Panel - check list

Panel installation and testing check list

Uploaded by

anmaruthi
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
10 views

Panel - check list

Panel installation and testing check list

Uploaded by

anmaruthi
Copyright
© © All Rights Reserved
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

INSPECTION & TEST PLAN FOR ELECTRICAL WORKS

FOR INSTALLATION/ ERECTION & TESTING OF SWITCH GEARS/ PCC/ MCC/


EMCCNFD's/ASB/LIGHTING PANELS/ HEATER PANELS / CONTROL PANLES OF
FILED EQUTS
ITP NO.: 3515 (Sheet 1 of
3)

FORMAT NO. :
PROJECT NAME:- Data center
REPORT NO:
PRINCIPAL CONSULTANT FIRM :- M/S BLOCK NO:
LOCATION:
CONTRACTOR :- ENTERPRISE
DATE:
PANEL TAG NO:
NAME OF WORK : ELECTRICAL WORKS
PANEL TYPE:
SERIAL NO: VOLTAGE RATING:
CURRENT RATING: SOR NO:
MANUFACTURER: FREQUANCY: 50HZ

Records to
SI. be
Contr Remarks
No Activity Submitted/
actor
. CAT CAT
Format
A. B. No.
Incoming Material inspection at site NA
1
a) Owners Supply
b) Contractors supply WC Note-1 Format E2
a. Calibration certificate of measuring & testing
2 equipment’s/instruments
WC RW RW Format E1
b. Field calibration, if any WC W S Format E1
Check the layout of base channels/frames and ensure the
Format
3 correct provisions for grouting/welding and cable entry WC S --
E8,E9
openings.
Ensure level and centre lines are within the prescribed limits
Format
4 and they match with the requirements of incoming Bus-ducts, WC S --
E8,E9
if any
Format
5 Ensure proper grouting/welding of the base channels/frames WC S --
E8,E9
Format
6 Ensure proper handling of panels WC S --
E8,E9
Check sequence wise (starting from centre or Bus-duct panel)
7 installation, final leveling and bolting up
WC S -- --
INSPECTION & TEST PLAN FOR ELECTRICAL WORKS
FOR INSTALLATION/ ERECTION & TESTING OF SWITCH GEARS/ PCC/ MCC/
EMCCNFD's/ASB/LIGHTING PANELS/ HEATER PANELS / CONTROL PANLES OF
FILED EQUTS
ITP NO.: 3515 (Sheet 2 of
3)

Records to
SI. be
Contr Remarks
No Activity Submitted/
actor
. Format
CAT CAT
No.
A B
Check main bus bar connection at all shipping sections and
shrouding at all tap-off points. Measure contact resistance of Format E8,
8 each bus bar joints. Checking the tightness of down comers
WC S -- E9
(feeding each feeders)
Check inter panel wiring after fixing of loose accessories and Format E8,
9 wiring
WC S -- E9
Ensure the level of flooring for smooth opening of panel
10 doors and drawing out & in operation of Breaker Trolleys
WC S -- --
Check interchangeabilities of circuit breakers, MCC Feeder Format E8,
11 Modules
WC S -- E9

12 Check equipment earthing & continuity of earth bus WC S S


Ensure thorough cleaning, removal of temporary spacers,
Format E8,
13 supports, any foreign materials and vacuum cleaning, dusting WC S -- E9
the panels
Verify the correctness, in accordance with the drawings, of all
Format E8,
14 type of relays, test blocks, control switches, meters & WC S S E9
instruments, motor starters, fuses, space heaters, etc.
Check name plate for each breaker, inspect & rest the
Format E8,
15 operating mechanics (Mechanically), interlocks, contacts, arc WC S S E9
chutes, auxiliary devices and adjustments as required
Visually check all relays and meters for removal of shipping
blocks and for mechanical damage..Ensure their range against. Format E8,
16 approved drawings, inspect calibration, testing and setting for
WC S S E9
each relay and meter.
Visually check name plates of CT's and PT's and ensure their
ratio, accuracy class and proper grounding against approved
Format E8,
17 drawings. Test their polarity, knee point voltage, Rcr and WC S S E9
ratio. Primary injection tests at three points on the
characteristics curve as per manufacturer recommendation.
Check tightness of bus-bar connections with torque Format E8,
18 wrench and measure contact resistance across joints.
WC HP HP E9
Format E8,
19 Test and witness IR value of the power and control bus WC HP HP E9
Format E8,
20 Test and witness high pot tests, as specified WC HP HP E9
Format E8,
21 Ensure tightness of connection of control wiring WC S -- E9
INSPECTION & TEST PLAN FOR ELECTRICAL WORKS
FOR INSTALLATION/ ERECTION & TESTING OF SWITCH GEARS/ PCC/ MCC/
EMCCNFD's/ASB/LIGHTING PANELS/ HEATER PANELS / CONTROL PANLES OF
FILED EQUTS
ITP NO.: 3515 (Sheet 3 of
3)
Records to
SI. be
Contr Remarks
No Activity Submitted/
actor CAT CAT
. Format
A B
No.
Check phasing & phase sequence between bus section Format E8,
22 and incomer
WC W S E9
Inspect secondary injection test and ensure tripping of Format E8,
23 C. B through protection relays
WC S S E9
Inspect primary injection & check the breaker tripping
through protective relays, check ammeter, voltmeter,
Format E8,
24 power factor indications etc. for proper functioning. WC W S E9
Conducting secondary injections on protective relay for
checking all protections and tripping
Switch on AC & DC control supply. Check the
sequence of operation of breakers electrically, local and
remote interlock; ensure proper alarm and annunciation Format E8,
and indications in Switch Gears/MCC/Control Panel. E9
25 Auto/Independent/manual mode of operation &
WC HP HP
(Annexure-
interlocks between of incomer & bus coupler shall be I)
checked as per Approved logics & schematics. Under
voltage tripping of breakers shall be verified.
Measure contact resistance and ensure simultaneous Format E8,
26 closing & making of breaker contacts.
WC S S E9
Check for relay parameters and settings recommended Format E8,
27 Setting charts
WC W W E9
Format E8,
28 Differential stability (as applicable) shall be verified. WC W W E9
Checking of Man machine communication and Format E8,
29 verification of graphics
WC S S E9

30 Mechanical Acceptance Test/Energisation protocol WC HP HP YES

INSPECTION & TEST DOCUMENTS

Review Test and Inspection Documents WC RW RW YES

NOTE : 1) For Incoming material Inspection please refer ITP no: 6-82-1010
CAT A: HT Switch Gears / PCC Control Panels VFD's
CAT B: MCC / EMCC/ASB/lighting panels.