13 Pouring Concrete M-20 for Drain Chute Km LHS 1 40.000 0.0400 OSS-SDS/HWY/5990 30-Nov-24 SPS-13
5900 5940 N/04020/04002/UP/RFI/HIGHWAY/S/1701
14 Pouring Concrete M-20 for Drain Chute Km LHS 1 20.000 0.0200 OSS-SDS/HWY/5991 30-Nov-24 SPS-13
5940 5960 N/04020/04002/UP/RFI/HIGHWAY/S/1702
15 Pouring Concrete M-20 for Drain Chute Km LHS 1 60.000 0.0600 OSS-SDS/HWY/5992 30-Nov-24 SPS-13
5960 6020 N/04020/04002/UP/RFI/HIGHWAY/S/1703
C Total Qty Nov-24 0.2200 Km
D Work Done Up to Date (A+B+C) 1.2000 Km
E Work Done Up to Previous SPS-12 0.9600 Km
F=D-E Work done in this SPS-13 0.2400 Km