Software Project Management Final Exam
Final Exam: Software Project Management
Maximum Marks: 30 Duration: 2:00 Hours
e) Name 3 benefit comparison methods that executives can use when conducting
feasibility study. (1 Mark)
Scoring Model
Murder Board
Return on Investment (ROI)
i) What are the 5 types of risk responses that project managers can plan? (1 Mark)
Escalate
Avoid
Transfer
Mitigate
Accept
Page 2 of 7
Software Project Management Final Exam
Final Exam: Software Project Management
Maximum Marks: 30 Duration: 2:00 Hours
j) What are four types of dependencies that you need to consider when determining
Activity sequence? (1 Mark)
External Dependencies
Hard Logic or Mandatory Dependencies
Soft Logic or Discretionary Dependencies
Internal Dependencies
Page 3 of 7
Software Project Management Final Exam
Final Exam: Software Project Management
Maximum Marks: 30 Duration: 2:00 Hours
Page 4 of 7
Software Project Management Final Exam
Final Exam: Software Project Management
Maximum Marks: 30 Duration: 2:00 Hours
s) Bidders Conference is a meeting where you and potential bidders sit around and discuss
your requirements and vendors’ offerings.
t) When your project is running late, Crashing the project means that you identify the effort
driven activities, and you add more effort.
Q3) Consider the following “Project Network Diagram” and Calculate Early Start, Early Finish,
Late Start & Late Finish for all activities. Calculate total length of each path and specify the
critical path (5 Marks).
A+B+F+I = 2+3+4+3 = 12
A+D+G+I= 2+3+1+3 = 9
A+C+E+H+I = 2+1+2+2+3 = 10
Page 5 of 7
Software Project Management Final Exam
Final Exam: Software Project Management
Maximum Marks: 30 Duration: 2:00 Hours
A+C+D+G+I = 2+1+3+1+3 = 10
A (2) 1 2 1 2
B (3) 3 5 3 5
C (1) 3 3 5 5
D (3) 4 6 6 8
E (2) 4 5 6 7
F (4) 6 9 6 9
G (1) 7 7 9 9
H (2) 6 7 8 9
I (3) 10 12 10 12
Q4) Convert the following Work Breakdown Structure (WBS) from Tree Format to Outline
Format – Make sure to include outline numbering. (5 Marks).
Page 6 of 7
Software Project Management Final Exam
Final Exam: Software Project Management
Maximum Marks: 30 Duration: 2:00 Hours
1. Software System
1.1. Web
1.1.1.Web Site
1.1.2.Database
1.1.3.Web Application
1.1.3.1. Admin Module
1.1.3.2. User Module
1.2. Mobile App
1.3. Manuals
1.3.1.User Manual
1.3.2.System Manual
2. Project Management
2.1. Status Report
2.2. Project Team
2.2.1. Full Time
2.2.2. Part Time
Page 7 of 7