Specification of HDPE Pipeline
Specification of HDPE Pipeline
FOR
1.1 Polyethylene Pipes for Potable water application are manufactured according to
latest International Standard ISO – 4427 : 1996 DIN 8074 / 8075 for Gas ISO 4437.
1.2 IIL HDPE Pipe are produced to stringent quality control tests and inspection M/s IIL
is an ISO: 9002 certified company for producing plastic pipe systems.
2. TECHNICAL INFORMATION
2.1 Product Detail as mentioned in the attached Technical Literature in Section “D”
3. HANDLING
Storage
• Pipe, whether bundles, coils or loose pipe must be stored in a manner which is both
safe and which keeps the product free from damage. Pipe ends in particular should be
protected, as distortion or damage may cause difficulties in jointing.
• Pipe and fittings should be stored away from risk of damage from exhausts and other
heat sources.
• Pipe and large fittings can be stored externally for up to a year. However for longer term
storage cover should be provided to avoid UV damage. Compression fittings should be
stored under cover and kept dry. Fittings packaging must be kept intact up to the point
of use.
Stacking
• Individual pipes should be stacked on level ground, free of stones and sharp objects,
with timber batten supports at 1 m centers. Stack height should not exceed 1 mater for
bundle pack and 1.5 mater for loose Pipes
4. INSTALLATION PROCEDURE
Pipe Trench
• The Depth of Trench should be 0.9 Meter over the Pipe Crown in normal conditions. In
case of rocky ground then the depth of trench should be increased by at least 0.15
Meter and the excavated earth replaced by a stone free layer.
Trench Width
• The Width of Trench should be out side Pipe dia plus 300mm
Trench Bed
• In case of rocky ground then the fine sand of 0.15m thick should be used as bedding
underneath the pipe and a cover of sand on the sides and over the crown up to the
height of around 0.3m from top of the crown should be provided.
5. LAYING OF PIPES
• Small diameter pipes could easily be handle with out use of auxiliary tools & Machinery
• When jointing of bigger diameter pipes 90mm to 630mm diameter, should be using Butt
Fusion Machine.
• The bending of polyethylene is permissible and the properties of fusion jointed systems
enable changes of direction without recourse to the provision of special bends or anchor
blocks. However, the pipe should not normally be cold bent to a radius smaller than 25
times the outside diameter of the pipe. For push-fit or mechanical non end-load resistant
jointing systems, anchor blocks to withstand the resultant thrusts must be provided in
the traditional manner.
• The installation of flanged fittings such as sluice valves, hydrant tees, end caps etc.
usually requires the use of polyethylene stub flanges complete with backing rings and
gaskets. Care should be taken when tightening these flanges to provide even and
balanced torque. Provision should be made where heavy fittings are installed, for
concrete support both for the weight and to resist the turning moments associated with
valves and hydrants.
7. PE JOINTING SYSTEM
General Information
• Polyethylene pipes systems are relatively simple to joint and install. Two jointing method
are available to cater for the components that are used to build an operational system.
Butt Fusion
• Butt Fusion jointing involves the Fusion of two pipe ends in a special machine which
prepares the pipe ends, heats them and brings them together under pressure to form a
homogeneous weld. The joint is fully end load resistant and is at least as strong as the
parent pipe.
7. BACK FILLING
8. PRESSURE TESTING
• After pressure testing, filling of they trench is to be done in layers of 0.15m over the
pipe, utilizing stone free soil. The soil layer immediately over the pipe is to be
compacted by the tamping bars.
• The material used for upper layers can be coarser than that used for the initial backfill.
These layers should be carefully rammed down one on top of the other until the backfill
is completed.
9. COMMISSIONING PROCEDURE
• Upon the successful completion of a test, the remaining pressure in the pipeline should
be released slowly.
Fallowing successful pressure testing all new mains, lined or re-furbished, should be
commissioned in the following manner and in accordance with any local requirements: