Grid-Development-Plan-2018-2040
Grid-Development-Plan-2018-2040
DEVELOPMENT PLAN
2018– 2040
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 1
GRID
DEVELOPMENT PLAN
2018– 2040
2 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Message from Management of UETCL
I am pleased to introduce to you this latest edition of our Grid development Plan
(GDevP) 2018 – 2040. The GDevP is a strategic document in UETCL’s overall planning,
which is in line with the Company’s Corporate Business Plan (CBP). It details the future
grid requirements in terms of projects and investment costs to meet the national load
growth, generation developments and regional interconnection requirements.
The 2018 edition of the Grid Development Plan provides a 23 year outlook of the
Uganda transmission system.
The Electricity Sector is one of the major enablers of economic transformation and
with this in mind, the GDevP will aid UETCL and the sector at large to make the right
investments to the grid to enable industrialization which is line with Vision 2040. The
GDevP is therefore a necessary guide to Government of Uganda on the required
investments to the transmission grid and will aid in sourcing funding and prioritizing
investments. As such, this document is important in fast tracking the Implementation
of Uganda’s Development Agenda.
Finally, I would like to thank and appreciate the efforts of all our stakeholders whom
we have worked with over the course of the year formulating various plans and
in particular, Ministry of Energy and Mineral Development, Electricity Regulatory
Authority, Uganda Electricity Distribution Company Limited, Uganda Electricity
Generation Company Limited, UMEME, Rural Electrification Agency amongst others.
Your contribution is much appreciated.
Willy K. Kiryahika
Managing Director/CEO
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 3
Foreword
The Grid Development Plan (GDevP) is a strategic document in UETCL’s overall planning, which is in line with
the company’s Corporate Business Plan (CBP).
The GDevP is updated annually. It details the future grid requirements in terms of projects and investment
costs to meet the national load growth, generation developments and regional interconnection requirements.
The 2018 edition of the Grid Development Plan provides a 23 year outlook of the Uganda transmission system.
The GDevP presents the latest demand forecast, generation expansion plan, Demand – Supply Balance for
the current and subsequent years, power system analysis result, the Grid Investment Requirements and
Implementation Schedule.
The 2018 edition presents an outlook of three scenarios showing their planned implementation strategy and
recommendations.
• The base case scenario looks at the business as usual case.
• The National Development Plan II (NDP 2015-2020) scenario that aims at strengthening Uganda’s
competitiveness for sustainable wealth creation, employment and inclusive growth with set targets
to be implemented within 5years.
• The Uganda’s VISION 2040 scenario that aims at transforming Ugandan Society from a Peasant to a
Modern and Prosperous Country within 30 years.
The 2018 GDP edition is our planning reference guide for the year 2018-2040.
4 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Table of Contents
Foreword 4
Table of Contents 5
List of Tables 7
List of Figures 8
Abbreviations and Acronyms 9
Executive Summary 11
Background 12
2 The Grid Development Plan Process 13
2.1 Objective for the Grid Development Plan 13
2.2 Methodology 13
2.2.1 The Grid Development Plan Process 13
3 Planning Criteria 15
3.1 Transmission Planning Criteria 15
3.1.1 System Voltage 15
3.1.2 Synchronism 15
3.1.3 Equipment Loading 16
3.1.4 Reactive Power Compensation 16
3.1.5 Voltage Selection 16
3.1.6 Reliability Criteria 16
3.1.7 Operating Reserve 16
3.1.8 Generation 16
3.1.9 Fault Current Criteria 16
3.1.10 System Frequency 17
3.1.11 Information and Communication Technology 17
Base Case Scenario 19
4 Load and Generation Prognosis 20
4.1 Assumptions for Demand - Supply Prognosis 20
4.1.1 Historical Demand Trends 20
4.1.2 Gross Domestic Product 22
4.1.3 Population Growth 22
4.1.4 System Losses 22
4.1.5 Export Potential 22
4.1.6 Load Factor 23
4.2 Assumptions for Generation Plan 23
4.3 Generation Expansion Plan 25
4.4 Present Demand - Supply Status 27
4.5 Demand Forecast 29
4.6 Forecasted Generation Mix 31
4.7 Demand-Supply Balance Findings 33
4.7.1 Observations and Findings from Demand Supply Balance 34
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 5
5 Power System Analysis 36
5.1 Present Power System 36
5.2 Power System Models 36
5.2.1 Model Inputs And Outputs 36
5.2.2 2017 Model – Baseline 37
5.2.3 2018 Model 38
5.2.4 2019 Model 39
5.2.5 2020 Model 40
5.2.6 2025 Model 41
5.2.7 2030 Model 43
5.2.8 2035 Model 44
5.2.9 2040 Model 45
6 Grid Investment Plan (2018-2040) 47
6.1 Grid Investment Plan Summary 47
6.2 Summary of Financial Requirements by the year 2040 59
6.3 Regional Interconnection Power Lines 61
6.4 Project Prioritization for Financing 61
6.5 Information and Communication Technology 64
7 NDPII Scenario 65
7.1 Load and Generation Prognosis 66
7.1.1 Assumptions for Demand Supply Prognosis 66
7.1.2 Demand and Generation Balance 67
7.1.3 Existing and Proposed Generation Resources 67
7.2 Observations 68
7.3 Projects to Realize NDPII 68
8 Vision 2040 71
8.1 Load and Generation Prognosis 72
8.1.1 Assumptions for Demand Supply Prognosis 72
8.1.2 Assumptions on Available Energy Resources By 2040 72
8.1.3 Vision 2040 Case GDP Forecast by 2040 72
8.1.4 Demand Forecast Vision 2040 73
8.2 Recommendations 74
9 Risk Analysis 75
10 Stakeholders 77
Appendices 79
A.1 Demand - Supply Balance and Prognosis 81
A.2 GIP Implementation Plan and Schedule 91
A.3 UETCL Transmission Lines 107
A.4 UETCL Substation Transformation Capacity 113
A.5 Maps 123
A.5.1 Uganda Power System Present and Future Network 124
A.5.2 East African Power System 125
A.5.3 National Development Plan Scenario (NDP) 126
6 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
List of Tables
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 7
List of Figures
8 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Abbreviations and Acronyms
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 9
km Kilo meter
KML Kilembe Mines Limited
kV Kilo Volt (1kV=1000 Volts)
kW Kilo Watt (1kW=1000 Watts)
kWh Kilo Watt Hour
MDMS Meter Data Management System
MEMD Ministry of Energy and Mineral Development
MoFPED Ministry of Finance, Planning and Economic Developement
MVA Mega volt Ampere
MVAr Mega Volt Ampere- reactive
MW Mega Watt
NBI Nile Basin Initiative
NDP National Development Plan
NELSAP Nile Equatorial Lakes Subsidiary Action Programme
NEMA National Environment Management Authority
NFA National Forestry Authority
OPGW Optical Ground Wire
OTDR Optical time Domain Reflectometer
PDH Plesiochronous Digital Hierarchy
PMA Power Market Analyzer
PSA Power Sales Agreement
PSS/E Power System Simulation for Engineers
RAP Resettlement Action Plan
REA Rural Electrification Agency
RPT Regional Power Trade
SCADA Supervisory, Control, and Data Acquisition
SDH Synchronous Digital Hierarchy
SVC Static var Compensator
SWECO SWECO AB of Sweden
TCP Transfer Control Protocol
SIA Social Impact Assessment
UBOS Uganda Bureau of Statistics
UETCL Uganda Electricity Transmission Company Limited
USD United States Dollar
UWA Uganda Wildlife Authority
var Volt Ampere Reactive
WA Wheeling Agreements
WIS Wayleaves Information System
WB World Bank
10 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Executive Summary
Uganda Electricity Transmission Company Limited (UETCL) has a leading role in developing, Operating and
maintaining an efficient High Voltage Transmission Grid (HVTG) to meet the national load demand, power evacuation
from new generation plants and regional power exchange requirement through regional interconnections within
the national and International technical, social-economic and environmental standards.
A key responsibility in this respect is to constantly plan and develop the HVTG. The purpose is to establish a
rationale for building a robust network, improve reliability and quality of supply, which will in turn contribute
towards the economic development of Uganda.
In line with company objectives, the Grid Development Plan (GDevP) is a strategic document in UETCL’s overall
planning process and thus must be communicated to all major stakeholders. The plan, which covers a period of 23
years, identifies and justifies new grid investments. It is reviewed and updated annually to reflect latest information
on Government policy and strategies. It is also an input to the company’s financial projections and annual budget.
The GDevP presents results of technical analyses for various investments to meet the national demand and power
exchange obligations.
The technical analysis derived from power system studies form a basis for determining technical feasibility of
the proposed projects. The results from the technical analysis are used to determine the Grid Investment plan
and the associated cost estimates which culminate into financial projections. The Environmental and Social
Impact Assessment are carried out before implementation of each individual project as required by the National
Environment Management Authority (NEMA).
The results from the above analyses indicate high capital investment requirements over a period of 2018-2025.
This is mainly attributed to the many generation plants that are to be commissioned during this period and
the corresponding power evacuation transmission lines and Substations. In order to absorb the new generation
capacity, several grid and substations extensions and reinforcements are to be implemented in the same period.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 11
Background
Uganda Electricity Transmission Company Limited (UETCL) has a major role in contributing to the development
of an efficient electricity sub sector in Uganda through planning, developing and maintaining an efficient
transmission grid to meet the national electric power requirements within the allowable national, regional and
international standards.
UETCL owns, operates, develops and maintains the high voltage transmission grid. The grid connects power
generation plants to load centers throughout the country as well as interconnection with neighboring countries.
UETCL also owns a National Control Center which coordinates and monitors grid operations and maintenance
activities.
Presently, the transmission grid comprises 150km of 220kV (initially operated at 132kV), 1443km of 132kV, 300m of
132kV underground cable, 35.2km of 66kV high voltage transmission lines and 20 substations (includes Kabulasoke
and Nalubaale switching stations).
The Grid Development Plan (GDevP) is a planning document that is written in line with UETCL’s strategic Corporate
Business Plan. It details present and future transmission grid infrastructure that will support National demand
growth, generation requirements and regional power trade obligations.
The GDP is updated annually to review the System Demand forecast, Generation Planning, Demand – Supply
Balance for the current and subsequent years, Power evacuation transmission lines and Substations, Grid
expansion requirements in line with National Development Plan II (NDP), Vision 2040, sustainable energy for all,
rural electrification strategy and plan, renewable energy policy among others, Power System Modeling Analysis
Results, the 2018-2040 Grid Investment Plan, Financial Implications and Proposed implementation schedule as
well as expectations from Stakeholders to provide a harmonized energy sector planning process.
The 2018 edition GDP is UETCL’s planning reference guide for the years 2018-2040.
12 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
2 THE GRID DEVELOPMENT PLAN PROCESS
2.2 METHODOLOGY
A scenario based approach has been adopted for the 2018 Grid Development Plan Update. Three scenarios have
been considered as follows:
• Base Case Scenario
The main assumptions for this scenario include: observed historical demand growth trends, Growth projections
of the Gross Domestic Product (GDP), distribution connection strategies and regional power trade projections,
implementation of loss reduction strategies and the need to address constraints that have created suppressed
demand in the past.
• NDPII Scenario
This scenario is designed to implement the second National Development Plan (NDPII) launched in March
2015. The planning horizon of this scenario is five years from 2015 to 2020.
• Vision 2040
Uganda Vision 2040 provides development paths and strategies to operationalize Uganda’s Vision statement
which is “A Transformed Ugandan Society from a Peasant to a Modern and Prosperous Country within 30
years”. It aims at transforming Uganda from a predominantly peasant and low income country to a competitive
upper middle income country.
It builds on the progress that has been made in addressing the strategic bottle-necks that have constrained
Uganda’s socio-economic development since independence, including; ideological disorientation, weak private
sector, underdeveloped human resources, inadequate infrastructure, small market, lack of industrialization,
underdeveloped services sector, underdevelopment of agriculture, and poor democracy, among others.
The Vision 2040 is conceptualized around strengthening the fundamentals of the economy to harness the
abundant opportunities around the country. The identified opportunities include: oil and gas, tourism, minerals,
ICT business, abundant labour force, geographical location and trade, water resources, industrialization and
agriculture among others that are to date considerably under-exploited. Achieving the transformational goal will
thus depend on the country’s capacity to strengthen the fundamentals including: infrastructure (energy, transport,
water, oil and gas, and ICT); Science, Technology, Engineering and Innovation (STEI); land use and management;
urbanization; human resource; and peace, security and defense and that’s where UETCL comes in to expand the
transmission network and offer a strong backbone that delivers bulk, quality and reliable power.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 13
Figure 1: GDevP process
From Figure 1, it can be observed that the inputs to the GDevP process include both external and internal factors,
which are then used in the analyses (load forecast and power system analysis) to yield results which are further
analyzed to come-up with the outputs.
The load forecast conducted for the Base, NDPII, and Vision 2040 scenarios for the period 2018 - 2040 was based on
the respective assumptions for each scenario as detailed in sections below respectively. Power system constraints
as observed in the day to day operation of the network were considered in the power system analysis. These
include quality of supply, equipment loading, system reliability and availability.
Generation expansion planning was based on the implementation timelines for power plants under construction
and those planned (Licensed, with or without executed Power Purchase Agreements). The demand-supply balance
analysis for each respective scenario recommended the timing of additional required generation capacities.
Power system studies and analysis were carried out on eight system models. The results formed the basis for
determining the Grid Investment Plan that details the technically feasible projects with their respective cost
estimates and timing.
14 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
3 PLANNING CRITERIA
The above limits may be exceeded only during outages of 400kV lines and in such cases it is necessary to supply
dynamic VAr resources at sensitive nodes. Such nodes should be identified by conducting power system analyses.
Under normal operations when all the system elements are healthy and tap positions of the power transformers
at the sending end at the nominal tap, the system voltages at various levels at the tail end of the lines shall be as
close to the nominal voltage as possible. The tap positions may be increased or decreased at peak load or off load
conditions as need arises.
The system should withstand outage of any two circuits of 220kV lines or any one circuit of 400 kV line with voltage
and frequency levels remaining within prescribed limits.
3.1.2 SYNCHRONISM
The system shall remain in synchronism even in case of a single line to ground fault or three phase fault, assuming
successful clearance of fault by the protective devices.
Adequate margin shall be available, in terms of voltage and steady state oscillating stability. The voltage angles
between consecutive substations should be in the region of 30 degrees.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 15
3.1.3 EQUIPMENT LOADING
Under normal conditions all transmission equipment can be loaded up to 100% of the continuous rating. Under
contingency conditions, this will be allowed to increase to 120% of continuous rating depending on the age and
physical conditions of the equipment.
3.1.8 GENERATION
For peak load conditions, optimal generation mix comprising of various energy resources taking into consideration
the marginal cost of production for the different plants is recommended to be used. For the minimum load
conditions, the must run power plants shall be used in conjunction with the most economical generation.
16 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
the rated fault interrupting capacity of the circuit breaker.
Rated Voltage (kV) Switchgear Rating (kA)
400 63
220 40
132 31.5
66 31.5
33 25*
11 25*
Table 2: Switchgear rated fault current interrupting capacity
*Due to the distribution grid configuration adopted and the proximity of generation sources to the medium
voltage buses, it has necessitated the installation of higher rated circuit breakers. This is considered on a case by
case basis.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 17
18 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
BASE CASE
SCENARIO
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 19
4 LOAD AND GENERATION PROGNOSIS
The load forecast is based on projected growth of Gross Domestic Product (GDP), population and new electricity
connection, regional power trade obligations and power transmission and distribution losses. The tool used for
load forecasting is an excel based econometrics model. The assumptions and results for the load forecast and
demand-supply balance are discussed below.
The average growth for the past ten years for system peak demand, domestic demand, system energy and
domestic energy is shown the table below.
Average growth (2008 – 2017)
System peak demand (MW) 5.59%
Domestic demand (MW) 3.99%
System Energy (GWh) 7.5%
Domestic Energy (GWh) 6.9%
TABLE 4: Average demand and energy growth for years 2008- 2017
20 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Figure 2: Trend of Uganda’s electricity peak demand (Jan 2011 - Jan 2018).
• The total peak demand for Uganda including exports significantly increased from 440MW in 2011 to as
high as 540MW in December 2012 as shown in figure 2. The significant growth in 2012 was as a result of
the commissioning of the Bujagali Hydro Power Plant which unlocked some of the unserved demand
due to load shedding that was experienced up to 2011.
• A significant spike is observed in 2012, 2014, 2016 and 2017 for the total peak demand due to an increase
in exports. This increase in exports for 2012 and 2014 was attributed to the shutdown of the transmission
line in western Kenya whereas for 2016 and 2017 was attributed to the draught in the western region
of Kenya and constraints in their transmission line capacity between western and eastern side of Kenya
leading to an increase in purchases of power by Kenya.
• The rate of growth in domestic peak demand is however noted to have been on average increasing
slowly at the rate of 5.6% starting from 2011 to 2017. In particular, domestic demand has been fluctuating
between 420MW and 562 MW from 2011 to 2017 with the highest domestic demand registered in
December 2017.
• Trend of energy sales compared to peak demand, it can be observed that the average growth in energy
sales has been 6% since 2011 to date. Despite the lower growth in peak demand which was less by 2%,
the growth in sales was significantly higher. The growth of total energy sales in 2017 was 9% compared to
6% in 2016 due to increased exports to Kenya.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 21
4.1.2 GROSS DOMESTIC PRODUCT
Historical of GDP Growth Rate
Recorded GDP
2011/12 2012/13 2013/14 2014/15 2015/16 2016/17
growth rate
4.4% 3.3% 4.8% % 4.7% 4.0%
Source: UBOS
Table 5: Historical GDP values
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017
Total Energy Losses (%) 38 39 33.9 31.3 29.6 28.1 25 23.1 20.3 19.2
Transmission Losses (%) 4.3 3.8 4.2 3.35 3.98 3.6 3.27 3.37 3.9 3.86
Distribution Losses (%) 34 35 30 27.3 26.1 24.3 21.3 19.5 19 16
Table 7 :System losses
Source for transmission losses: UETCL System Annual Operations Reports
22 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Energy Sales (GWh)
2010 2011 2012 2013 2014 2015 2016 2017
KPLC 29.24 38.2 37.9 47.41 107.06 56.03 83.21 225.88
Total Export 76.71 93.87 99.20 105.36 167.74 121.45 165 316.63
% Growth Rate -6.5% 22.4% 5.7% 6.2% 59.2% -27.6% 35.9% 91.9%
TABLE 9: Energy exports
Source: UETCL Annual Report
Uganda has not concluded any new export contract with her neighbouring countries however a Wheeling
Agreement was signed between Kenya, Uganda and Rwanda for the export power from Kenya to Rwanda over
UETCL’s network until 2019.
In this analysis it is assumed that no additional export above 50 MW (export to Kenya and Tanzania) will be made
by end of 2020. This assumption is mainly based on the fact that Uganda does not have any new Power Sale
Agreements. It is assumed that with the commissioning of various interconnectors with neighbouring countries
the export capacity shall increase to more than 50MW during the planning horizon. This is subject to UETCL
entering into Power Sales Agreements with the neighbouring countries refer to Annex-A.1: Demand-Supply
Balance prognosis.
The assumed increase in the load factor is due to growth in the base load due to increased industrialization.
2. Spinning Reserve –the additional output from generating plant that must be realisable in real time in
order to arrest a drop of system frequency due to a loss of generation or a loss of external inter-connector
or mismatch between generation and demand. The spinning reserve should be equal to the largest unit
on the grid.
2 Probability of getting 50%
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 23
3. Plant factor for large hydros is :
• Nalubaale & Kira – 0.38
• Bujagali – 0.6
5. Dispatch of Bujagali HPP will follow the discharge from Kiira and Nalubaale thus limiting its capacity to
1.237 times the combined dispatch of Nalubaale and Kiira and is estimated as below;
• Peak: 235 -250MW
• Shoulder : 185 - 217MW
• Off peak: 100 -169MW -The exact dispatch will depend on the coincident maximum demand
requirements for the different periods.
6. Mini hydros have been dispatched with a plant factor between 40% and 80%. All the mini-hydro Power
Plants are dispatched as base plants. The following plant factors have been observed and are assumed to
hold for the future:-
• Mobuku 1(KML) 0.52
• TPL(Bugoye) 0.77
• EMS (Mpanga) 0.52
• EPUL (Ishasha) 0.4
• Hydromaxx (Buseruka) 0.48
• Mobuku 3(KCCL) 0.78
• Muvumbe (0.55)
• Siti 1 (0.57)
• Rwimi (0.56)
8. Cogeneration Plants
• 51MW Kakira dispatching up to 32MW
• 14.5MW Kinyara dispatching 2-5MW
• 11.9MW SAIL dispatching up to 6.9MW
24 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
4.3 GENERATION EXPANSION PLAN
The objective of generation expansion planning is to determine the generation capacity and energy requirements
to meet forecasted demand during the planning period.
2 Mahoma HPP 2.7 2018 Embedded generation: (connecting to the 33kV grid)
3 Nkusi HPP 9 2018 Embedded generation: (connecting to the 33kV grid)
4 Sindila HPP 5.25 2018 Embedded generation: (connecting to the 33kV grid)
5 Mayuge Solar plant 10 2018 Embedded generation: (connecting to the 33kV grid)
Embedded generation, To be evacuated at Nkenda
6 Nyamwamba HPP 9.2 2018 Substation: new 2x60MVA, 33/132kV additional
transformers are proposed at Nkenda Substation
7 Agago-Achwa HPP II (ARPE) 42 2018 132kV - Gulu Agago double Circuit transmission line Project
Karuma Interconnection Project:
248.2km, 400kV, 1423MVA Double Circuit Karuma Kawanda
Transmission line, 2x650MVA, 400/220kV Kawanda
Substation
8 Karuma HPP 600 2018 54.25km, 400kV 1423MVA Double Circuit Karuma Olwiyo
Transmission line, 2x125MVA, 400/132/33kV Olwiyo
Substation
75.5km, 132kV, 135MVA Karuma Lira Double Circuit
Transmission line
80km, 132kV Mbale Bulambuli transmission line, 132/33kV
9 Siti 2 HPP 16.5 2018 2X32/40MVA Mbale substation, 132/33kV, 2X32/40MVA
Bulambuli substation
10 Mayuge Sugar plant 23 2020 Embedded generation: (connecting to the 33kV grid)
11 Waki Hydro HPP 4.8 2019 Embedded generation: (connecting to the 33kV grid)
12 Kakaka HPP 5 2019 Embedded generation: (connecting to the 33kV grid)
Embedded generation and operating off grid but shall
13 Nyagak III HPP 5.5 2019 eventually be evacuated via 132kV Lira Gulu Nebbi Arua
Project
14 Kyambura HPP 7.6 2019 Embedded generation: (connecting to the 33kV grid)
To be evacuated at Nkenda Substation: new 2x60MVA,
15 Nyamagasani 1 HPP 15 2019 33/132kV additional transformers are proposed at Nkenda
Substation)
To be evacuated at Nkenda Substation: A new 2x60MVA,
16 Nyamagasani 2 HPP 5 2019 33/132kV Substation is proposed adjacent to Nkenda
Substation
17 Ndugutu HPP 5.1 2019 Embedded generation: (connecting to the 33kV grid)
18 Kanyampara 4.8 2019 Embedded generation: (connecting to the 33kV grid)
19 Nyamabuye 7 2019 Embedded generation: (connecting to the 33kV grid)
20 Nyabuhuka-Mujunju HPP 3.2 2019 Embedded generation: (connecting to the 33kV grid)
21 SCOUL 25 2020 Embedded generation: (connecting to the 33kV grid)
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 25
Estimate
Capacity
No. Power Plant Commission Evacuation Line Project Name
(MW)
Year
22 Xsabo Solar 20 2019 132kV Kabulasoke Substation
23 Nengo Bridge HPP 6.7 2020 Embedded generation: (connecting to the 33kV grid)
24 Bukinda HPP 6.5 2020 Embedded generation: (connecting to the 33kV grid)
25 Kikagati HPP Project 14 (7) 2020 Embedded generation: (connecting to the 33kV grid)
26 Senok Wind Project 20 2020 Embedded generation: (connecting to the 33kV grid)
27 Agago-Achwa HPP I (ARPE) 42 2020 132/33kV Agago Substation
28 Keere Small HPP 6.3 2021 Embedded generation: (connecting to the 33kV grid)
29 Kinyara Cogen plant 35 2021 45km, 220kV double circuit Hoima Kinyara transmission line
30 Albatros Thermal Power 50 2021 220kV Hoima Nkenda Project
31 Sironko HPP 7 2021 Embedded generation: (connecting to the 33kV grid)
32 Gas to Power 58 2021 220kV Hoima Nkenda Project
33 Kabeywa HPP 12 2021 Embedded generation: (connecting to the 33kV grid)
38km, 132 kV double circuit Mirama-Nsongezi Transmission
line, Mirama 220/132kV Substation extension
34 Nshongezi HPP Project 35 (17.5) 2021
Nshongezi 33/132kV Substation: 2x32/40MVA power
transformer 2 x line feeder bay for 33kV lines from Kikagati
35 Ngoromwo HPP 8 2021 Embedded generation: (connecting to the 33kV grid)
36 Maziba 1 2021 Embedded generation: (connecting to the 33kV grid)
37 Nyagak 1 3.5 2021 Embedded generation: (connecting to the 33kV grid)
38 Cresta 5 2021 Embedded generation: (connecting to the 33kV grid)
39 Muyembe-Sirimityo HPP 7 2021 Embedded generation: (connecting to the 33kV grid)
40 Jinke solar 500 2021 Unknown
41 CP- EM solar 1000 2021 Unknown
42 Sky power Solar 500 2021 Unknown
43 Bukwa HPP 9 2021 Embedded generation: (connecting to the 33kV grid)
44 Ngoromwo HPP 8 2021 Embedded generation: (connecting to the 33kV grid)
To be interconnected and evacuated via 132 (220kV)
45 Muzizi HPP 44.7 2022 double circuit Nkenda Fort Portal Hoima transmission line
(Evacuation line is 6km)
Agago-Achwa HPP III
46 13 2022 132/33kV Agago Substation
(ARPE)
Agago-Achwa HPP IV
47 10.5 2022 132/33kV Agago Substation
(ARPE)
48 Kigwabya 4.2 2022 Embedded generation: (connecting to the 33kV grid)
80km 132kV Mbale Bulambuli transmission line, 132/33kV
49 Sisi 7.1 2022 2X32/40MVA Mbale substation, 132/33kV, 2X32/40MVA
Bulambuli substation
80km 132kV Mbale Bulambuli transmission line, 132/33kV
50 Simu 9.9 2022 2X32/40MVA Mbale substation, 132/33kV, 2X32/40MVA
Bulambuli substation
51 Lwakhaka 6 2024 Embedded generation: (connecting to the 33kV grid)
52 Agbinika 2 2024 Embedded generation: (connecting to the 33kV grid)
53 Okulacere 6.5 2024 Embedded generation: (connecting to the 33kV grid)
26 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Estimate
Capacity
No. Power Plant Commission Evacuation Line Project Name
(MW)
Year
54 Oriang HPP 392 2025 To be evacuated at Olwiyo Substation
12.57km, 400kV underground cable double circuit Ayago
55 Ayago HPP 840 2025
Olwiyo transmission line
12km, 400kV underground cable double circuit to Ayago
56 Kiba 330 2025
switchyard
Embedded generation, 132kV Mirama Kabale Double Circuit
57 Kabale Peat 30 2027
Transmission Line Project
40km, 400kV underground cables double circuit to Ayago
58 Uhuru 600 2035
switchyard.
Total 5,614.05
TABLE 12: Generation expansion plan
The graph below shows the load duration curve for December 2017. It illustrates the relationship between
generating capacity requirements and capacity utilization.
The maximum system peak demand registered in 2017 was about 562.45MW and 534MW in 2016. The peak
demand period is experienced for about 15% of the time. There is need to improve Demand Side Management
measures to reduce the peak demand to avoid investment in expensive peak generation facilities.
The future outlook of the Demand –Supply is presented in Annex A.1.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 27
FIGURE 4: Load duration curve Dec’17
The Load Duration curve shows that the base load of the Ugandan grid is about 250MW and the maximum power
peak load of the Ugandan grid is about 590 MW that is observed to occur for approximately a period of less than
5% of the time. Therefore since UETCL is the system operator should ensure that the generators are well scheduled
to serve the different load requirements.
In order to meet the power and energy requirements, the generation plants in Table 14 are utilized.
CATEGORY/SUPPLIER INSTALLED CAPACITY (MW)
LARGE HYDROS
ESKOM UGANDA LIMITED 380MW
BUJAGALI 250MW
MINI HYDROS
MPANGA 18MW
BUGOYE 13MW
KILEMBE MINES 5MW
KASESE COBALT 10.5MW
ISHASHA 6.4MW
BUSERUKA 9MW
RWIMI 5.54MW
MUVUMBE 6.5MW
SITI 1 5MW
LUBILIA 5.4MW
NYAMWAMBA 9.2MW
NKUSI 9.6MW
CO-GENERATION
KAKIRA SUGAR WORKS 51MW
28 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
CATEGORY/SUPPLIER INSTALLED CAPACITY (MW)
KINYARA SUGAR WORKS 14.5MW
SAIL SUGAR WORKS 11.9MW
THERMAL
JACOBSEN UGANDA LIMITED (NAMANVE HFO) 50MW
ELECTROMAXX (TORORO HFO) 50MW
SOLAR
ACCESS UGANDA SOLAR (OPUYO) 10MW
TORORO SOLAR NORTH LIMITED 10MW
AVAILABLE TOTAL GENERATION 930.54
Table 13: Existing generation plants
Source: Executed Power Purchase Agreements
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 29
Domestic Demand Export Demand Industrial Loads Total Demand
Year
(MW) (MW) (MW) (MW)
2037 1,265 164 1677 3106
2038 1,317 164 1761 3242
2039 1,370 164 1849 3383
2040 1,426 164 1941 3536
TABLE 14: Demand forecast (MW) 2018-2040
Source for Industrial loads : Umeme LTD
30 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
4.6 FORECASTED GENERATION MIX
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 31
FIGURE 8: Forecasted generation mix 2030
32 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Figure 11: Forecasted generation mix for planning period
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 33
Figure 13: Energy projection 2017-2040
Recommendations
• Demand growth opportunities need to be explored in order to realise demand that matches the
generation capacity development.
• Hydro power generation plant development should be matched with demand growth outlook..
34 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Power Excess/ Deficit Power Excess/ Deficit
Power Excess/ Deficit
Year (Domestic with proposed (Domestic with industrial
(Domestic) (MW)
industrial loads) (MW) loads + Export) (MW)
2029 2,806 1,834 1,670
2030 1,648 619 455
2031 2,805 1,717 1,553
2032 2,764 1,614 1,450
2033 3,063 1,847 1,683
2034 3,019 1,734 1,570
2035 3,324 1,967 1,803
2036 3,376 1,943 1,779
2037 3,527 2,014 1,850
2038 3,475 1,879 1,715
2039 3,422 1,737 1,573
2040 3,411 1,639 1,470
TABLE 17: Deficit/Excess supply 2018-2040
Note: Excess generation is envisaged throughout the planning horizon from 2020 to 2040, however in the event
that the industrial loads do not materialize as envisaged, the quantity of surplus power will significantly increase
and this will bear a financial burden on UETCL due to payment of deemed energy fees.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 35
5 POWER SYSTEM ANALYSIS
Output Results
The output results for power system modeling are:
a) Power flow result in terms of:
• Voltage profile to guard against insulation failure and maintain quality of supply
• Line and transformer loading
36 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
• Power flow and
• Losses
b) Fault calculation results in terms of:
• Fault levels to confirm switchgear safe breaking capability and protection settings
c) Contingency Analysis
d) Economic Dispatch/ Optimal power flow
e) Dynamic System Analysis:
• Power system stability to avoid black outs and maintain quality of supply
The technical analysis derived from power system studies formed a basis for determining technical viability and
timing of the projects. The results of the studies are presented below.
Key Events
• Queensway substation 132/33kV substation commissioned
• The following generation plants were commissioned;
Mini hydro power plants ; Siti I(5MW), Muvumbe (6.5MW), Rwimi (5.5MW).
Solar ; Tororo north solar (10MW).
Findings
• No buses violate the voltage limits of +/- 10%
• Violations of loading above 100% of MVA rating:
Kawanda 132/33kV– 100.4%
N-1 criterion is violated at the following:
• Substation ;Lugogo 132/33/11kV,Kawanda 132/33kV,Mutundwe 132/33/11kV,Lugazi
66/11kV ,Nkonge 132/33kV,Opuyo 132/33kV,Mbarara 132/33kV,Lira 132/33kV,Tororo
132/33kV,Kampala North 132/33/11kV,Kawaala 132/11kV,Masaka West 132/33kV,Owenfalls
33/66kV.
Transmission line ; Kabulasoke – Masaka west 132kV , Nalubaale - Namanve 132kV.
Mitigation Measures
• Expedite the upgrade of Opuyo, Kawanda, Kampala North and Tororo substations.
• Upgrade transformation capacities where N-1 criterion is violated.
• UMEME should consider 33kV interconnectors between the primary substations to allow for flexible
transfer of loads.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 37
5.2.3 2018 MODEL
Scenario without envisaged additional Industries
The demand and generation capacity modeled are:-
• Peak Demand : 637MW
• Required generation : 660.3MW
• Total losses : 23.35MW
• Trans. power losses : 19.86MW (3%)
• Transmission energy losses : 2.4%
Key Events
• Commissioning of large hydro:
Isimba -183MW and Agago/Achwa – 42MW
• Commissioning of the following mini-hydros;
Siti II (16.5MW), Sindila (5.5MW), Nkusi (9.6MW), Nyamwamba (9.2MW), Mahoma (2.7MW), and
Lubilia (5.4MW).
• The following projects commissioned:
Kawanda-Masaka 220kV, Nkenda-Fortportal-Hoima 220kV, Bujagali-Isimba 132kV, Mbarara-Mirama
220kV, Mbarara-Nkenda 132kV, Kawanda-Kapeeka 132kV and supply to phosphate Sukulu factory
(with 25MVAr Capacitor Bank) commissioned.
• Additional Industrial Load – 100MW
38 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
20MVA (54.1%).
Transmission line; Bujagali – Iganga – Tororo 132kV (77%), Bujagali – Isimba 132kV (55.7.5), Tororo-
Sukulu 132kV (90.8%).
Mitigation Measures
• Expedite the commissioning of 132kV Tororo – Opuyo – Lira Transmission line
• Install a 10MVar capacitor bank at Lugazi 66kV.
• Install a 25MVar capacitor bank at Sukulu 10.5kV.
• Expedite upgrade of Kapeeka substation
Key Events
• Large hydro commissioned :
Karuma is fully commissioned 600MW.
• Mini hydros commissioned:
Waki(4.8MW), Kakaka(5MW), Kyambura(7.6MW), Nyamagasani I & II(20MW), and Nyamabuye
(7MW),
• Solar plant commissioned ;
Xsabo Solar (20MW).
• The following projects commissioned:
Bujagali-Tororo-Lessos 220kV,132kV Opuyo – Moroto, Tororo-Lira 132kV Mutundwe-Entebbe 132kV,
Bujagali-Kawanda 220kV, Opuyo, Kawanda, Tororo, Lira and Kampala North substation upgrade,
Electrification of Industrial Parks (Namanve South,Luzira, Iganga and Mukono) and 54km, 132kV
Kawanda-Kasana
• Additional Industrial Load – 310MW
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 39
Findings with envisaged additional industries
• Voltage Violations were observed at -10%: Lugazi 66kV (0.7337pu), Lugazi 11kV (0.6239pu), Moroto 132kV
(0.8619pu), Nalubaale 66kV (0.8472pu)
• Loading violations are observed at:-
Substations: Mutundwe 132/11kV (110.5%), Lira 132/33kV (103.7%)
Transmission lines: Nalubaale – T-Bujagali (130.1%)
• Additional N-1 criterion violations are observed at
Substations: Moroto 132/33kV (84.2%), Kasana 132/33kV (69.2%)
Transmission Lines: 8km Nalubaale – Bujagali 132kV (130.1%), Kampala North – Lugogo 132kV
(59.1%), Nalubaale – T-Mukono 132kV (86.2%), Kawanda – Kasana 132kV (52.2%)
Mitigation Measures
• Expedite the upgrade of Nkenda Substation to higher transformation capacity of 2x60MVA
Key Events
• Mini hydros commissioned;
Nengo Bridge (6.7MW), Bukinda (6.5MW), Kikagati (16MW), Achwa III &IV (42MW),Nyagak I (3.5MW),
Nyagak III (5.5MW), Ndugutu (51MW).
• Wind generation commissioned;
Senok wind (10MW).
• Cogeneration Plants Commissioned
Mayuge Sugar (23MW)
• The following projects commissioned;
313km, 132kV Lira-Gulu-Nebbi-Arua132kV
83km Gulu – Agago 132kV
Nkenda Substation Upgrade
• Additional Industrial Load – 249MW
40 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Findings without additional industries
• Voltage Violations were observed at Moroto 132kV (0.8982pu)
• Loading violations are observed at
Substations; Mutundwe 132/11kV (112.7%)
Transmission Lines; 3km T-Bujagali – Nalubaale132kV (119.9%)
• Additional N-1 criterion violations are observed at
Transmission lines: Mukono-Namanve (52%), Lugogo- Nalubaale (50.5%)
Key Events
• Large hydros commissioned include Ayago (840MW), Oriang (392MW) and Kiba (330MW), Muzizi
(44.7MW),
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 41
• Mini-hydros commissioned
Kabeywa (12MW), Bukwa (9MW), Keere Small HPP (6.3MW),Ngoromwo HPP (8MW),
Maziba(1MW),Okulacere(6.5MW),Agbinika(2MW),Lwakhakha(6MW),Nyagak1(3.5MW),Crest
(5MW),Nshongezi (35MW), Muyembe-Sirimityo (7MW), Sironko (7MW).
Other generation plants commissioned include; Gas to power -Tilenga&Kingfisher (58MW), Kinyara
25MW
• The following transmission projects commissioned;
Hoima-Kinyara-Kafu 220kV, Kampala Metropolitan project, Mirama-Nsongezi132kV,Mutundwe-
Gaba-Luzira132kV,Bulambuli-Kapeterol 132kV,Nkenda-FortPortal-Lyanda-Kaabale-Hoima
220kV,Nkenda-Mpondwe220kV,Mirama-Kabale132kV,Masaka-Mwanza 220kV, Ayago
interconnection project, Oriang interconnection project Kiba interconnection project, Olwiyo-
Nimule-Juba 400kV, Masaka–Mbarara220kV, Ishaka132/33kV and associated transmission
lines ,Wobulenzi-Kapeka 220kV ,Kapeka-Kaweweta-Nakasongola 132kV, Lugazi 132/33kV and
associated transmission line, ,Evacuation of tilenga and kingfisher oil fields,
Upgrade Tororo, Mbarara South and Mirama 220/132kV substations, Upgrade of Moroto
Tororo, Mbarara North, Masaka West, Nkonge, Lira (kole), Mutundwe and Lugogo 132/33/11kV
substations
Supply to 5 Standard Gauge Railway traction stations(Iganga, Tororo, Nyenga, Buwoola and
Kampala East) at 132kV Eastern Route)
• Additional Industrial Load – 182MW
Mitigation measures
• All big customers should ensure local reactive power compensation. (Entebbe, Kawanda, Kasana)
42 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
5.2.7 2030 MODEL
Key Events
• The following projects commissioned:
Masaka-Mbarara 400kV, 130.5km
Supply to Sukulu at 220kV
Northern Corridor (Tororo-Wobulenzi-Masaka, Mbarara-Shango 400kV, 535.8km)
Tororo-Karuma 400kV, 345km
Supply to Standard Gauge Railway traction stations for the Western Route (15 Traction Stations
each at 2X4MVA) and Northern Routes (15 Traction Stations each at 2X4MVA) at 132kV
• Additional Industrial Load – 351MW
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 43
Mitigation measures
• Install an additional 200MVA transformer at Tororo 400/220kV substation
Key Events
• The following projects commissioned:
Ishaka-Kabale 132kV 94km
Kapeka-Kiboga 220kV 67.2km
Kiboga-Hoima 220kV 75.7km
Kabulasoke-Kiganda-Kiboga 132kV
• Additional Industrial Load – 329MW
44 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
• Additional N-1 criterion violation is observed at :-
Substations; Mubende 132/33kV 2x40MVA (54%), Rakai 132/33kV 2x40MVA (53.8%), Tororo
400/220kV 2x200MVA (101.5%)
Transmission Lines; Kole-Lira 132kV (75.2%), Masaka-Rakai 132kV (85.6%), Nkonge-Kabulasoke
132kV (113.4%), Nkonge-Kahungye 132kV (69.3%), Opuyo- Lira 132kV (61.2%), Nile HPPS –Ayago
400kV (57.3%)
Mitigation measures
• Upgrade Lira 132/33kV substation
• Re-conductor Nkenda-Kahungye-Nkonge-Kabulasoke 132kV transmission line
Key Events
• The following projects commissioned:
Bulambuli-Moroto 132kV 15km
Moroto-Kitgum 132kV 250km
kitgum-Agago 132kV 50km
Agago-Adjumani 132kV 86km
Adjumani-Arua 132kV 110km
Arua-Aru 132kV 5.4km
• Additional Industrial Load – 420MW
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 45
2018 2019 2020 2025 2030 2035 2040
Power losses
Without new industries 3 2.93 3.8 2.69 3.5 3.84 5.4
(%)
With industries 3.77 4.04 4.35 3.3 3.66 4.98
Load factor 0.74 0.74 0.74 0.75 0.76 0.77 0.79
Conversion Factor 0.82 0.82 0.82 0.83 0.83 0.84 0.85
Energy losses Without new industries 2.45 2.40 3.11 2.22 2.91 3.22 4.61
With industries 3.08 3.30 3.56 2.72 3.05 4.18
Table 18: Transmission loss trajectory
46 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
6 GRID INVESTMENT PLAN (2018-2040)
To ensure that the future electricity needs of the nation are satisfied, there is need to have major capital investments
in the power sector. Such investments comprise of generation plants, transmission lines and expansion of the
distribution network.
It is against this background that the Grid Investment Plan was developed to establish a rationale for building
a robust network, contribute to Government of Uganda’s strategic objective to provide adequate and reliable
energy supply to meet national and regional, socio-economic development.
The Grid Investment Plan Projects have been classified into the following categories:
• Power evacuation projects
• Grid re-investment projects
• System Expansion Projects
• Regional Projects
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 47
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
48
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
A POWER EVACUATION PROJECTS
Improvement of reliability
220kV Nkenda - FortPortal - Hoima Government of the
and quality of supply in the
(2X40MVA 132/33kV Hoima SS, 2X40MVA Royal Kingdom of
western region of Uganda.
3 132/33kV FortPortal SS; 54km 220kV Nkenda 299.03 81,807.85 2015 – 2018 Under Construction Norway and French
Provision of transmission
- FortPortal Transmission Line, 172km 220kV Development Agency
capacity to evacuate power
FortPortal - Hoima SS) (AFD) at EPC
from Kabaale 53MW Testcrude
Provision of transmission
China EXIM Bank at
4 132kV 42km Isimba Interconnection Project capacity to evacuate power 2,114.25 578,414.20 2015 – 2018 Under Construction
EPC
from Isimba HPP
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Provision of transmission
5 220kV Bujagali – Kawanda Line Bays capacity to evacuate power 11.63 3,182.81 2017 - 2019 Under Construction World Bank
from Bujagali Substation
48 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
183km, 132kV single circuit Agago - Lira Provision of transmission
Sourcing for Funding from
9 Transmission Line on wooden structures and capacity to evacuate power 79.42 21,728.42 2018 GOU
GOU for Implementation
related substations from Agago 42 MW HPP
Feasibility Study
Provision of transmission Complete
83km 132kV Gulu-Agago TL Project GOU at FS and kfW
10 capacity to evacuate power 144.14 39,432.65 2016 – 2020
(2X32/40MVA 132/33kV Agago SS) at EPC
from Agago 83MW HPP Procurement of EPC
Contractor stage
Government of the
Update of Tender
Royal Kingdom of
Documents.
45km 220kV Hoima-Kinyara (2X90/40MVA Provision of transmission Norway at FS
11 169.10 46,261.08 2016 – 2021
220/132/33kV Kinyara SS) capacity to evacuate power
Sourcing for Financing
EPC Funding to be
for EPC
determined
74km 132kV Mbale – Bulambuli - Kapterol Provision of transmission
12 Transmission Line; 2X 60/80MVA 132/33kV capacity to evacuate power 208.58 57,063.71 2017-2022 Feasibility Study Ongoing KFW at FS
Mbale SS, 2X45/60MVA 132/33kV Kapterol SS from IPPs in Bulambuli area
400kV Oriang Interconnection project (10km Provision of transmission Sourcing for Financing
14 400kV Oriang - Nile HPPs Switching Station capacity to evacuate power 206.11 56,388.45 2019 – 2023 for Feasibility Study and To be determined
Underground cable) from Oriang HPP Implementation
400kV Kiba Interconnection Project (10km Provision of transmission Sourcing for Financing
15 400kV Kiba - Nile HPPs Switching Station capacity to evacuate power 202.49 55,398.30 2021 – 2025 for Feasibility Study and To be determined
Underground cable) from Kiba HPP Implementation
400kV Uhuru Falls Interconnection Project Provision of transmission Sourcing for Financing
16 (145km 400kV Uhuru - Tilenga - Kabaale capacity to evacuate power 479.30 131,126.35 2025 - 2031 for Feasibility Study and To be determined
Transmission Line) from Uhuru Falls Implementation
50
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
B GRID RE-INVESTMENT PROJECTS
Substation Works
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Connection of 132kV grid Sourcing for Financing
Tororo 2x250MVA 220/132kV Interbus Under Consideration
7 to the 220kV grid at the 40.94 11201.53 2021 for Feasibility Study and
Transformers using EPC + F
substation Implementation
50 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
To be pitched to the
Improvement of reliability Sukulu Phosphate Developer of Sukulu
11 20MVAr Capacitor Banks at Sukulu 10.5kV Bus 2.56 700.00 2018
and power supply quality Developer for Phosphate Factory
implementation
Preparation of Tender
Documents by World World Bank for
Nkenda Substation 132/33kV Upgrade Bank. Tender Document
18 Increase Substation Capacity 43.83 11,992.20 2018 – 2020
(2X60MVA 132/33kV Transformers) Preparation. EPC - To
Sourcing of Financing for Be Determined
Implementation
52
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
Kampala Metropolitan Area Improvement
Project ((Transmission Lines; 25.4km 132kV
1 cct Mukono branch point (Northern trunk
line) – Kampala North Substation, 10.2km
2cct Kampala North Substation – Mutundwe
Substation, 5.3km 132kV 2 cct Kampala
North Substation – Lugogo Substation,
0.1km 132kV 2 cct Kawaala branch point –
Feasibility Study
Kawaala Substation, 0.3km 132kV 2 cct (New
Complete.
Mukono Substation – Mukono Substation),
4.2km 220kV 4 cct New Mukono branch Provision of adequate
EPC Loan approved.
20 point – New Mukono Substation, 0.4km capacity, improvement of 506.98 138,700.00 2015 - 2021 JICA at EPC
132km 2 cct New Mukono Substation – New reliability
Procurement of
Mukono branch point (Southern trunk line),
Supervision Consultant
0.8km 132kV 2 cct Buloba branch point
ongoing
– Buloba Substation, 0.9km 220kV 4 cct
Buloba branch point – Buloba Substation;
Substations (2X 125MVA 220/132kV Buloba
SS, 2X40MVA 132/33kV Buloba SS, 3X125MVA
220/132/33kV Mukono SS, 3X40MVA
132/33kV Kawaala SS, 1X20MVA 132/11kV
Kawaala SS, 1X250MVA 220/132/33kV
Bujagali SS, 1X20MVA 132/33kV Mobile SS))
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
2X50/60MVA 132/11kV Lugogo SS,
2X50/60MVA 132/33kV Masaka West SS; New Provision of adequate
Sourcing for Financing for Under Consideration
21 Substations: 3X50/60MVA 132/33kV Jinja SS, capacity, improvement of 449.77 123,047.32 2019 - 2022
Feasibility Study and EPC using EPC + F
2X40MVA 132/33kV Mubende SS, 2X40MVA reliability
132/33kV Ishaka SS & 2X40MVA 132/33kV
Rakai SS; Transmission Lines: 5km 132kV
Bujagali Tororo T-Off to Jinja SS, 30km 132kV
Nkonge - Mubende, 10km 132kV Mbarara -
Nkenda T-off to Ishaka & 10km 132kV Masaka
- Kyaka T-Off to Rakai)
52 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
Upgrade of Nkenda - Hoima to 220kV
(Nkenda 2X250MVA 220/132/33kV Provision of adequate
Sourcing for Financing for Under Consideration
23 Substation, 2X90MVA Fort Portal capacity, improvement of 431.70 118,103.75 2019 - 2021
Feasibility Study and EPC using EPC + F
220/132/33kV Substation, 2X250MVA Hoima reliability
220/132/33kV Substation)
Improvement of reliability
and quality of supply in the
160km 132kV Mbarara-Nkenda & 260km western region of Uganda
1 132kV Tororo - Opuyo - Lira TL Project & & Provision of transmission 114.93 31,442.21 2014 - 2018 Under Construction AfDB at EPC
2X32/40MVA 132/33kV Fortportal SS capacity to evacuate power
from other generation plants
in the West.
Improvement of reliability,
Queensway SS Project (2X32/40MVA
4 availability and quality of 23.14 6,330.26 2015 - 2017 In Defects Liability Period JICA at EPC
132/33kV SS)
power supply
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
53
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
54
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
90km 132kV Kabale - Ishaka Transmission Improvement in availability Sourcing for Financing for
8 194.09 53,099.05 2029 - 2033 To be determined
Line Project of power supply Feasibility Study and EPC
65km 132kV Kitgum - Agago Transmission Improvement in availability Sourcing for Financing for
9 189.97 51,972.77 2036 - 2040 To be determined
Line (2X15/20MVA 132/33kV Kitgum SS) of power supply Feasibility Study and EPC
220km 132kV Kitgum - Moroto Transmission Improvement in availability Sourcing for Financing for
10 419.71 114,823.25 2036 - 2040 To be determined
Line of power supply Feasibility Study and EPC
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
105km 132kV Adjumani - Arua Transmission Improvement in availability Sourcing for Financing for
12 207.04 56,642.13 2036 - 2040 To be determined
Line of power supply Feasibility Study and EPC
Improvement of availability,
85km 132kV Mirama - Kabale Transmission Procurement of EPC
13 reliability, and quality of 179.35 49,067.07 2016 - 2020 ISDB at EPC
Line (2X32/40MVA 132/33kV Kabale SS) Contractor On-going
power supply
54 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
132kV Mutundwe-Gaba-Luzira (32/40MVA
Improvement of availability,
132/33kV Gaba SS; 25km 132kV Mutundwe Sourcing for Financing for
15 reliability, and quality of 165.44 45,262.15 2020 - 2025 To be determined
- Gaba Transmission Line, 25km 132kV Gaba - Feasibility Study and EPC
power supply
Luzira Transmission Line)
Improvement of availability,
47km 220kV Kinyara-Kafu Transmission Line Sourcing for Financing Under Consideration
18 reliability, and quality of 154.04 42,142.54 2016 - 2021
(2x250/250MVA, 400/220/33kV Kafu SS ) for EPC using EPC + F
power supply
Improvement of availability,
50km 220kV Buloba - Gaba Transmission Line Sourcing for Financing for
20 reliability, and quality of 185.20 50,665.90 2023 - 2028 To be determined
(2X60MVA 220/132/33kV Gaba SS) Feasibility Study and EPC
power supply
Improvement of availability,
345km 400kV Karuma - Tororo Transmission Sourcing for Financing for
22 reliability, and quality of 635.08 173,745.12 2026 -2031 To be determined
Line (2X650MVA 400/220kV Tororo SS) Feasibility Study and EPC
power supply
56
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
Improvement of availability,
142.9km 220kV Kapeeka – Kiboga - Hoima Sourcing for Financing for
27 reliability, and quality of 267.46 73,172.06 2018 - 2021 To be determined
Transmission Line Feasibility Study and EPC
power supply
Improvement of availability,
Mbale Industrial and Business Park
reliability, and quality of Sourcing for Financing for Under Consideration
28 Substation (3X60/80MVA 132/33kV 76.43 20,909.21 2019 - 2020
power supply to several Feasibility Study and EPC using EPC + F
Transformers)
industrial parks in Mbale
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Standard Gauge Railway Transmission Line
Project (Substations: 2X10MVA 132/27.5kV
Tororo, Buwoola, Iganga, Nyenga and
Kampala East Traction Stations; Transmission
Lines: 11km 132kV 2cct from UETCL Tororo to
the SGR Tororo SS, 64km 132kV 2cct double
Improvement of availability,
pi-branch off from Bujagali – Tororo 132kV Sourcing for Financing for Under Consideration
29 reliability, and quality of 174.21 47,660.00 2019 - 2021
to the SGR Buwoola SS, 3.5km 132kV 2cct Feasibility Study and EPC using EPC + F
power supply
from UETCL Iganga Industrial Park SS to SGR
Iganga SS, 5km 132kV cct double pi-branch
off from Nalubaale – Lugogo 132kV to the
SGR Nyenga Traction SS & 3.7km 132kV 2cct
from UETCL Namanve south Industrial Park
SS to SGR Kampala East Traction SS)
56 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
UETCL GRID INVESTMENT PLAN (2018-2040) : IMPLEMENTATION SCHEDULE SUMMARY
COST(BILLION COST(X1000 IMPLEMENTATION
No. PROJECT OBJECTIVE CURRENT STATUS FINANCIER
UGX) USD) PERIOD
Improvement of availability,
reliability, and quality of
Olwiyo 400kV Line Bays 13.92 3,809.17 2022 - 2024 Sourcing for Financing To be determined
power supply
Improvement of availability,
SCADA and Communication upgrade and
1 reliability, and quality of 27.74 7,590.00 2017 – 2020 Under Implementation World Bank
Emergency Control Centre
power supply
58 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
By the end of the planning period and upon successful implementation of this plan, the grid shall have a total
additional length of about 13,029.43km, 55 additional substations and 17,229MVA additional transformation
capacity. Tables 19 and 20 below illustrate the incremental transmission line length, number of substations and
transformational capacity during the period.
Line Voltage (kV) Line Length 2017 (km) Line Length 2040 (km) Additional Grid (km)
66 35.20 35.20 0
132 1,406.99 6,688.99 5282.00
220 260.00 2,939.84 2679.84
400 0 3,365.40 3365.40
TOTAL 1,702.19 13,029.43 11,327.24
TABLE 20: Transmission line length growth
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 59
TABLE 24:5 YEAR PLAN GDP 2018 – 2040 INVESTMENT REQUIREMENT SUMMARY
Project Category Estimated Cost (x1000USD)
2018-2020 2021-2025 2026-2030 2031-2035 2036-2040
Power Evacuation Projects 1,243,748 172,031 169,874 16,651 0
Re-investment Projects 279,217 246,510 0 0 0
System Expansion Projects 818,711 270,224 313,160 166,199 375,928
Regional Interconnection Projects 73,156 129,347 531,494 0 36,542
Total Grid Re-investment Requirement 2,414,832 818,112 1,014,528 182,850 412,470
TABLE 25: 5 YEAR PLAN GDP 2018 – 2040 DONOR FUNDING AND COUNTERPART FUNDING
REQUIREMENTS INVESTMENT REQUIREMENT SUMMARY
Project
Estimated Cost (x1000USD)
Category
2018-2020 2021-2025 2026-2030 2031-2035 2036-2040
EPC RAP EPC RAP EPC RAP EPC RAP EPC RAP TOTAL
Power
Evacuation 1,137,737 106,012 156,206 15,825 153,121 16,752 16,651 0 0 0 1,602,303
Projects
Re-investment
258,012 21,205 243,644 2,867 0 0 0 0 0 0 525,727
Projects
System
Expansion 650,386 168,325 227,251 42,973 256,414 56,746 144,973 21,226 243,548 132,380 1,944,222
Projects
Regional
Interconnection 49,639 23,517 123,800 5,548 481,234 50,260 0 0 33,127 3,415 770,539
Projects
Total Grid
Re-investment 2,095,773 319,059 750,900 67,213 890,769 123,758 161,624 21,226 276,675 135,795 4,842,791
Requirement
60 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
6.3 REGIONAL INTERCONNECTION POWER LINES
Regional interconnection power lines are based on the recommendations from the interconnection studies carried
out by the regional bodies (NBI and EAC) including EAPMP, the Comprehensive Basin Wide Study undertaken by
the Nile Basin Initiative (NBI) and the Eastern Africa Power Pool Master Plan by EAPP.
Within the Nile Basin Initiative framework, the NELSAP has engaged in solidarity actions to promote poverty
reduction, economic growth and reverse the environmental degradation process in member countries. Regarding
the energy sector, the NBI focused on optimization and development of hydroelectric power generation and
interconnection among member states.
The Interconnections projects, involving Uganda under the NELSAP project are currently under construction with
expected commissioning year as 2018. These include:
• Uganda (Bujagali) – Kenya (Lessos) 220 kV line
• Uganda (Mbarara) – Rwanda (Birembo) 220 kV line
And studies have been concluded for the following interconnectors awaiting implementation :-
• Uganda (Masaka) – Tanzania (Mwanza) 220kV line
The update of the feasibility study is yet to commence under the financing of KFW. Procurement of the consultant
is ongoing and the process is being spreaheaded by TANESCO in Tanzania.
• Uganda (Nkenda_ - DRC (Beni/Bunia) 220kV line
No feasibility studies have been carried out on the proposed Uganda (Olwiyo)- Juba (Southern Sudan) 400kV
interconnector ; However the Government of Uganda and the Government of South Sudan entered into an MOU
on the development of the project and AfDB has expressed interest in funding the study.
• 400kV Northern Corridor
• Arua – Aru 132kV line
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 61
Project Rationale Current Status Financing Status
183km, 132kV single circuit Agago - Lira Provision of transmission
Sourcing for financing for Sourcing for financing
Transmission Line on wooden structures and capacity to evacuate power
Interim solution from GOU
related substations from Agago 42 MW HPP
Provision of transmission
Sourcing for Financing for
400kV Oriang Interconnection project capacity to evacuate power Sourcing for Financing
Feasibility Study
from Oriang HPP
Provision of transmission
Sourcing for Financing for
400kV Kiba Interconnection Project capacity to evacuate power Sourcing for Financing
Feasibility Study
from Kiba HPP
Mirama Substation Upgrade (2X50/63MVA, Enable power supply to the Under Consideration
Sourcing for Financing
132/33kV Transformers) distribution network using EPC + F
Tororo 2x250MVA 220/132kV Interbus Connection of 132kV grid to the Under Consideration
Sourcing for Financing
Transformers 220kV grid at the substation using EPC + F
2X250MVA 220/132kV Mbarara South Interbus Connection of 132kV grid to the Under Consideration
Sourcing for Financing
Transformers 220kV grid at the substation using EPC + F
Mbarara North Substation Upgrade (2x50/63MVA, Improvement of reliability and Under Consideration for
Sourcing for Financing
132/33kV Power Transformers) power supply quality Funding Using EPC+F
Tender Documents
Prepared
2km 132kV Mukono - Nalubaale Toff - Lugazi SS Provision of adequate capacity,
Procurement of To be determined
(2X32/40MVA 132/33kV Lugazi SS) improvement of reliability
Supervision of works
Consultant ongoing
62 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Project Rationale Current Status Financing Status
Substation Reinforcement Project (Upgrade
132/33kV Power Transformers), Upgrade of
Provision of adequate capacity, Under Consideration
Tororo Substation (2x125MVA, 132/33kV Power Sourcing for Financing
improvement of reliability using EPC+F
Transformers), Upgrade of Kole Substation
(2x32/40MVA, 132/33kV Power Transformers)
Improvement of availability,
47km 220kV Kinyara-Kafu Transmission Line Under Consideration
reliability, and quality of power Sourcing for Financing
(2x250/250MVA, 400/220/33kV Kafu SS ) using EPC+F
supply
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 63
6.5 INFORMATION AND COMMUNICATION TECHNOLOGY
UETCL’s objective is to build and maintain a smart national grid that maintains a flexible and reliable electricity
supply. This requires a changed approach to grid investment and a similar change in its telecommunications
investment.
UETCL currently implements the Optical Fibre with Ground Earth wire (OPGW) as part of every EPC contract for
construction of transmission lines and as such the communication infrastructure is expanding at the same pace
as the power transmission grid.
The current UETCL telecommunications network is in most cases up to date but there is need to make certain that
it shall continue to be future proof.
The demand for a reliable communication network that ensures optimum management of the power system and
its ability to meet other business requirements are increasing.
UETCL’s response to the challenges faced includes and shall continue to have the following initiatives:
• Communication infrastructure that enables improved monitoring and control of the power system as
well as increased access to detailed power system network information.
• The telecommunications network needs to support UETCL’s critical grid services comprising of tele-
protection, SCADA, telemetering and voice communication.
• The move towards an IP based environment is leading UETCL into paying more attention to communication
networks.
• Evolving real time requirements that shall impact on communication infrastructure development include:
o SCADA, which is changing to IP based solutions
o IT security, which requires a robust and reliable network
o New substation features, such as IP CCTV
In addition, new lines of business in telecommunication are being identified by the company. This shall ensure
better utilisation of present and future grid communication infrastructure.
Optical Fibre Leasing: This is a business area that has been identified by UETCL. All new transmission lines shall
have sufficient optical fibre installed to cater for other users who wish to lease the fibre. An aggressive marketing
campaign shall be used to attract more users. UETCL, however, has a challenge of avoiding service interruptions
resulting from vandalising the towers that support the fibre.
64 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
7|NDPII
SCENARIO
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 65
7.1 LOAD AND GENERATION PROGNOSIS
The current National Development Plan (NDP II) is the second out of the six - five-year NDPs that will be implemented
under Vision 2040 and covers the fiscal period 2015/16 to 2019/20. It builds on the achievements attained under
NDP I, mitigates the challenges encountered during its implementation, and seeks to take advantage of regional
and global development opportunities. Unlike its predecessor, NDP II will serve as the point of reference to
inform government planning processes, thereby eliminating parallel planning. The goal of this Plan is to propel
the country towards middle income status by 2020 through strengthening the country’s competitiveness for
sustainable wealth creation, employment and inclusive growth.
66 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
7.1.2 DEMAND AND GENERATION BALANCE
The charts below illustrate the growth outlook of demand and generation capacity.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 67
Plant Capacity (MW)
17 Kabaale & Refinery 53
18 Bujagali 250
19 Isimba 183
20 Karuma 600
21 Mini hydros 203
22 Solar Generation 20
23 Co-generation (Biomass) 100
24 Peat (Kabale) 33
25 Ayago 840
TOTAL (MW) 2500
TABLE 30:Existing and proposed enegy sources-NDPII case
7.2 OBSERVATIONS
In order to meet the NDP II targets, the requirement is to fast track the implementation of the grid investments
plan for the planning horizon 2018 –2026 within the next two years.
The table below shows the rationale for the deduction above
NDP II target- 2020 Base case -2026
Domestic Demand forecast 821 816
Generation forecast 2500 4022
Table 31: Comparison between the base case 2026 and NDP11 targets
68 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
11. 45km 220kV Hoima-Kinyara (2X90/40MVA 220/132/33kV Kinyara SS).
12. 74km 132kV Mbale – Bulambuli - Kapterol Transmission Line; 2X 60/80MVA 132/33kV Mbale SS,
2X45/60MVA 132/33kV Kapterol SS.
13. Extension of Transmission Grid to evacuate excess electricity generated from Tilenga and Kingfisher oil
fields.
14. 400kV Oriang Interconnection project (10km 400kV Oriang - Nile HPPs Switching Station Underground
cable)
15. 400kV Kiba Interconnection Project (10km 400kV Kiba - Nile HPPs Switching Station Underground cable)
Grid re-investment projects
1. Kabulasoke-Nkonge-Nkenda 132kV 216.5 km (Re-stringing)
2. Kabulasoke-Masaka West 132kV 60km (Re-stringing)
3. Reconductoring 3km of Bujagali - Nalubaale line with HTLS Conductor
4. Reconductoring 113km of Bujagali - Tororo line with HTLS Conductor.
5. 50MVA 33/33kV Bujagali Phase Shifting Transformers.
6. Mirama Substation Upgrade (2X50/63MVA, 132/33kV Transformers).
7. 2X250MVA 220/132kV Mbarara South Interbus Transformers.
8. Reallocation of 1X60MVA 220/132/33kV Transformer from Mbarara to Mirama Substation.
9. Refurbishment of transformer bay and shift of 20MVA Transformer to Lira Substation from Tororo.
10. 20MVAr Capacitor Banks at Sukulu 10.5kV Bus.
11. 10MVAr 11kV Capacitor Banks at Lugazi.
12. Tororo 80MVA, 132/33kV.
13. Mbarara North Substation Upgrade (2x50/63MVA, 132/33kV Power Transformers).
14. Kampala North substation upgrade (1X32/40MVA 132/33kV Transformer).
15. Kawanda substation upgrade (1X32/40MVA 132/33kV Transformer).
16. Opuyo Substation 132/33kV Upgrade (2X32/40MVA 132/33kV Transformers).
17. Nkenda Substation 132/33kV Upgrade (2X60MVA 132/33kV Transformers).
18. 2km 132kV Mukono - Nalubaale Toff - Lugazi SS (2X32/40MVA 132/33kV Lugazi SS).
19. Kampala Metropolitan Area Improvement Project.
20. Power Transformers Project 1 (Reinforced Substations: 2X32/40MVA 132/33kV Nkonge SS, 2X50/60MVA
132/33kV Mutundwe SS, 2X50/60MVA 132/11kV Mutundwe SS, 2X50/60MVA 132/33kV Lugogo SS,
2X50/60MVA 132/11kV Lugogo SS, 2X50/60MVA 132/33kV Masaka West SS; New Substations: 3X50/60MVA
132/33kV Jinja SS, 2X40MVA 132/33kV Mubende SS, 2X40MVA 132/33kV Ishaka SS & 2X40MVA 132/33kV
Rakai SS; Transmission Lines: 5km 132kV Bujagali Tororo T-Off to Jinja SS, 30km 132kV Nkonge - Mubende,
10km 132kV Mbarara - Nkenda T-off to Ishaka & 10km 132kV Masaka - Kyaka T-Off to Rakai).
21. Substation Reinforcement Project (Upgrade 132/33kV Power Transformers), Upgrade of Tororo Substation
(2x125MVA, 132/33kV Power Transformers), Upgrade of Kole Substation (2x32/40MVA, 132/33kV Power
Transformers).
22. Upgrade of Nkenda - Hoima to 220kV (Nkenda 2X250MVA 220/132/33kV Substation, 2X90MVA Fort Portal
220/132/33kV Substation, 2X250MVA Hoima 220/132/33kV Substation).
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 69
3. 23.5km 132kV Mutundwe-Entebbe Transmission Line Project: Substation; 2X60/80MVA 132/33kV Entebbe
SS.
4. Industrial Parks SS Project:
5. 160km 132kV Opuyo-Moroto Transmission Line Project (2X32/40MVA 132/33kV Moroto SS).
6. 85km 132kV Mirama - Kabale Transmission Line (2X32/40MVA 132/33kV Kabale SS).
7. 130.5km 400kV Masaka - Mbarara Transmission Line.
8. 132kV Mutundwe-Gaba-Luzira (32/40MVA 132/33kV Gaba SS; 25km 132kV Mutundwe - Gaba Transmission
Line, 25km 132kV Gaba - Luzira Transmission Line.
9. 132kV 313km Lira-Gulu-Nebbi-Arua Project.
10. 47km 220kV Kinyara-Kafu Transmission Line (2x250/250MVA, 400/220/33kV Kafu SS ).
