Patterson-Ch6-Extract-Project-Management
Patterson-Ch6-Extract-Project-Management
Topics Covered
Definitions
Attributes of a Security Project
Attributes of a Successful Security Project
Benefits of Project Management
Overview of Project Phases
Relationship between PPS Life Cycle Stages and Project Phases
Explanation of PPS Project Stages
Introduction
Project management has evolved to plan, coordinate, and control the complex
and diverse activities of security projects. Several forces are driving the
development of project management techniques:
The exponential expansion of human knowledge
The rapid evolution of new and very sophisticated technologies aimed at
improving detection of and response to security incidents
The growing demand for customized systems incorporating the latest
technology.
Highly competitive international markets for security products and
services. These three forces combine to mandate the use of project
teams to solve problems that used to be solved by individuals.
Definitions
Security Project
From the global construction industries’ perspective, a project is a temporary
endeavor undertaken to produce a product, accomplish a service, or create a
specific result. Projects normally involve several people performing activities as
a team; the main sponsor of the project is often interested in the efficient use of
resources to complete the project promptly at reasonable cost. A security
100
Implementing Physical Protection Systems –A Project Management Guide
project meets these criteria from the security manager’s perspective, but not
necessarily from the security system integrator’s perspective. Once the security
system installation is complete, the warranty is satisfied, and the system is
turned over to the owner for operation, the security systems integrator who
installed the system often remains with the system for the life of the system. So
the Closing and Operations Phases of the project have different activities for the
security manager and the security integrator and the word temporary needs to
be further explained.
Project Management
Project Management is the mixture of people, skills, tools, systems, and
techniques applied to project activities to meet or exceed stakeholders’ needs
and expectations. A successful project balances scope, time, quality, cost, and
other factors. Figure 6.1 depicts what needs to be considered. The project
manager’s role is to balance the three often competing goals of time, quality,
and cost. About project managers, it has often been said that “There are really
no good project managers - only lucky ones.” A project manager should have
the following key process oriented skills:
Well skilled organization
Self-disciplined
Follow-up skills
Capable of multi-tasking
Logical thought process
Competent problem solver with the analytical ability to determine root
causes
Expert estimator
Competent budget manager.
In addition to good process skills, a project manager must have team leadership
and management abilities including: General management skills needed to
establish processes and make sure that people follow them, set reasonable and
clear expectations of people, and holding them accountable for meeting the
expectations.
o Appropriate leadership skills to communicate a vision to the team and
induce them to follow directions. Good team-building skills so that the
people work together and feel motivated to work hard for the sake of
the project and their project team members.
o Proactive verbal and written communication skills including good
listening skills.
o Ability to give good quality performance feedback to team members.
Project managers work with the stakeholders - the people directly concerned
101
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
102
Implementing Physical Protection Systems –A Project Management Guide
Relationship between Project Life Cycle Phases and PPS Life Cycle Stages
The Security Industries Association’s (SIA) security project manager body of
knowledge identifies five process phases for a security project. They are:
1) Initiation
2) Planning
3) Execution
4) Project Closing
5) Operation
This chapter describes the life cycle of a Physical Protection System (PPS) and
how the PPS life cycle stages relate to the SIA’s project management phases.
Due to the complexity of many electronic security measures, security managers
must conduct lengthy, complex processes to implement them. The
implementation process can take six to 24 months or longer. Since the
implementation of a PPS is a unique endeavor involving many personnel
performing related activities, the term “project” is appropriate to describe the
implementation.
The PPS may also be an element of the construction of a new or upgraded office
building. In that case, the process can take up to twice as long. Therefore,
103
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
security professionals should start the process far enough in advance to avoid a
crisis with the existing, aging systems, such as escalating maintenance costs,
unreliable equipment, or hopelessly outdated software. The relationship of the
eight PPS implementation stages and the five phases of a security project are
shown in Figure 6.2 and the details within each stage are described below:
With this information, the project manager can develop a technology roadmap,
recommend new technologies, and make other recommendations based on the
risks, needs, and objectives of the client. After the risk and vulnerability
assessment, one of tools to use is a gap analysis comparing where the client is
with existing technology to where they want to be.
