Final Exam - Code
Final Exam - Code
Duration - 2 Hours
Books
- ACI 318-14 or 318-19
- Concrete Manual
- ASTM Packet
Email *
a) 25°F
b) 35°F
c) 40°F
d) 45°F
2) From the stripping of the molds to just prior to testing, final curing of * 1 point
a) 70°F to 77°F
b) 68°F to 78°F
c) 60°F to 80°F
d) 68°F to 86°F
a) 30
b) 70
c) 100
d) 150
e) 300
a) 1” to 2”
b) 1” to 3”
c) 1.5” to 2”
d) 1.5” to 3”
a) 8”
b) 12”
c) 24”
d) 30”
a) 50% of f’c
b) 75% of f’c
c) 85% of f’c
d) 100% of f’c
7) For a load bearing concrete wall that is 14 feet in height and fifty feet * 1 point
a) 4.000”
b) 4.313”
c) 5.680”
d) 6.720”
a) Type I
b) Type IIA
c) Type IIIA
d) Type IVA
e) Type VA
9) What is the required minimum inside diameter of bend for a #5 rebar * 1 point
a) 1.875”
b) 2.250”
c) 2.500”
d) 3.000”
e) 3.750”
11) Concrete made with Type III cement must be kept above what * 1 point
12) Samples of concrete for use in making strength specimens must be of * 1 point
what size?
a) 1/2 ft3
b) 1 ft3
c) 2 ft3
d) 3 ft3
13) Given: A proposed concrete mix is to be used for a reinforced parking * 1 point
deck slab located in a region where freezing and thawing are common, and
it will be frequently exposed to water and occasionally to deicing
chemicals. If it contains total cementitious materials of 564 lbs./yd3, what
is the maximum amount that may be comprised of fly ash, by weight?
a) 56 lbs./yd3
b) 94 lbs./yd3
c) 113 lbs./yd3
d) 141 lbs./yd3
e) 197 lbs./yd3
14) When f’c is 6000 psi, the initial curing of concrete strength specimens * 1 point
15) The purpose of slump testing is to measure which of the following * 1 point
elements of concrete?
a) Shrinkage
b) Strength
c) Workability
d) Plasticity
16) For a 5” concrete slab, what is the maximum spacing for #4 rebar if * 1 point
a) 12”
b) 15”
c) 18”
d) 21”
e) 25”
17) Given: A slab pour is to have a total of 46,000 sq. ft placed. The * 1 point
specifications call for the inspector to cast sets of five cylinders. How
many cylinders should you cast if ACI 318 is utilized as the minimum?
a) 25
b) 30
c) 45
d) 50
e) 55
18) For piping embedded in solid slabs, which of the following must be * 1 point
true?
c) It is between top and bottom reinforcement, unless being used for radiant
heating or snow melting.
b) Concrete that has been retempered outside the limits of ASTM C94.
20) Discharge of concrete must be done within what time frame? * 1 point
e) both a and b
a) True
b. False
22) What is the minimum amount of reinforcement that must be added * 1 point
around all window and door openings in a 12” thick concrete wall having
two layers of reinforcement?
a) 1 - #5
b) 2 - #5
c) 1 - #4
d) 2 - #4
e) 1 - #6
23) What is the minimum length of lap splices for spiral reinforcement * 1 point
a) 12”
b) 18”
c) 24”
d) 28”
e) 36”
24) Concrete produced with heated aggregates shall at no time during its * 1 point
a) 70ºF
b) 75ºF
c) 90ºF
d) 120ºF
e) 150ºF
25) The maximum temperature of concrete when delivered in hot weather * 1 point
a. 85
b. 90
c. 95
d. 100
26) A 36” square beam is placed using concrete with a slump of 2”. How * 1 point
a) rodding
b) vibration
c) jigging
d) rodding or vibration
e) rodding or jigging
27) For a shotcrete wall containing two curtains of #6 rebar, what is the * 1 point
a) 3”
b) 4.5”
c) 6”
d) 7.5”
e) 9”
28) What is the minimum temperature for concrete at time of placement * 1 point
for a 24” thick structural slab, if the ambient air temperature is 20ºF?
a) 45ºF
b) 50ºF
c) 55ºF
d) 65ºF
e) 70ºF
29) Transportation time for concrete strength specimens shall not exceed * 1 point
a) 4 hours
b) 6 hours
c) 8 hours
30) What is the specified cover for the bottom #8 reinforcing bars in a * 1 point
a) 2"
b. 1"
c. 1/2"
d. 1/4"
31) Piping shall be fabricated and installed such that which of the * 1 point
following is true?
