PSF_Questionnaire_EN
PSF_Questionnaire_EN
The objective of this questionnaire is to collect information on the main issues that can prevent compliance with process safety fundamentals, giving hints to the
management about how address the issues.
If any question does not apply to your job/duties, please mark it as N.A. (not applicable).
Use the Notes field to insert any considerations, especially if the answer is NO or there are actions that should be done but are not done.
Superintendent / Foreman
Supervisor
Operator/ Technician
Engineer
PSF 1 – Verify process line-up condition before start-up
Objective:
minimize spills of hazardous materials or involuntary mixing, which occur when the line is not ready for correct operation due to open disconnections, incorrect
alignments of valves or vessels/tanks, improperly tightened flanges
During your activities, can you always determine the correct __ Yes (specify how)
position of the valves or other equipment? __ No (specify location)
If not, specify the area/location.
Do you verify the line-up on P&IDs and the real line-up in __ Never
the plant location? __ When my supervisors asks me
__ Always before the job
__ Always before the job and when there is spare time
How do you inform your management about the changes in __ I do not report
the position of the valves/lines, which are not indicated on __ I tell my supervisor
the P&IDs? __ I mark up the P&ID and provide it to my supervisor
__ We have a procedure for reporting P&ID discrepancies
Do you check the condition of all drains and bleeders before __ All drain/bleeder valves are checked before start-up
equipment start-up? __ Only those involved in the maintenance work
__ Only those indicated in the start-up checklist
__ Only those requested by the supervisor/lead
Objective:
prevent releases from flanges or other types of seals of process equipment
To be verified on site:
correct execution of the tightening procedure (if the job is relevant)
execution of leak tests (e.g. visual inspection, preventive pressing) and analysis of the results
monitoring of the areas concerned, during the restart phase
PSF 2 - Verify connections tightness before returning to service
If carrying out tightening/tightness check is part of your job __ It is not part of my duties
duties, when did you receive last training on this topic? __ Never
__ At the beginning of the job
__ At each technical or procedural modification
__ Other (specify)
Is it always possible to verify (on field and DCS) that all __ Yes
instrumentation is properly connected before equipment __ No (specify)
start-up?
If not, specify when/where it is not possible.
Are operators always present on-site during the start-up of __ Always present
process equipment for monitoring and responding to any __ Not always present
deviations? __ Never present
PSF 3 – Report & take interim mitigating measures for impaired Safety & Environmental Critical Elements (SECE)
Objective:
bring attention to those parts of the plant whose failure could cause or contribute substantially to a major accident, or whose purpose is to prevent or limit the
effect of a major accident (safety and environment critical elements - SECE)
To be verified on site:
identify SECEs and visually verify their correct functioning
PSF 3 – Report & take interim mitigating measures for impaired Safety & Environmental Critical Elements (SECE)
Do you know which equipment is considered safety critical __ I don’t know what is a safety critical element
(SECE) at your work site? __ All equipment is safety critical
__ I know in general
__ I know exactly which equipment is safety critical in my work
area
What are your actions if you find a damaged SECE, e.g. __ I cannot do anything
while performing the maintenance activity in your area? __ I try to fix it myself
__ I report to my line manager
__ Other (specify)
Are there SECEs in your area that require shutdown in case __ I don’t know
of unavailability? __ No, there aren’t
__ Yes, there are and I know them (specify)
Objective:
prevent releases from single valves or process equipment because they are not completely segregated during the preliminary works to maintenance (e.g.
blinding, segregation, etc.)
How often is safe isolation (e.g. blinds) put in place before __ Always
maintenance works? __ Often
__ Sometimes
__ Rarely
__ Never
What do you do if, in your opinion, there is a more efficient __ I perform isolation as per the plan
method of isolation which is different from the isolation __ I stop the work and inform my supervisor
plan provided to you? __ I use more efficient method of isolation and later inform my
supervisor
__ I use more efficient method of isolation and don’t inform my
supervisor
PSF 5 – Operate override and bypass of safeguards only with authorization
Objective:
check for inhibition or bypass on the process equipment safeguard systems
Do you record and update every inhibit/override on a __ Usually I don’t record inhibits/overrides
dedicated register? __ I write it in my own note book
__ There is a dedicated log for recording all inhibits/overrides,
visualized in the control room
Objective:
prevent releases of hazardous fluids or damage to process equipment, resulting from exceeding operating limits
Do you know which are the safe operating limits for key __ No
process variables? __ Yes
__ Yes and they are visible to to the operators in the control
room
Which documents/procedure do you use for taking __ I don’t use documents or procedures
predetermined actions to bring the process variables back __ I have my own reference document, which I created
within the safe limits? __ I use the Operating Manual
__ I use other reference documents (specify)
Can you tell if the Operating Manual is updated and reflects __ The operating manual is regularly updated through the
the current situation of the plant? formal issue of a new revision
__ Any changes to the operating manual are made manually
on the master copy in the control room
__ The operating manual would need updating
When safe operating limits are exceeded, do you report the __ I record the event on a dedicated register and investigate
event and investigate the causes? the causes
__ I record the event but don’t looking for the causes
__ I don’t report the event nor investigate the causes
__ Other (specify)
PSF 7 – Monitor open draining operations
Objective:
prevent releases during the drainage phases from the equipment into open systems
How often do you carry out open transfers/ drainages which __ No activities like this
may involve hazardous fluids presence? __ Specify average number per month:
Do you participate in the risk assessment of activities which __ Always Is the evaluation activity tracked? Where can it be
involve open draining or venting into atmosphere? __ Often verified?
__ Sometimes
__ Rarely
__ Never
Can operators leave the draining/transfer location while __ They never leave the location while drainage is in progress
open draining is in progress? __ They leave the location as they have other duties at the
same time
__ They don’t know about the requirement
__ Other reason (specify)
Objective:
prevent releases during loading and unloading of hazardous fluids
How do you ensure that the actual quantity involved in the __ I don’t check
loading operation is in line with the capacity of the receiver? __ I personally verify the exact volume to transfer and the
free volume in the receiving tank/vessel
__ Other (specify)
How do you ensure that the overfill protection is properly __ I don’t check How do you check the accuracy of the instrumentation
working? __ Other (specify) data and possible malfunction of the overfill protection?
When you use a flexible hose for connection, how do you __ I don’t check
confirm that it was inspected and approved for use? __ There is a label on hose with the inspection date
__ I visually check its condition and the inspection label
__ Other (specify)
PSF 9 – Empty & de-energize process equipment before opening
Objective:
prevent uncontrolled releases of energy or hazardous fluids during the opening of pipes or equipment
How do you check the adequacy of isolations before breaking __ We install a pressure gauge on the line
the first flange joint? __ We break one of the flanged joints to check for residual
pressure
__ Other (specify)
Objective:
know and prevent containment losses from the process
To be verified on site:
report and record any detected or suspected loss
PSF 10 – Report & manage any loss of containment on site
If you detect leak, do you report it even if minor (“weeps & __ Always
seeps”) on INDACO as PSE Tier 3.1? __ Often
__ Sometimes
__ Rarely
__ Never
How many leaks from process equipment have you detected __ Specify the average number per year:
during last year, in your working area?