Critical in today’s environment is to analyze the IT capabilities of the client and
the sophistication of the proposed system and to ensure the client’s
infrastructure is capable of supporting the new system. Getting the customer’s
IT department involved and supportive of the project is essential to the success
of the project. They are tasked with keeping the business running smoothly and
adding anything new that resides on their network is of legitimate concern for
them. We need to determine if the IT service is in-house or out-sourced and
whether it is located at the main facility or a remote location.
During the initiation phase, we will need to review the proposed staffing
requirements and other resources necessary to meet the project requirements
and timelines. Later during the planning phase we can use the Work Breakdown
Structure (WBS) to build our timeline projections. We also need to develop a
preliminary budget estimate and review this budget with the customer for
approval. A flow chart of the major activities is shown in Figure 6.3
104
Implementing Physical Protection Systems –A Project Management Guide
Project Overview: Add the business benefit of the project. Share any
business goals and objectives that this project is trying to achieve.
Project Objectives: State the goals for the project. The project goals and
project deliverables should support the business goals and objectives.
Project Scope: Add information as to what the project will produce and
will not produce. In other words, what is out of scope? It is vital to be
clear about what things the project could produce, but will not. This will
make it much easier to deal with scope changes throughout the project.
Estimated Cost: Estimate the cost of labor, based on the staff hours. Add
any non-labor expense such as hardware, software, training and travel.
Estimated Duration: Estimate how long the project will take to complete,
once it starts. If the start date is known, then the end date can be
indicated here as well.
Significant Risks: For each identified risk, include a clear plan that shows
how you intend to ensure that the risk does not occur, or it is mitigated.
These risk management activities should also be included in the
document.
105
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
106
Implementing Physical Protection Systems –A Project Management Guide
Please see Figure 6.4 for a flowchart of the PPS Planning Stage.
107
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
During the Execution Phase, the Project Plan is executed and adapted as
necessary. Project Plan modifications may result from such things as the
following:
• New work to be done
• Changes in work scope
• Changes in functionality of the PPS
• Resource changes
• Other unexpected circumstances
In addition to keeping the Project Plan up to date, Project Execution Phase
activities include scrutinizing risks, reporting status, and authorizing project
changes as needed. Plans for these activities are developed during the Project
Planning Phase and the two PPS Implementation Stages – Planning Stage and
Design and Estimating Stage.
Again, because of their importance, rather than a single project Execution Stage,
we have separated the major activities we accomplish during this Project Phase
as follows:
108
Implementing Physical Protection Systems –A Project Management Guide
109
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
See Figure 6.8 for a flowchart of the PPS Commissioning and Warranty Stage.
110
Implementing Physical Protection Systems –A Project Management Guide
111
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
112
Implementing Physical Protection Systems –A Project Management Guide
Project Deliverables
Deliverables are the products that are produced by the work activities defined.
113
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
Identifying the deliverables for each phase of the PPS life-cycle is important. It is
crucial to differentiate between the PPS life cycle stages and the project phases.
