EST 21
EST 21
USN
RV COLLEGE OF ENGINEERING®
(An Autonomous Institution Affiliated to VTU)
VISemester B. E. Grade Improvement ExaminationsNovember 2021
Civil Engineering
ESTIMATION AND COSTING
Time: 03 Hours Maximum Marks: 100
Instructions to candidates:
1. Answer onefull questionfrom 2 and 3.
2. Answer any THREE full questions from 1,4,5,6,7,8.
3 a Estimate the quantities for the following items of works for septic tank
shown in Fig 3a and cost of abstract.
i. Earthwork in excavation for foundation ,hard soil at . 400/
ii. PCC 1: 4: 8 for bed concrete at . 2500/
iii. BBM in 1: 4 for side walls at . 2200/
iv. RCC 1: 1 : 3 for cover slab at . 3000/ .
Fig 3a 20
b Estimate the quantities for the following items of work for a two room
building shown in Fig 3b and cost of abstract.
i. Earthwork excavation for foundation at . 120/
ii. PCC 1: 4: 8 bed concrete at . 2300/
iii. Size stone masonry in 1: 6 for foundation @ 2300/ .
Note : All dimensions are in meter
Fig 3b 20
6 Work out from first principle, the rate per unit of the following.
i. Brick masonry in 1: 6 in super structure
ii. 20 thick cement mortor 1: 3 plastering for outside wall.
iii. Cement concrete bed for foundation 1: 4: 8. 20
7 Work out from first principle, the rate per unit of the following.
i. RCC roofing of 150 thick with 1.5% reinforcement (TMT steel)
and 20 grade of concrete.
ii. Random rubble masonry in 1: 6 in foundation and plinth.
iii. 2.5 thick cement 1: 2: 4 floor. 20