11. 54km 132kV Kawanda – Kasana.
12. 50km 220kV Buloba - Gaba Transmission Line (2X60MVA 220/132/33kV Gaba SS).
13. 303km 220kV Nkenda - Buloba Transmission Line.
14. Sukulu Phosphate Transmission Line Project 2X50/63MVA 132/10.5Kv Power Transformers – Phase 1;
2x125MVA, 220/10.5kV Power Transformers – Phase 2).
15. T-Matugga - Kapeeka (Substations: 1X20MVA 132/33kV Kapeeka; Transmission Lines: 45km 132kV
T-Matugga - Kasana).
16. Nakasongola - Kaweweeta - Kapeeka (2X32/40MVA 132/33kV Nakasongola SS; 2X32/40MVA 132/33kV
Kaweweeta SS 160km, 132kV double circuit Nakasongola, Kaweweta Kapeeka transmission line ).
17. 37km 220kV Wobulenzi - Kapeeka Transmission Line (2x250/250/50MVA 400/220/33kV Wobulenzi
Substation, 2x125MVA 220/132/33kV Kapeeka Substation, 3X50/63MVA 132/33kV Kapeeka SS).
18. 142.9km 200kV Kapeeka – Kiboga - Hoima Transmission Line.
19. Mbale Industrial and Business Park Substation (3X60/80MVA 132/33kV Transformers).
20. Standard Gauge Railway Transmission Line Project.
21. SCADA and Communication upgrade and Emergency Control Centre.
70 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
8|VISION 2040
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 71
8.1 LOAD AND GENERATION PROGNOSIS
8.1.1 ASSUMPTIONS FOR DEMAND SUPPLY PROGNOSIS
• expected to increase from the current 35 million to 60.4
Uganda’s Population
million by 2040
Average Energy Consumption per capita • 3,668kWh/person/ year by 2040
Access to National Grid • 80%
Installed Generation Capacity • 41,738MW by 2040
TABLE 33: Assumptions for demand supply prognosis-vision 2040
SOURCE: NPA –VISION 2040
72 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
8.1.4 DEMAND FORECAST VISION 2040
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 73
8.2 RECOMMENDATIONS
From the above studies and analysis, the following recommendations are made for consideration.
• The Ugandan 2040 Vision case methodology differs from the other cases in order to be able to match the
targeted per capita consumption levels of the reference document. These targets yield very ambitious
demand levels and would require a complete transformation of the sector and massive levels of
investment in the next 23 years up to 2040.
• The forecasts presented in the above table requires substantial amounts of investments in the power
system infrastructure i.e. generation plants, transmission line network and distribution network in order to
be realized. Nuclear power plants, given their base load generation profiles, will play a key role in the future
investment portfolio allowing for the supply of reliable base load energy that can be complemented with
other technologies in order to adapt to the future load profile of the country. These investments will be
enormous for the Ugandan 2040 Vision case and will require a complete transformation of the Ugandan
electricity system.
• Review other Government Policies e.g. Energy policy, transport, housing, agriculture, industry etc. to align
them with the 2040 vision.
• The Ministry of Energy and Mineral Development should give policy guidance to ensure harmonized
planning within the energy sector (generation, transmission, distribution and rural electrification.
The demand supply balance prognosis comparing all the three scenarios is shown in the figures below.
FIGURE 20: Demand supply power balance prognosis for all three scenarios
FIGURE 21: Demand supply energy balance for all three scenarios
74 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
9 RISK ANALYSIS
Below are the general risks identified, relating to the implementation of the GDevP and the proposed mitigation
measures. Mitigation measures will further be discussed in the feasibility studies of the individual projects.
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 75
RISK ASSESSMENT MITIGATION MEASURES
76 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
10 STAKEHOLDERS
Due to the nature of the projects and the environment in which UETCL operates, identification of key
stakeholders is a prerequisite for the successful implementation of this Grid Development Plan.
Further still, the key stake holders need to create an environment conducive for the survival of UETCL as a self-
sustaining organization without collapsing under the debt burden.
Below are some of the stakeholders and their roles.
STAKEHOLDER ROLE
Independent Power Producers • Generate and sell power under Power Purchase Agreements
• Project identification
Funding agencies • Project appraisal
• Approval of financing
• Project supervision
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 77
78 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
APPENDICES
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 79
80 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
A.1 DEMAND - SUPPLY
BALANCE AND PROGNOSIS
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 81
82 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
A.2 GIP IMPLEMENTATION
PLAN AND SCHEDULE
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 91
A.3 UETCL TRANSMISSION
LINES
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 107
Period: 1954 - 2017
Route Circuit Line
Nominal No. of No. of In service Line Rating
Line Length Length Type Age
Voltage (kV) circuits structures date (MVA)
(km) (km) (yrs)
Kampala North - Namungoona 132 5.6 2 11.2 20 Steel tower 1959 59 79.1
Namungoona - Mutundwe 132 5.4 2 10.8 16 Steel tower 1959 59 79.1
Lugogo - Kampala North 132 5.7 2 11.4 25 Steel tower 1997 21 73.2
Lugogo - Mutundwe 132 10.2 2 20.4 46 Steel tower 1997 21 180
Mutundwe - Kabulasoke 132 84.7 1 84.7 476 wooden 1963 55 63.1
Kabulasoke - Masaka West 132 60 1 60 338 wooden 1963 55 63.1
Masaka West - Kyaka 132 84.5 1 84.5 262 Steel tower 1994 24 73.8
Masaka West - Mbarara North 132 130.5 1 130.5 407 tower 1995 23 151.6
Kabulasoke - Nkonge 132 78.5 1 78.5 422 wooden 1963 55 63.1
Nkonge - Rugonjo 132 62.113 1 62.113 529 wooden 1963 55 63.1
Rugonjo - Nkenda 132 40.978 1 40.978 229 wooden 1963 55 63.1
Nalubaale – Namanve 132 56.3 1 56.3 169 Steel tower 1954 64 147
Namanve - Kampala North 132 12.6 1 12.6 37 Steel tower 1954 64 147
Nalubaale - Lugazi 66 35.2 1 35.2 104 Steel tower 1963 55 10.6
Nalubaale- Lugogo 132 70.2 2 140.4 243 Steel tower 1998 20 180.6
Bujagali – Tororo 132 118.8 2 237.6 207 Steel tower 1954 64 78
Tororo - Opuyo 132 119.5 1 119.5 775 wooden 1963 55 63.1
Opuyo – Lira 132 141.2 1 141.2 607 wooden 1963 55 63.1
Tororo - Kenya 132 27 2 54 28 Steel tower 1954 64 78
Bujagali - Nalubaale 132 8 2 16 35 Steel tower 2011 7 205.8
Bujagali - Kawanda 220 75 2 150 212 Steel tower 2012 7 205.8
Kawanda - Mutundwe 132 17 2 34 72 Steel tower 2012 7 457
Underground
Queensway – Lugogo Queens way t off 132 0.3 1 0.3 2017
cable
Nkenda – Fort Portal 220kV 55 2 110 Steel tower 2017
Total 1701.19
108 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
PLANNED TRANSMISSION LINES
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
109
Period: 2018 – 2040
(New Mukono Substation – Mukono Substation) 132 0.3 2 0.6 Steel tower 2020
Kampala North Substation – Mutundwe Substation 132 10.2 2 20.4 Steel tower 2020
Kawaala branch point – Kawaala Substation 132 0.1 2 0.2 Steel tower 2020
Buloba branch point – Buloba Substation 220 0.9 4 3.6 Steel tower 2020
Mirama – Kabale 132 85 2 170 Steel tower 2020
Masaka - Mbarara 400 130.5 2 261 Steel tower 2021
Tororo SS – SGR Tororo Traction SS 132 11 2 22 Steel tower 2021
Bujagali – Tororo T/L T-off to SGR Buwoola SS 132 64 2 128 Steel tower 2021
Iganga SS – SGR Iganga Traction SS 132 3.5 2 7 Steel tower 2021
Nalubaale – Lugogo T/L to SGR Nyenga SS 132 5 2 10 Steel tower 2021
Namanve South – SGR Kampala East SS 132 3.7 2 7.4 Steel tower 2021
Hoima - Kinyara 220 45 2 90 Steel tower 2021
Kinyara – Kafu 220 47 2 94 Steel tower 2021
Kingfisher – Kabale 132 50 2 100 Steel tower 2021
Tilenga - Kabale 132 135 2 270 Steel tower 2021
Wobulenzi – Kapeka 220 37 2 74 Steel tower 2022
110 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Period: 2018 – 2040
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
111
Period: 2018 – 2040
Mbarara 400/220 - Mbarara 220/132 220 2.16 2 4.32 Steel towers 2030
Tororo - Karuma 400 345 2 690 Steel tower 2031
Underground
Kiba interconnection project 400 10 2 20 2031
cable
Underground
Uhuru – Olwiyo 400 38 2 76 2031
cable
Kabale – Ishaka 132 90 2 180 Steel towers 2033
Kabulasoke – Kiboga 132 131 2 262 Steel towers 2035
Bulambuli – Moroto 132 130 2 260 Steel towers 2040
Kitgum – Agago 132 65 2 130 Steel towers 2040
Kitgum – Moroto 132 220 2 440 Steel towers 2040
Agago – Adjumani 132 110 2 220 Steel towers 2040
Adjumani – Arua 132 105 2 210 Steel towers 2040
Arua – Aru 132 15 2 30 Steel towers 2040
Total 11327.24
TOTAL CIRCUIT LENGTH BY 2040 13,029.43
112 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
A.4 SUBSTATION
TRANSFORMATION
CAPACITY
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 113
A.4 UETCL SUBSTATION TRANSFORMATION CAPACITY
Period: 1963-2017
IMPEDANCE CONNECTION
YEAR OF MIN MAX VOLTAGE NOMINAL NO. OF EARTHING
SUBSTATION TRANSFORMER MAKE/ TYPE VOLTAGE AT SYMBOL
MANUFACTURE MVA MVA RATIO TAP TAPS RESISTANCE
NOMINAL TAP (VECTOR GROUP)
CENTRAL REGION
NAMANVE
LUGOGO
MUTUNDWE
114 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Period: 1963-2017
IMPEDANCE CONNECTION
YEAR OF MIN MAX VOLTAGE NOMINAL NO. OF EARTHING
SUBSTATION TRANSFORMER MAKE/ TYPE VOLTAGE AT SYMBOL
MANUFACTURE MVA MVA RATIO TAP TAPS RESISTANCE
NOMINAL TAP (VECTOR GROUP)
KAWAALA
KAWANDA
QUEENSWAY
NKONGE
NKENDA
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
115
Period: 1963-2017
IMPEDANCE CONNECTION
YEAR OF MIN MAX VOLTAGE NOMINAL NO. OF EARTHING
SUBSTATION TRANSFORMER MAKE/ TYPE VOLTAGE AT SYMBOL
MANUFACTURE MVA MVA RATIO TAP TAPS RESISTANCE
NOMINAL TAP (VECTOR GROUP)
FORT PORTAL
Transformer 1 32 40 132/33kV
Transformer 2 32 40 132/33kV
EASTERN REGION
LUGAZI
TORORO
BUJAGALI
NORTHERN
REGION
OPUYO
LIRA
Hackbridge Hewittic-
Transformer 1 1974 15 20 132/33kV 9 9.82% 17 YNyn0d11
Easun
Transformer 2 ABB 2007 20 20 132/33kV 5 9.39% 17 YNyn0d11
TOTAL 1640.5
116 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
PLANNED SUBSTATIONS
Period: 2018-2040
EXPECTED MIN VOLTAGE
SUBSTATION TRANSFORMER MAX MVA
COMMISSIONING YEAR MVA RATIO
CENTRAL REGION
NAMANVE SOUTH
Transformer 1 2019 40 63 132/33kV
Transformer 2 2019 40 63 132/33kV
Transformer 3 2019 40 63 132/33kV
LUZIRA
Transformer 1 2019 32 40 132/33kV
Transformer 2 2019 32 40 132/33kV
Transformer 3 2019 32 40 132/33kV
MUKONO
Transformer 1 2019 40 63 132/33kV
Transformer 2 2019 40 63 132/33kV
Transformer 3 2019 40 63 132/33kV
MUTUNDWE
Transformer 1 2022 50 60 132/33kV
Transformer 2 2022 50 60 132/33kV
Transformer 3 2022 50 60 132/11kV
Transformer 4 2022 50 60 132/11kV
ENTEBBE
Transformer 1 2019 60 80 132/33kV
Transformer 2 2019 60 80 132/33kV
KASANA
Transformer 1 2019 15 20 132/33kV
KAPEEKA
Transformer 1 2018 15 20 132/33kV
Transformer 2 2022 50 63 132/33kV
Transformer 3 2022 50 63 132/33kV
Transformer 4 2022 50 63 132/33kV
Transformer 1 2022 125 125 220/33kV
Transformer 2 2022 125 125 220/33kV
KAWANDA
Transformer 1 2018 20 20 132/33kV
Transformer 2 2018 250 250 220/132kV
Transformer 3 2018 250 250 220/132kV
Transformer 4 2018 650 650 400/220kV
Transformer 5 2018 650 650 400/220kV
Transformer 6 2019 32 40 132/33kV
WOBULENZI
Transformer 1 2021 250 250 400/220/33kV
Transformer 2 2021 250 250 400/220/33kV
NAKASONGOLA
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 117
Period: 2018-2040
EXPECTED MIN VOLTAGE
SUBSTATION TRANSFORMER MAX MVA
COMMISSIONING YEAR MVA RATIO
LUGOGO
Transformer 1 2022 50 60 132/33kV
Transformer 2 2022 50 60 132/33kV
Transformer 4 2022 50 60 132/11kV
Transformer 5 2022 50 60 132/11kV
KAMPALA NORTH
Transformer 1 2019 32 40 132/33kV
NEW MUKONO
Transformer 1 2021 125 125 220/132kV
Transformer 2 2021 125 125 220/132kV
Transformer 3 2021 125 125 220/132kV
BULOBA
Transformer 1 2021 125 125 220/132kV
Transformer 2 2021 125 125 220/132kV
Transformer 3 2021 32 40 132/33kV
Transformer 4 2021 32 40 132/33kV
KAWAALA UPGRADE
Transformer 6 2021 20 20 132/11kV
Transformer 1 2021 32 40 132/33kV
Transformer 2 2021 32 40 132/33kV
Transformer 3 2021 32 40 132/33kV
MOBILE SUBSTATION
Transformer 1 2018 50 50 132/33kV
Transformer 2 2021 20 20 132/33kV
NYENGA TRACTION
SS
Transformer 1 2021 10 10 132/27.5kV
Transformer 2 2021 10 10 132/27.5kV
GABA
Transformer 1 2025 32 40 132/33kV
Transformer 2 2026 60 60 220/132/33kV
Transformer 3 2026 60 60 220/132/33kV
KABULASOKE
Transformer 1 2035 15 20 132/33kV
Transformer 2 2035 15 20 132/33kV
KAMPALA EAST
TRACTION SS
Transformer 1 2021 10 10 132/27.5kV
Transformer 2 2021 10 10 132/27.5kV
KAWEWETA
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
WESTERN REGION
MASAKA WEST
Transformer 3 2018 125 125 220/132kV
Transformer 4 2018 125 125 220/132kV
118 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Period: 2018-2040
EXPECTED MIN VOLTAGE
SUBSTATION TRANSFORMER MAX MVA
COMMISSIONING YEAR MVA RATIO
Transformer 5 2022 50 60 132/33kV
Transformer 6 2022 50 60 132/33kV
NEW MASAKA
Transformer 1 2030 200 200 400/220kV
Transformer 2 2030 200 200 400/220kV
MBARARA SOUTH
UPGRADE
Transformer 1 2018 40 60 132/220kV
Transformer 1 2021 250 250 132/33kV
Transformer 2
2021 250 250 132/33kV
MBARARA NORTH
UPGRADE
Transformer 1 2022 50 63 132/33kV
Transformer 2 2022 50 63 132/33kV
MBARARA NEW
Transformer 1 2030 200 200 400/220kV
Transformer 2 2030 200 200 400/220kV
FORT PORTAL
Transformer 1 2021 40 90 33/132/220kV
Transformer 2 2021 40 90 33/132/220kV
MIRAMA
Transformer 1 2018 60 60 220/132kV
Transformer 2 2021 60 60 220/132kV
Transformer 2 2021 50 60 133/33kV
Transformer 3 2021 50 60 133/33kV
HOIMA
Transformer 1 2018 32 40 132/33kV
Transformer 2 2018 32 40 132/33kV
Transformer 3 2021 250 250 220/132/33kV
Transformer 4 2021 250 250 220/132/33kV
NKENDA
Transformer 1 2022 60 60 132/33kV
Transformer 2 2022 60 60 132/33kV
Transformer 3 2021 250 250 220/132/33kV
Transformer 4 2021 250 250 220/132/33kV
KABALE
Transformer 1 2020 32 40 132/33kV
Transformer 2 2020 32 40 132/33kV
NSONGEZI
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
KAFU
Transformer 1 2021 250 250 400/220/33kV
Transformer 2 2021 250 250 400/220/33kV
KABAALE
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 119
Period: 2018-2040
EXPECTED MIN VOLTAGE
SUBSTATION TRANSFORMER MAX MVA
COMMISSIONING YEAR MVA RATIO
Transformer 1 2021 250 250 220/132/33kV
Transformer 2 2021 250 250 220/132/33kV
KINGFISHER
Transformer 1 2021 32 40 132/33kV
Transformer 2 2021 32 40 132/33kV
TILENGA
Transformer 1 2021 32 40 132/33kV
Transformer 2 2021 32 40 132/33kV
Transformer 2021 32 40 132/33kV
MUZIZI
Transformer 2 2021 250 250 220/132/33kV
Transformer 3 2021 250 250 220/132/33kV
NKONGE
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
MUBENDE
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
RAKAI
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
ISHAKA
Transformer 1 2022 32 40 132/33kV
Transformer 2 2022 32 40 132/33kV
KIBOGA
Transformer 1 2035 15 20 132/33kV
Transformer 2 2035 15 20 132/33kV
KINYARA
Transformer 1 2021 40 90 132/220kV
Transformer 2 2021 40 90 132/220kV
EASTERN REGION
BUJAGALI
Transformer 3 2021 250 250 220/132kV
JINJA
Transformer 1 2022 50 60 132/33kV
Transformer 2 2022 50 60 132/33kV
Transformer 3 2022 50 60 132/33kV
TORORO
Transformer 3 2019 60 80 132/33kV
Transformer 1 2021 250 250 220/132kV
Transformer 2 2021 250 250 220/132kV
Transformer 4 2022 50 63 132/33kV
Transformer 5 2022 50 63 132/33kV
Transformer 6 2022 50 63 132/33kV
120 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Period: 2018-2040
EXPECTED MIN VOLTAGE
SUBSTATION TRANSFORMER MAX MVA
COMMISSIONING YEAR MVA RATIO
Transformer 1 2031 650 650 400/220kV
Transformer 2 2031 650 650 400/220kV
IGANGA
Transformer 1 2019 32 40 132/33kV
Transformer 2 2019 32 40 132/33kV
KAPTEROL
Transformer 1 2022 45 60 132/33kV
Transformer 2 2022 45 60 132/33kV
MBALE
Transformer 1 2022 60 80 132/33kV
Transformer 2 2022 60 80 132/33kV
Transformer 3 2020 60 80 132/33kV
BULAMBULI
Transformer 1 2040 60 80 132/33kV
Transformer 2 2040 60 80 132/33kV
TORORO TRACTION
SS
Transformer 1 2021 10 10 132/27.5kV
Transformer 2 2021 10 10 132/27.5kV
BUWOOLA
TRACTION SS
Transformer 1 2021 10 10 132/27.5kV
Transformer 2 2021 10 10 132/27.5kV
IGANGA TRACTION
SS
Transformer 1 2021 10 10 132/27.5kV
Transformer 2 2021 10 10 132/27.5kV
SUKULU PHOSPHATE
Transformer 1 2018 50 63 132/10.5kV
Transformer 2 2018 50 63 132/10.5kV
Transformer 1 2026 125 125 220/10.5kV
Transformer 2 2026 125 125 220/10.5kV
NEW LUGAZI
Transformer 3 2025 32 40 132/33kV
Transformer 4 2025 32 40 132/33kV
NORTHERN REGION
OPUYO SUBSTATION
UPGRADE
Transformer 2 2019 32 40 132/33kV
Transformer 3 2019 32 40 132/33kV
KARUMA
Transformer 1 2018 650 650 400/132kV
Transformer 2 2018 650 650 400/132kV
Transformer 3 2018 20 20 132/33kV
Transformer 4 2018 20 20 132/33kV
OLWIYO
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 121
Period: 2018-2040
EXPECTED MIN VOLTAGE
SUBSTATION TRANSFORMER MAX MVA
COMMISSIONING YEAR MVA RATIO
Transformer 1 2018 15 20 132/33kV
Transformer 2 2018 15 20 132/33kV
Transformer 3 2026 150 150 400/132kV
Transformer 4 2026 150 150 400/132kV
GULU
Transformer 1 2020 32 40 132/33kV
Transformer 2 2020 32 40 132/33kV
NEBBI
Transformer 1 2020 32 40 132/33kV
Transformer 2 2020 32 40 132/33kV
ARUA
Transformer 1 2020 32 40 132/33kV
Transformer 2 2020 32 40 132/33kV
AGAGO
Transformer 1 2020 32 40 132/33kV
Transformer 2 2020 32 40 132/33kV
MOROTO
Transformer 1 2019 32 40 132/33kV
Transformer 2 2019 32 40 132/33kV
KOLE
Transformer 1 2022 50 63 132/33kV
Transformer 2 2022 50 63 132/33kV
KITGUM
Transformer 1 2040 15 20 132/33kV
Transformer 2 2040 15 20 132/33kV
ADJUMANI
Transformer 1 2040 15 20 132/33kV
Transformer 2 2040 15 20 132/33kV
ARU
Transformer 1 2040 15 20 132/33kV
Transformer 1 2040 15 20 132/33kV
17,229
TOTAL MVA 18,869.50
122 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
A.5 MAPS
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 123
A.5.1 UGANDA POWER SYSTEM PRESENT AND FUTURE NETWORK
UGANDA POWER SYSTEM PRESENT AND FUTURE NETWORK
124 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
A.5.2 EAST AFRICAN POWER SYSTEM
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 125
A.5.3 NATIONAL DEVELOPMENT PLAN SCENARIO (NDP)
NATIONAL DEVELOPMENT PLAN SCENARIO (NDP)
126 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040
Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040 105
Plot 10 Hannington Road
P. O. Box 7625, Kampala-Uganda
Tel: +256 414 233 433/4,
+256 417 802 000, +256 314 802 000
Fax: 256-41-4341789
Email: [email protected]
106 Uganda Electricity Transmission Company Limited Grid Development Plan 2018– 2040