32) The average strength of shotcrete cores shall meet or exceed at least * 1 point
a) 75
b. 80
c. 85
d. 100
33) Construction joints shall be located within the _________ of spans of * 1 point
a. edges
b. middle third
c. top
d. bottom
34) What is the minimum number of vertical bars that must be used for an * 1 point
a) 2
b) 4
c) 6
d) 8
e) 10
35) In a column, what is the maximum slope of an offset bent longitudinal * 1 point
a) 1 in 2
b) 1 in 4
c) 1 in 5
d) 1 in 6
e) 1 in 7
36) Which of the following is not required before concrete is placed on a * 1 point
c) Surfaces of the columns should be wetted and the standing water removed.
37) What is the maximum spacing of ties for a 16” x 24” column made with * 1 point
#3 ties, #7 vertical bars, and made from concrete with a maximum size of
aggregate of ½”?
a) 14”
b) 16”
c) 18”
d) 24”
38) What is the minimum effective depth of bottom reinforcement for a * 1 point
foundation footing?
a) 4”
b) 6”
c) 8”
d) 10”
e) 12”
39) When concrete is specified to be at least 5000psi, the specified air * 1 point
a. increased, 1
b. decreased, 1
c. increased, 2
d. decreased, 2
placed. The mix has a specified strength of 5000 psi and will include 38 cu.
yds. of material total. For this day, how many sets of strength samples
must be cast?
a) 1
b) 2
c) 3
d) 4
e) 5
41) Epoxy coating of reinforcing steel must conform to which of the * 1 point
following standards?
a) ASTM A36
b) ASTM A615
c) ASTM A706
d) ASTM A775
e) ASTM A996
42) For cold weather concrete, what is the required mix temperature at * 1 point
a) 40° F
b) 45° F
c) 50° F
d) 55° F
43) To what degree of accuracy must mixing water be measured for a * 1 point
a. .5%
b. 1%
c. 1.5%
d. 2%
44) What is the minimum concrete cover for #4 rebar used as stirrups in a * 1 point
a) 1-1/2”
b) 1-5/8”
c) 2”
d) 1-1/8”
45) What size rebar is required for ties in a 20’ tall column that is 36” * 1 point
a) #3
b) #4
c) #5
d) #6
46) What is the specified air content of the concrete as delivered for a * 1 point
a) 3.5%
b) 4%
c) 4.5%
d) 6%
47) For a 24” square column, with 4 #10 vertical bars contained within #3 * 1 point
a) 18”
b) 24”
c) 20”
d) 16”
e) 28”
48) What is the yield strength for a #4 Grade 60 low-alloy reinforcing bar? * 1 point
a) 40,000 psi
b) 60,000 psi
c) 75,000 psi
d) 100,000 psi
49) What is the maximum spacing for vertical and horizontal reinforcement * 1 point
a) 12”
b) 24”
c) 18”
d) 16”
e) 30”
50) A strength test is the average of how many 6 x 12 in. cylinders? * 1 point
a) 1
b) 2
c) 3
d) 4
construction?
a) Slabs supported by walls are cast while the walls are plastic.
52) What is the minimum straight extension of the tail for a standard 180° * 1 point
a) 1.5”
b) 2.25”
c) 2.5”
d) 4.5”
e) 6”
a) 2 - #8 bars
b) 4 - #4 bars
c) 3 - #6 bars
d) 5 - #3 bars
e) 2 - #5 bars
54) For ready-mix concrete specified as having a maximum slump of 5”, * 1 point
b) 2.5”
c) 3”
d) 3.5”
e) 4”
55) What is the minimum clear spacing between #7 longitudinal bars * 1 point
a) 1/2“
b) 7/8”
c) 2”
d) 1”
e) 1 1/2”
56) What is the required concrete cover for rebar in a cast-in-place grade * 1 point
a) 1 1/4”
b) 1 1/2”
c) 2 1/2”
d) 3”
57) What is the minimum specified strength of concrete used to fabricate a * 1 point
a) 2500 psi
b) 3000 psi
c) 3500 psi
d) 4000 psi
e) 5000 psi
58) Fresh concrete may be handled and placed such that which of the * 1 point
following is true?
a) Concrete that has been contaminated is adequately mixed with other material.
59) Which of the following is not a means of curing concrete which * 1 point
a) Curing compound
b) Ponding
d) Sprinklers
60) Given: 6060lbs cement batched and the target w/c ratio = .396. If there * 1 point
were 269.71 gallons of water batched, how much water can still be added
to the batch?
a) 13.5 gallons
b) 15.3 gallons
c) 18.3 gallons
d) 17.1 gallons