0% found this document useful (0 votes)
24 views

Piping System Design Steps

Uploaded by

Ahmed bassam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views

Piping System Design Steps

Uploaded by

Ahmed bassam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 3

Piping System Design Steps

Step 1: Define System Requirements


Purpose: Establish system conditions to design the piping system.

Inputs:
 Flow Rate (Q):
Source: Project specifications or process flow diagram (PFD).
Units: kg/hr or m³/hr.
 Operating Pressure (P):
Source: Process design requirements or equipment manufacturer.
Units: bar, psi.
 Operating Temperature (T):
Source: Project specifications or fluid property charts.
Units: °C or °F.
 Media Properties (Density, Viscosity, Specific Heat):
Source: ASME Steam Tables (for steam systems), material data sheets, or chemical engineering handbooks.
Units: kg/m³ (density), cP (viscosity).

Outputs:
 Complete list of system conditions (flow rate, pressure, temperature, and fluid properties).

Step 2: Material Selection


Purpose: Choose the correct material based on design conditions and standards.

Inputs:
 Operating Pressure and Temperature: From Step 1.
 Corrosion Allowance (C): Based on fluid corrosivity and system lifespan.
Typical values: 3 mm for carbon steel, 1 mm for stainless steel.
Source: ASME B31.3 Table A-1.
 Material Mechanical Properties:
Yield Strength (), Ultimate Tensile Strength (UTS), Modulus of Elasticity.
Source: ASTM standards, ASME BPVC, Material Handbooks.
 Fluid Compatibility: Ensure selected material resists media.
Source: Chemical Compatibility Charts.

Outputs:
 Selected material grade (e.g., ASTM A106 Gr. B, ASTM A312 TP 316L) and corrosion allowance.

Step 3: Hydraulic Studies


Purpose: Determine flow characteristics, allowable velocity, and basic pressure drop values.

Inputs:
 Flow Rate (Q): From Step 1.
 Fluid Properties:
Density (): From fluid data charts.
Viscosity (): cP.
 Allowable Velocity (v):
Liquids: 2–3 m/s (Source: Piping Handbook).
Gases/Steam: 20–30 m/s (Source: Crane TP-410).

Equations Used:
 Velocity Formula:

v=Q/A

- v: Velocity (m/s)
- Q: Flow Rate (m³/s)
- A: Pipe cross-sectional area (m²)

Outputs:
 Calculated velocity to ensure it is within limits.

Step 4: Pipe Sizing


Purpose: Determine the required pipe diameter based on flow rate and allowable velocity.

Inputs:
 Flow Rate (Q): From Step 1.
 Allowable Velocity (v): From Step 3.

Equations Used:
 Diameter Formula:

D = sqrt((4 * Q) / (π * v))

- D: Pipe internal diameter (m)


- Q: Flow Rate (m³/s)
- v: Allowable velocity (m/s).

Outputs:
 Selected nominal pipe size and schedule.

Step 5: Pressure Drop Calculations


Purpose: Determine pressure losses due to friction, fittings, and components.

Inputs:
 Flow Rate (Q): From Step 1.
 Pipe Diameter (D): From Step 4.
 Friction Factor (f):
For turbulent flow: Use the Colebrook Equation or Moody Chart.
For laminar flow: f = 64 / Re.
 Pipe Length (L): Based on layout.
 Fluid Density (): From Step 1.

Equations Used:
 Darcy-Weisbach Equation:
ΔP = f * (L / D) * (ρ * v² / 2)

- ΔP: Pressure Drop (Pa)


- f: Friction factor
- L: Length of pipe (m)
- ρ: Density (kg/m³)
- v: Velocity (m/s)

Outputs:
 Total pressure drop across the system.

Step 6: Wall Thickness Calculation


Purpose: Ensure the pipe can safely handle internal pressure.

Inputs:
 Internal Pressure (P): From Step 1.
 Pipe Outer Diameter (D): From Step 4.
 Allowable Stress (): Material property.
Source: ASME B31.3 Table A-1.
 Corrosion Allowance (C): From Step 2.

Equations Used:
 Wall Thickness Formula:

t = (P * D) / (2 * (S * E - P)) + C

- t: Wall thickness (mm)


- P: Internal Pressure (Pa)
- D: Outer Diameter (mm)
- S: Allowable Stress (Pa)
- E: Weld Joint Efficiency (typically 0.85–1)
- C: Corrosion Allowance (mm).

Outputs:
 Final pipe wall thickness and selected schedule.

Step 7: Verification
Purpose: Cross-check all calculations against standards and project specifications.

Inputs:
 All outputs from previous steps.
 Design standards: ASME B31.3, Crane TP-410.

Outputs:
 Verified design that meets code compliance and project requirements.