form of
No Demand Certificate
NO DEMAND CERTIFICATE
Authorised Signatory
(__________Name__________)
For __________Name of the Agency________
FORM 5: No
Claim Certificate for Labour
To be submitted at the time of submission of final bill
Sample Form of
No Claim Certificate for Labour
To,
City Engineer,
Thane Municipal Corporation, Thane.
Adv. Almeida Road, Panchpakhadi,
Thane.
We hereby confirm that we have paid all the wages to all the labours employed
under this contract as per minimum Wages declared by the Govt. of Maharashtra.
Authorised Signatory
(__________Name__________)
For __________Name of the Agency________
CHAPTER XI
DRAWINGS