1.0 PURPOSE
This practice establishes the requirements for the preparation and issue of Supplier Quality
Surveillance (SQS) Reports.
2.0 APPLICATION
This practice is applicable to all projects where SQS personnel are performing supplier quality
surveillances, including reporting, verification and issue of SQS reports.
4.0 DEFINITIONS
See glossary at the end of this practice
6.0 REQUIREMENTS
6.1 The PSM / Surveyor will assign a number to all SQS reports according to Attachment 01,
SQS Report Numbering System.
6.2 The PSM / Surveyor will hold the Supplier Quality Alignment Meeting (SQAM) and issue
the Alignment Meeting Report (AMR) to document the results of the meeting in
accordance with Attachment 02, Supplier Quality Alignment Meeting and Report.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 1/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Supplier Quality Surveillance
Full Practice Printed from Quality Requirements System Global Library
6.3 The PSM / Surveyor will issue SQS Surveillance Reports in accordance with Attachment
03, SQS Surveillance Reports.
Prompt reporting is essential to keep project informed regarding quality surveillance activities.
Reports are to be generated utilizing the predefined templates available in Word format for the
specific commodity type. An Excel spreadsheet is also completed by the Surveyor which is
used by the PSM to update the surveillance information in MatMan.
6.4 The PSM / Surveyor will issue Non-Conformance Reports for identified
nonconformances, and also the associated Non Conformance Release Reports when
the nonconformance has been resolved, in accordance with Attachment 04, Non-
Conformance Report / Non-Conformance Release Report (NCR/NCRR).
6.5 The PSM / Surveyor will issue Supplier Observations when warranted in accordance
with Attachment 05, Supplier Observation Reports.
6.6 The PSM / Surveyor will issue the SQS Release Report for each Purchase Order once all
surveillance activities have been completed in accordance with Attachment 06, Supplier
Quality Surveillance (SQS) Release Report.
6.7 The assigned Surveyor will verify that all necessary documentation has been sent to the
PSM at the completion of the assignment.
Typically, documentation includes:
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 2/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Supplier Quality Surveillance
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 3/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 01
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 4/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
1.0 PURPOSE
These instructions provide the requirements for conducting a Supplier Quality Alignment Meeting (SQAM) at the
Supplier's facility and issuing the Alignment Meeting Report (AMR).
The purpose of the meeting is to ensure that the Supplier and those involved in fabrication and monitoring the quality
of the equipment fully understand the PO scope of work and corresponding inspection and quality requirements.
The meeting also serves to confirm that Fluor's surveillance participation is incorporated into the Supplier's ITP.
The Surveyor uses this information to prepare for, conduct and report the results of the SQAM.
Note: This is sometimes referred to as the Pre-Inspection Meeting (PIM), but Supplier Quality Alignment Meeting is
the preferred term.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 5/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 6/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 7/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 8/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 9/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 10/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
2.7 The PSM receives the minutes of meeting and Excel file from the Surveyor and reviews, edits if
necessary, makes the necessary distribution of the report in accordance with the project distribution
list, and files the report.
The PSM files the report in the corresponding purchase order assignment file on the network directory or in
an email folder for retention at project completion.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 11/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 02
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 12/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
1.0 PURPOSE
These instructions provide the requirements for the completion, transmission, and processing of SQS Surveillance
Reports.
Prompt reporting is essential to keep the project informed regarding quality surveillance activities. Reports are to be
generated utilizing the predefined templates available in Word and Excel Spreadsheet format.
This practice is applicable to SQS personnel who are performing supplier quality surveillances including reporting,
verification and issuance of Surveillance Reports.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 13/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
2.3 The assigned Surveyor will complete the SQS Surveillance Report (SR) form according to the
following instructions.
Complete the surveillance report including the appropriate surveillance activities associated with each visit to
a supplier's facility. When a surveillance activity is identified as not applicable include a brief explanation.
1. Insert Header Information (File Number and Report Number) by double clicking on the report form in
the header area next to “File Number”.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 14/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 15/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
Item “2” Total NCR(s) Issued: Include total number of NCR(s) issued to date for this
assignment. If none type “0”
NCR(s) Open: List the total number of NCR(s) considered open pending
verification, disposition, correction, etc.
Item “3” Repeat instruction above (“N” / Item “1”) for new SOR(s) issued this report
period
Item “4” Repeat instruction above (“N” / Item “2”) for total SOR(s) Issued to date
Item “6” Inspection Release Issued - check appropriate box by locating cursor over
the box and double click; select “checked / not checked”.
If “YES” check the box accordingly and list SQS Release Report number.
If, “NO” check the box accordingly.
Note: Entries such as “Unknown”, “Unavailable”, “TBD”, etc. will not be accepted.
Purpose: State short anticipated activities that will be performed during next visit (e.g. verify
material/WPS/NDE, witness bundle insertion, etc.)
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 16/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 17/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
Column
Column Name Description of required Information
Alpha
A File Number Pre-populated; do not change content
B PO Number Pre-populated; do not change content
C Supplier Pre-populated; do not change content
D Report Number SR01, SR02, SR03, etc. (no spaces, dashes, etc.)
E Contact Date MM/DD/YY – last date of the visit
F Report Date MM/DD/YY – date report is written
G Hours Expended Number of hours expended for resulting in this visit / report
(match the hours expended as indicated on your timesheet)
H Estimated Date of MM/DD/YY – date of next planned visit (must enter date if more
Next Contact visits are planned per the Assignment Instruction)
Note: For final visit, no date required in this row.
I Estimated MM/DD/YY – date the purchase order will be completed
Completion Date
2.5 The assigned Surveyor will submit the completed Surveillance Report and the Excel file to the PSM
within 48 hours of a visit.
2.6 The Project Surveillance Manager (PSM) will review the Surveillance Report and verify its content
adequacy and correctness, and add any clarifying comments as needed.
Upon receipt review, the PSM reviews the report and discusses any revisions to the report with the Surveyor.
2.7 The PSM will distribute supplier Surveillance Reports in accordance with the project distribution list,
and then file the report.
Reports are filed on the network directory or in an email folder.
2.8 The Project Surveillance Manager (PSM) will import the report information into the SQS Module in
the Material Manager® database using the Excel worksheet.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 18/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 03
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 19/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
1.0 PURPOSE
This practice outlines the roles and responsibilities of a quality representative when a product or service presented
for Fluor acceptance fails to comply with a Purchase Order (PO) or Contract quality requirements.
A Non-Conformance Report (NCR) will be issued to supplier(s)/Contractor(s) when findings deviate from quality
requirements of the Purchase Order (PO), Contract, specifications, drawings, Codes, Standards, and datasheets.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 20/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
2.2 The assigned Surveyor will complete the NCR portion of the form according to the following
instructions.
Update the information for each of the following fields on the selected form (refer to the graphic on the
previous page for location of data):
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 21/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
Note: Only one box (Category) will be checked. Should there be more than one category of non-
conformance identified for a given item a separate NCR will be issued. When the “Punch List
Attached” option is selected, the surveyor will complete the non-conformance punch list information
and follow the above.
“R” Detailed description of the nonconforming condition
“S” Detailed Commercial or Technical Requirement in which the equipment does not
comply with
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 22/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
Note: For Non-Conformance Punch List items to be repaired at site, the Surveyor will select the “Repair at
Site” box. The non-conformance will be closed and the NCR Punch List will be transferred to the
Site Quality Manager via distribution and be logged in the Project Quality Management System for
tracking and disposition at site.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 23/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
"A" – “F” This area is pre-populated by the MatMan System – DO NOT ADD OR
CHANGE ANY INFORMATION
Note: you may add rows for multiple punch items for a Tag Item
(See Example above)
"G" Surveyor to fill in quantity of items
"H" Surveyor to describe the deficiency of item that requires additional work
"I" Surveyor to provide overview of the disposition
"J" Project Surveillance Manager is responsible to rout form for signature of
applicable parties. The signed Punch List is then transmitted to the project
MCPlus coordinator. If MCPlus is not used, the PQM will issue stand alone NCR
in QMS to transfer the punch list items to the fabrication yard or site for
disposition / closure.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 24/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
2.4 The assigned Surveyor will complete the Excel spreadsheet to document each Non-Conformance
Report.
The entry information in the Excel sheet columns will match exactly to the entry in the Non-Conformance
Report form.
2.5 The assigned Surveyor will update the Excel spreadsheet to document each Non-Conformance
Release Report when the NCRs have been addressed and closed.
The entry information in the Excel sheet columns will match exactly to the entry in the Non-Conformance
Report form. When releasing an NCR, use the same NCR row entry you Opened the NCR with to Close it.
DO NOT CHANGE THE NUMBER FROM NCR01, NCR02, NCR03, etc!!!
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 25/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 26/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
2.6 The Surveyor will submit the Nonconformance Report and the Excel file to the PSM on the day of
detection.
The Surveyor will also provide a copy of each NCR-NCRR to the Supplier's Quality Control (QC)
representative prior to leaving the shop.
The assigned Surveyor will also notify, via telephone, the PSM or responsible Commodity Engineer
whenever an item that required an NCR is identified.
2.7 The PSM will review, process and distribute the NCR issued on the project in accordance with the
project distribution list.
Project Surveillance Manager (PSM)/Project Surveillance Coordinator (PSC) will verify NCR Report content
adequacy and correctness.
2.8 The PSM will file a copy of the report in the corresponding PO SQS assignment file.
2.9 The PSM will expedite the resolution of each NCR with the responsible Commodity Engineer.
2.10 The PSM will import the information from the NCR-NCRR form into the MaterialManager® SQS
Module using the Excel worksheet.
2.11 The PSM will select the impact level of the NCR in the MaterialManager® SQS Module as Low,
Medium, or High.
PSM will select the impact level of the NCRR in the MaterialManager® SQS Module as Low, Medium, or
High.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 27/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 28/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
The impact level is determined based on involvement to disposition and is progressed as outlined below:
2.12 The Surveyor will document the completion of corrective action by the Supplier by completing the
release portion of the NCR-NCRR form and issue it to the PSM.
The Surveyor will release the non-conformance only when the authorized corrective action has been
completed.
The Surveyor also updates the release portion of the Excel spreadsheet as discussed in Section 2.5.
Note: The NCR-NCRR may be used to partially clear a non-conformance when only some of several items
on an NCR have been corrected.
A copy of each NCR release is also provided to the Supplier's QC representative.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 29/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 04
Full Practice Printed from Quality Requirements System Global Library
2.13 The Surveyor will take the following steps when there is a Non-Conformance with Conditional
Release and Punch List.
If release is based on certain conditions being met prior to shipment and these conditions are not being met,
the following actions will be initiated by the assigned SQS representative, PSM, and Responsible Engineer
(RE):
1. The Surveyor will advise the Supplier immediately when materials / equipment cannot be released for
shipment due to the existence of non-conforming conditions at time for release for shipment.
2. The Surveyor will prepare a SQS Non-Conformance Report Punch List identifying all non-conforming
conditions and discuss with Supplier what action they intend to correct, schedule impacts, or what will
be deferred to site for correction.
Note: All corrective actions / work deferred to site will have Project Management approval prior to
shipment.
3. The Surveyor will provide the PSM copy of the non-conformance report and punch list if the Supplier is
planning on deferring any non conforming conditions / work to site for correction.
4. The PSM will provide the Project Manager, Project Procurement Manager, Site Receiving Manager,
Client Representative, and Responsible Engineer a copy of SQS Conditional Release Report
highlighting all non conforming conditions / work the Supplier is deferring to the site for correction.
5. The Project Management Team will collaborate with all affected parties (i.e. Logistics, Construction,
Procurement, Client, and RE) prior to issuance of conditional punch list acceptance of the Supplier’s
intention to defer nonconforming conditions / work to site for correction.
2.14 The PSM will copy and distribute the NCR-NCRR form once the release portion at the bottom of the
form has been completed.
2.15 The PSM will file the completed NCR-NCRR in the SQS assignment file.
2.16 The PSM will import the release information into the MaterialManager® SQS Module to close the
NCR.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 30/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 05
Full Practice Printed from Quality Requirements System Global Library
1.0 PURPOSE
These instructions are to be used by the Project Surveillance Manager (PSM) / Surveyor to document those
deviations, problems, and situations that are not by definition non-conformances, but which could, if left uncorrected,
result in NCRs at a later time. These types of deviations, problems and situations will be documented as Supplier
Observations.
These issues are documented in Supplier Observation Reports (SORs) which provide a means to track those
situations where the surveyor has taken a proactive role in avoiding potential quality problems and/or shipping
delays. It will also contribute to a more accurate quality profile of a Fluor Supplier. These are not on separate forms,
but are included in the Surveillance Reports.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 31/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 05
Full Practice Printed from Quality Requirements System Global Library
2.3 The PSM/PSC will verify that SORs are documented in the Surveillance Reports and the condition
described by the SQS Surveyor has the necessary information to support the observation.
If the PSM feels an NCR has been issued in lieu of an SOR, the Surveyor is contacted to discuss the
circumstances surrounding the issuance of the SOR prior to report distribution.
2.4 The SQS Surveyor will verbally advise the Supplier’s quality representative of the identified
observation for corrective action.
2.5 The PSM/PSC will review, process, and distribute SQS Surveillance Reports in accordance with the
project distribution list and highlight the SORs when needed.
The PSM assists in resolution of any SORs which might require project input / action or support.
2.6 The SQS Surveyor will complete the Excel worksheet and submit it to the PSM for import to MatMan
for update of the SOR data.
Categories and description will be the same as those identified in the Surveillance Report and will indicate if
the SOR is “Open” or “Closed”.
The entry information in the Excel sheet columns will match exactly to the entry in the Surveillance Report
form in the Action Items / Areas of Concern section.
OPEN SORs –
Column
Column Name Description of Required Information
Alpha
J SOR # SOR901, SOR902, SOR903,…– (No spaces, dashes, etc.)
K SOR Type SOR Category – choose category from drop down menu. One Category per SOR.
(click box for drop down arrow)
L SOR Description Unlimited text, row will expand as text is entered. Text is to give full detail as to why
SOR was written. Be sure to “double click” in the applicable row/column field where
text is to be entered (cursor will blink in field). (match description in SR form – copy
and paste)
M Status Select OPEN (drop down)
Note: There may be more than one entry of SOR per report. Just use the next row and add the next SOR number as
shown by 902 above. Do not enter the report information (columns D-I), only the SOR information (columns J-M).
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 32/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 05
Full Practice Printed from Quality Requirements System Global Library
Column
Column Name Description of Required Information
Alpha
J SOR # SOR901, SOR902, SOR903, etc. (No spaces, dashes, etc.)
K SOR Type SOR Category – choose category from drop down menu. One Category per SOR.
(click box for drop down arrow)
L SOR Description Unlimited text, row will expand as text is entered. Text is to give full detail as to why
SOR was written. Be sure to “double click” in the applicable row/column field where
text is to be entered (cursor will blink in field). (match description in SR form – copy
and paste)
2.7 The PSM will Import the SOR information included in the SQS Reporting Excel worksheet into the
MaterialManager® Supplier Quality Surveillance Module.
Each observation will be entered as a separate report using sequential numbers beginning with SOR901 as
reported by the Surveyor. The category, description and open/closed status of the SOR will be entered in
the same manner as an NCR.
Upon resolution of the SOR, the PSM will reflect the SOR as "Closed" in the MaterialManager® SQS
Module.
2.8 The SQS Surveyor will obtain the objective evidence needed to address and close the condition
described in the SOR prior to the Supplier presenting the material / equipment for Fluor’s
acceptance.
Closed SORs will be documented in the next issued Surveillance Report. Failure of the Supplier to
adequately address an SOR will result in the issue of an NCR.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 33/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 06
Full Practice Printed from Quality Requirements System Global Library
1.0 PURPOSE
These instructions provide requirements for preparing, issuing, and distribution of Supplier Quality Surveillance
(SQS) Release Reports.
An SQS Release Report is issued to a Supplier when the assigned Surveyor has completed the required surveillance
activities identified in the Assignment Instructions and found the activities associated with the product(s) meet the
PO/Contract quality requirements.
The Project Surveillance Manager (PSM), Project Surveillance Coordinator (PSC), and Surveyor will use this practice
when the Surveyor, in the execution of an SQS surveillance assignment, has found surveyed equipment / materials
conform to the Purchase Order (PO)/Contract requirements, including any conditional items.
Note: Issuance of the SQS Release Report does not relieve the Seller from any obligations related to the PO.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 34/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 06
Full Practice Printed from Quality Requirements System Global Library
2.3 The assigned Surveyor will complete the SQS Release Report according to the following
instructions.
