TIA-569 Overview_ Standards Standards Update Pathways & Spaces
TIA-569 Overview_ Standards Standards Update Pathways & Spaces
A standard established for rooms, pathways, and areas into and through which
structured cabling,
cabling components,
components and equipment are installed
installed. Applies to:
– Conduits
– Under‐floor ducts and Floor Boxes
– Access
A fl
floor (Raised
(R i d Floors)
Fl )
– Ceiling pathways (J‐Hooks & Rings)
– Cable tray systems
– Perimeter
P i t pathwaysth
• Raceways
– Telecommunications Closet & Equipment Room
• Sizes & Provisions
TIA‐569 Pathways & Spaces Standard
Building Spaces: General Requirements
– UPS larger
g than 100kVA located in separate
p room
• Distributor Enclosure
– Centrally located
– Lighting, measured in distributor enclosure, minimum 500 lux
– Minimum of one dedicated 120 VAC /20 A outlet
TIA‐569 Pathways & Spaces Standard
Access & Service Provider Spaces
– Consider q
quantity,
y, size & bend radius requirements
q of cable
when determining size of pathway
• Allow for growth
– Not
N t llocated
t d iin elevator
l t shafts
h ft
– Non‐continuous supports
pp located at intervals not to
exceed 1.5 m (5 ft)
TIA‐569 Pathways & Spaces Standard
Building Pathways
– Cable Trays
• Planned for initial max calculated fill ratio of 25%
Note A calculated fill ratio of 50% for 4
Note: 4‐pair
pair & similar
cable will physically fill entire tray due to spaces between
cables
– Cable Runway
• Stacked no higher than 150 mm (6 in)
– Conduit
Sections between pull points shall not exceed 30 m (100 ft)
in runs that total more than 30m (100
(100’)), insert pull boxes so that no
segment between pull points exceeds the 30m (100’) limit.
No section shall contain more than two 90 degree bends
Conduits with internal diameter of 50 mm (2 in) or less, inside
bend radius of a bend in conduit shall be at least 6 times the
internal diameter
Conduits with an internal diameter of more than 50 mm (2 in),
the inside radius of a bend in conduit shall be at least 10 times
the internal diameter.
Maximum fill
f ll ffor ffurniture pathways
h is 40%
TIA‐569 Pathways & Spaces Standard
Building Pathways
Splice boxes
Intended to be used for splicing in addition to pulling cable. A slip sleeve is a conduit sleeve
that is larger than the main conduit, and slipped over an opening in a conduit run after the
cable is in place. A gutter is a square, sheet-metal housing, which is placed over an
opening in a conduit. Slip sleeves or gutters cannot be used for splices, but can be used in
place of a pull box, are more economical to install, and will provide more space for pulling.
TIA‐569 Pathways & Spaces Standard
Other Pathway Types
• Slots
• Sleeves
• Trays
TIA‐569 Pathways & Spaces Standard
Backbone
Sleeves –
An opening, usually circular, through the wall, ceiling, or floor to allow the
passage of cables and wires.
Slots –
An opening through a wall,
wall floor,
floor or ceiling , usually rectangular
rectangular, to allow
the passage of cables and wires.
TIA‐569 Pathways & Spaces Standard
Firestopping
TIA‐569 Pathways & Spaces Standard
New Version!
29
TIA‐569 Pathways & Spaces Standard
30
TIA‐569
Pathways & Spaces Standard
32
TIA‐1179 Healthcare Facilities Standard
Larger pathways
P
Pathways
th should
h ld nott compromise
i operation
ti off
the facility
Enclosed pathway systems ‐‐ in air handling
spaces to
t meett Infection
I f ti Control
C t lR Requirements
i t
(ICR)
Segregation of cables for different networks &
applications
li ti (due
(d tot safety
f t protocols)
t l)
TIA‐1179 Healthcare Facilities Standard
E t
Entrance FFacilities
iliti (EF)
(EF)&E i t Rooms
& Equipment R (ER)