0% found this document useful (0 votes)
69 views

Risk Assessment for Lighting Control System Testing and Commissioning

Uploaded by

engbahaa.mb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
69 views

Risk Assessment for Lighting Control System Testing and Commissioning

Uploaded by

engbahaa.mb
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 6

PROJECT NAME

Ref No:
ACTIVITY– Lighting Control System Testing and Commissioning Rev.No:0
Page 1 of 5

Serial Sub-Activities Risks Involved Risk Rating


No. Hazards Identified Residual
(People & Severit Probabili Initial Control Measures
(Generic & Task) Risk
Property) y ty Risk
· TBT/DSTI shall be conducted by the
foreman/
· Unauthorized, · Cuts safety officer prior to work Low
1. Prepare work area untrained workers · Abrasions 2 A L commencement. (ALARP)
· Task specific safety training to be
provided.
· Authorized personnel to undertake
the job.
· Daily safety inspection should be
carried out
and eliminate the hazard.
•Hand tools shall be free from oil,
• Slip, trip and fall grease & etc.
Use of Hand tools • Damaged / worn out hand • Fatigue • Damaged tools shall not be used.
2. ( Hammer, pulling tools • Trigger finger 3 C M • Tools shall not be kept around the Low
spring, crimping • Flying objects • Cuts and abrasions work area, it (ALARP)
tools ) ∙ Mushroom Heads may causes to slip, trip and fall.
• Using incorrect type • Use right tools for the job
• Use eye/ face protection when there is flying
materials hazard, wear gloves while required to
protect the hands.
• The ladder should extend minimum one meter
from the top for safe movement
• Do not erect in slippery, uneven surface
• Should be set up with a 4 vertical to 1
• Person/ material • Sprain and horizontal slope ( 4:1 ) Low
falling from strain 3 C M • Step ladder must fully open and lock the (ALARP)
3. Use of ladder/ height • Fracture devices as per manufacturer recommendations.
scaffold • Over reaching • Spinal cord • Do not work from the top of two rungs of step
• Over loading damage ladders.
• Obstructing the access • Musculoskeletal • Remember the 3 point contact.
way Injury • Ladder shall be used for short duration works
• Slippery or uneven • Fatality Only limited to 15 min.
surface • Colour code system shall be implemented.
• Overhead structure • Do not stack materials on to the scaffold.
PROJECT NAME

Ref No:
ACTIVITY– Lighting Control System Testing and Commissioning Rev.No:0
Page 2 of 5
and cable • Visual inspection should be carried out before
• Untrained, use (i.e., hand rails, toe board, on the platform
unauthorized and any opening are there).
Workers
• Collapse of scaffold

Serial Sub-Activities Risks Involved Risk Rating


No. Hazards Identified Residual
(People & Severit Probabili Initial Control Measures
(Generic & Task) Risk
Property) y ty Risk
• Work at height is restricted during adverse
weather condition.
• Adequate lighting shall be provided while
working at night.
• Keep walkways free of obstacles, tools and
equipment.
• Safety harness shall be used above 2mtr height
and anchored in above shoulder height at all
time.
∙ Competent team shall be involved to
Testing & • Unauthorized/ execute the activities.
4. commissioning untrained • Electric shock • PTW ( Electricity ) shall be applied Low
using by multi Person and 3 B M and (ALARP)
meter, cable • Faulty Instrument Burns obtained prior to start work
tester • Improper identification • Cut and • Calibrated / certified instrument only
• Electrocution abrasion shall be
used.
• Ensure that the circuit is not live
before
using the instrument.
• Safe and obstruction free access for
working personnel’s shall be
maintained at all the times.
• Emergency procedure shall be
briefed to all personnel prior to start
the activity.
• Emergency evacuation plan shall be
readily available according to site
PROJECT NAME

Ref No:
ACTIVITY– Lighting Control System Testing and Commissioning Rev.No:0
Page 3 of 5
condition and briefed to the workforce
prior to start.
• Emergency contact numbers shall be
displayed at work location for easy
communication
• Trained first aider, fire warden and
emergency vehicle to be available at
the site during the activity.
• Communicate to all personnel about
testing
& commissioning.
• Warning signs and boards should be
provided
and area to be well barricaded
• Appropriate PPE shall be worn at all
times.