Examples of some of the project deliverables for each PPS Stage are:
Initiation Stage
a. Risk and Vulnerability Study
b. Project Concept Document
c. Project Charter
d. Project Success Definitions
e. Project Description Statement
f. Project Feasibility Document
g. Other: Assumptions and Comments (Team frustration, obtaining
management commitment, customer indecision, scarcity of resources, lack
of coordinated leadership, no consensus on objectives, lack of management
sponsor)
Planning Stage
a. Objectives and Scope Definitions
b. Work Breakdown Structure
c. Organizational Breakdown Structure
d. Activity Definition and Sequencing
e. Cost Benefit Analysis
f. Resource Planning
g. Design Criteria
h. Performance Requirements
i. Capacity Requirements
j. Project Schedule
k. Budget Plan
l. Communications Plan
114
Implementing Physical Protection Systems –A Project Management Guide
Procurement Stage
a. Bidders Conference Minutes and Questions
b. Technical Evaluations
c. Cost Evaluations
d. Interview Results
e. Due Diligence Results
f. Contract
115
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
Installation Stage
a. Factory Test Plan
b. Acceptance Test Plan
c. Site Acceptance Test Plan
d. Reliability Test Plan
e. Factory Acceptance Test Results and Recommendations
f. Site Acceptance Tests Results and Recommendations
g. As Built Drawings
h. Product Data
i. Commissioning Plan
j. Quality Test Results and Recommendations
k. Punch Lists From Each Testing Activity
l. Commissioning Certificate of Completion
116
Implementing Physical Protection Systems –A Project Management Guide
Closing Stage
Action Plan to Resolve Any Existing Problems
Customer Sign Offs on All Pertinent Documents and Deliverables
A Post Implementation Review Report – Showing Objectives and Critical
Success Factors Achieved.
Lessons Learned Report Including Feedback from the Customer and Your
Team
Turnover to Operations - Preparation of organizational entities that will
continue technical support and operational support once the system is
commissioned. Information technology, maintenance personnel, and
security officers are the key support staff that must be prepared.
Collect and Archive All Project Data
Reassign Facilities and Equipment Used by the Project
Financial Closeout
Project Transition Checklist
Operations Stage
a. Training Syllabus
b. Training Manuals
c. Instructor Guides
d. Tests
e. Trouble Shooting Guides
f. Training Class Evaluations
g. Trouble Shooting Guides
h. Operating Procedures
i. Response Procedures
j. Maintenance Procedures
k. Maintenance Records
l. Trouble Reports
m. Upgrades
n. PPS Operating Procedures
o. Policies and Procedures for Monitoring, Assessing, Dispatching, and
Response
117
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
118
Implementing Physical Protection Systems –A Project Management Guide
119
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
Installation Stage
Operation Stage
a) Policies and Procedures
Phase 5 - Operation
b) Training
c) Maintenance
Figure 6.2 – Relationship between Project Life Cycle Phases and PPS
Implementation Life Cycle Stages
120
Implementing Physical Protection Systems –A Project Management Guide
Initiation Stage
Develop project
Select Project overview, objectives,
Manager scope
Form Implementation Estimate Cost and
Team Time Required,
Involve Stakeholders Identify Resources
Define Roles
121
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
Planning Stage
Identify Critical Success
Factors
122
Implementing Physical Protection Systems –A Project Management Guide
Prepare Specification
Prepare Bid
Package
123
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
124
Implementing Physical Protection Systems –A Project Management Guide
Procurement
Stage
Identify bidders
Conduct bidders
Respond to questions conference
Receive bids
Evaluate bids
Change
Orders
Conduct
negotiations
Award
Contract
125
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
Installation
Stage
Remove Legacy
Equipment Change
Prepare The Site Orders
Install Infrastructure
Install components
Complete
installation
Commissioning
&
Warranty
Stage
Establish Warranty
Conduct Factory
Team
Acceptance Test
Determine Type Of
Warranty
Conduct Site
Acceptance Tests Change
Orders
Prepare Warranty Plan
Complete Reliability
And Availability
Tests
Carry out
Maintenance System
Activities During Commissioned
Warranty Period
127
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
128
Implementing Physical Protection Systems –A Project Management Guide
Customer Sign Off & Reassign Personnel and Adminstrative and Financial
Post Implementation Review
Approvals Facilities Closeout
Report
Lessons Learned Report
129
Chapter 6 – How to Apply the Project Life Cycle Phases to the PPS Implementation Stages
Operations
Stage
Prepare Replacement
Documentation
And
Start New Project
130
Implementing Physical Protection Systems –A Project Management Guide
References
CSPM Security Project Manager Common Body of Knowledge Guidebook,
Security Industries Association, 2014
131