1. Insert Header Information (File Number and Report Number) by double clicking on the report form in
the header area next to “File Number”.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 35/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 06
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 36/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 06
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 37/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Attachment 06
Full Practice Printed from Quality Requirements System Global Library
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 38/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Supplier Quality Surveillance
Full Practice Printed from Quality Requirements System Global Library
DEFINITIONS
The following terms and acronyms apply to this practice.
Title Description
Alert and Warning List (AWL) Contains listing of suppliers and contractors whose recent performance or
financial conditions indicate capability issues in providing consistent
execution to Fluor projects. Refer to Practice 000.400.0800, Alert and
Warning List.
Coreworx (CWX) Coreworx (CWX) is the approved Fluor Document Management System
(DMS) and Project Collaboration System (PCS) that allow the project team to
exchange files or access documents and data issued on the project.
Discipline Control Level This is a special type of Level 4 schedule for Engineering, used by Project
Schedule (DCLS) Discipline Leads for planning their work.
Non-Conformance Report / A form used for documenting non-conforming conditions and release of those
Non-Conformance Release conditions.
Report (NCR/NCRR)
Project Surveillance Works for the PSM and may assume some of the duties assigned to the PSM
Coordinator (PSC) as delegated.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 39/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Supplier Quality Surveillance
Full Practice Printed from Quality Requirements System Global Library
Quality and Certification Quality and Certification Requirements (Q&CR) form has two purposes: 1.
Requirements (Q&CR) Conveyance to Supplier as to observations and hold points that are required
to be included in the Supplier’s Inspection and Test Plan, an attachment to
the PO, or to the Supplier’s equivalent ITPs. 2. Used by PSM or Project
Surveillance Coordinator (PSC) as instruction to the assigned Surveyor on
the required level and detail of surveillance for a particular order. Note: he
Q&CR form is NOT used to outline all inspection and quality control
requirements. These are defined by the Commodity Engineer in the
requisition and data sheets.
SQS Release Report Supplier Quality Surveillance (SQS) Release Report indicates that the
equipment has been surveyed to the degree outlined in the SAI and its
issuance does not imply that 100 percent surveillance was performed or that
the equipment/material was accepted on that assumption.
SQS Surveillance Report (SR) SQS Surveillance Report (SR) is a key deliverable of source inspection and is
the progressive inspection reports detailing the documents reviewed,
inspection activity performed, observed and/or witnessed during the source
inspection visits. The report is normally on a standard format, and follows a
consistent approach to reporting as specified by the purchaser.
Supplier ITP Supplier Inspection and Test Plan (ITP) is a detailed plan developed with all
stages of inspection and various witness points; includes observations and
essential details and is an attachment to the PO, or to the supplier’s
equivalent ITPs; integrates practices and procedures contained in the
Supplier’s Quality Management System.
Supplier Observation Reports Supplier Observation Reports (SOR) are PSM and/or Surveyor identified
(SOR) deviations, problems and situations which are not by definition NCRs, but
which may, if left uncorrected, could result in NCRs at a later time. The intent
is to verbally inform supplier(s) of a potential non-conforming situation or
fabrication practice.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 40/41
1/27/2021 000.450.1600 Supplier Quality Surveillance (SQS) Reporting.pdf
Practice 000.450.1600
Date 27Jan2021
Supplier Quality Surveillance
Full Practice Printed from Quality Requirements System Global Library
Supplier Quality Alignment Supplier Quality Alignment Meetings (SQAM) are meetings held with
Meetings (SQAM) suppliers on POs that require SQS to ensure alignment of all activities and
communications. Formal alignment meetings are arranged for high critical
and high value purchase orders. The meeting is chaired by the assigned SQS
Surveyor with multiple project team member participants, and may include the
Client. Informal alignment meetings are typically requested for medium to low
critical and valued purchase orders. The meeting will be chaired by the
assigned SQS Surveyor with no project team members anticipated in
attendance.
Supplier Quality Surveillance Refers to a supplier quality surveillance approach that provides a specific
(SQS) level of assurance that material/equipment released for shipment conforms to
the PO requirements and/or approved project deviation.
© 2021, Fluor Corporation. All rights reserved. Fluor Restricted Data. Further copying or distribution only by permission.
http://localhost:8082/PDF/000.450.1600%20Supplier%20Quality%20Surveillance%20(SQS)%20Reporting.pdf 41/41