Serial Sub-Activities Risks Involved Risk Rating


No. Hazards Identified Residual
(People & Severit Probabili Initial Control Measures
(Generic & Task) Risk
Property) y ty Risk
PROJECT NAME

Ref No:
ACTIVITY– Lighting Control System Testing and Commissioning Rev.No:0
Page 4 of 5
• Electricity • Electrocution or • Lock out tag out (LOTO) procedure to be
5. Working with • Conductors ( water, metal, death followed during testing & commissioning. Low
electricity concrete ) • Burns and shocks 4 B M • Only those persons who have been adequately (ALARP)
• Broken wires • Muscle contraction trained and experienced in the work of
• Improper plug, case • Heart , lung electricity to allow for the same.
• Overloading Paralysis • Electrical work shall not carry out in wet
• Fire • Property damage Conditions.
• Do not overload to the circuits.
• Don’t use homemade electrical accessories and
use industrial type only.
• Disconnect main supply before commencing
of work.
• Defective tools and equipment should not be
used, report it and replaced it immediately.
• Temporary power supply shall be taken
through standard rated MCBs & RCBs.
• Temporary power supply cables shall
not
have joints.
• Barricade the location and signage to be
placed where circuits and equipment’s are
energized.
• Appropriate PPE shall be worn while working
in energized circuits. ( Insulated gloves, electric
resistivity shoe )
· Work notification shall be applied and
obtained prior to start the night work Low
∙ Poor illumination ∙ Fatality 3 B M from (ALARP)
6. While working at · Slip/trip/fall • Cuts main contractor.
night shift · Sufficient illumination shall be
provided.
· Light post shall be secured to avoid
fall.
· Proper cable management system
shall be
followed

Serial Sub-Activities Hazards Identified Risks Involved Risk Rating Control Measures Residual
PROJECT NAME

Ref No:
ACTIVITY– Lighting Control System Testing and Commissioning Rev.No:0
Page 5 of 5
No. (People & Severit Probabili Initial
(Generic & Task) Risk
Property) y ty Risk
· All materials shall be staged in
proper
manner without obstacles.
∙ Employees shall be trained about
∙ Dehydration heat
∙ Heat Stress · Sunburn stress symptoms & first aid Low
7. Working in hot · Skin Cancer 2 B M measures. (ALARP)
weather · Isotonic drinks shall be provided.
• Provide sufficient rest breaks based
on the
humidity & temperature conditions.
• Heat stress management plan shall be
developed and implemented during the activity.
· General housekeeping, Remove all
· Poor housekeeping surplus and unwanted waste
8. Work Completion · Slip/trip/fall · Fire 2 A L materials from the work place. Low
· All necessary precautions will be (ALARP)
adopted to
prevent fire

RISK MATRIX
PROJECT NAME

Ref No:
ACTIVITY– Lighting Control System Testing and Commissioning Rev.No:0
Page 6 of 5
Probability

A B C D E
Improbable Remote Occasional
Probable Frequent
Severity People Assets Environment Reputation 1 in 100,000 1 in 10,000 1 in 1000
1 in 100 years 1 in 10 years
Years Years years
Multiple
fatalities or
Extensive International
5-Catatrophic permanent Massive effect
damage impact
total
disabilities
Single
fatalities or
4-Severe permanent
Major
Major effect National impact
High Risk
damage
total
disabilities
Major injury
Local Considerable
Medium Risk
3-critical or health Localised effect
effects
damage impact (ALARP)
Minor
Minor
2-Marginal injury or Minor effect Minor impact
damage
health effects
Slight injury
Slight
1-Negligble or health
Damage
Slight effect Slight impact Low Risk
effects

3-E
HIGH 4-C,D,E
5-B,C,D,E
1-D,E
2-B,C,D,E
MEDIUM 3-A,B,C,D
4-A,B
5-A
LOW 1-A,B,C
2A

You might also like