Proposed Program
Proposed Program
4km)
Client: Awaday Town Administration
Contractor:
Consultant: East harerge Roads Authority
Subject : WORK SCHEDULE ACTIVITY
Work Schedule
Month=390 DAYS
Activity
Code
Activity Description Starting Ending Duration MONTH 1 MONTH2 MONTH3 MONTH4 MONTH 5 MONTH 6 MONTH 7 MONTH 8 MONTH 9 MONTH 10 MONTH 11 MONTH 12 MONTH 13
WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 WK10 WK11 WK12 WK13 WK14 WK15 WK16 W17 W18 W19 W20 WK21 WK22 WK 23 WK 24 WK25 WK26 WK 27 WK 28 WK29 WK30 WK 31 WK 32 WK33 WK34 WK 35 WK 36 WK37 WK38 WK 39 WK 40 WK41 WK42 WK 43 WK 44 WK45 WK46 WK47 WK 48 WK49 WK50 WK51 WK 52
2
Commecement or Mobalization Time (material,man power and Equipment) Week 4 week 10 week 6
204p2.1 soft Excavation to spoil (refer claus 204.9 of AACRA Standard week 9 week 34 week 25
205p2 laboratory testing to be carred out in extarnal laboratory as ordered by the engineer Week 6 week 52 week 46
205p3 laboratory fully fittedl furnished and equiped inculind all service Week 6 week 52 week 46
41.02 roadbed preparation and compacation of material to 95% of modified AASHTO T 180 Density Week 6 week 52 week 46
(iii) Compaceted TO 95% OF MODIFIED AASHTO T18 density Week 6 week 52 week 46
403P4Dense Graded Asphaltic Concrete (AC) Wearing Course Comppacted thickness 50mm
B. Side Walk
301: Sub base
Gpacted layer thravel Sub base (Unstabilized Crushed Gravel Compaction to 96% of modified ASHTO density
301P1.1ii (compacted layer thickness of maximum 200mm) Week 6 week 52 week 46
302: Base course
302P1.2iCrushed Stone base 98% of modified ASHTO density (maximum compacted layer thickness 200mm) Week 6 week 52 week 46
Foot Path and General Paving Works
615P14(a Foot path (side walk) Terazo tile flooring (400x400x50mm) or precolored concrete blocks on Cement screed
) stablized sand base including any jointing works. Week 6 week 52 week 46
Total carried to summary
Bill No.4: MINOR DRAINAGES
610p1.1: Excavating soft material situated within the following depth ranges below the surface
610P1.1i0.0m up to 1.5m
610P1.1ii1.5 up to 3.0m Week 6 week 52 week 46
610P1.1iii3.0m up to 4.5
610p1.1ivAbove 4.50m
610p1.2Excavation in hard material irrespective of Depth
610p2Backfilling
609p2.1Using excavated material
610p2.2Using Imported selected material
610p4.3Foundation fill consisting of compacted Granular material
610P3: Concreted pipe Culverts
32.01Excavation of open drains (channel excavation)
(a) Excavation of soft material irrespective of depth
(b) Extra over sub item 32.01(a) for excavation in hard material, irrespective of depth
32.02Back filling
(a) Using the excavated material
(b) Using Imported selected material
(c ) selected Granular Backfill
32.03Concret pipe culverts
(b) On Class B bedding
i36" dia pipe under walkway
ii42" dia pipe under walkway
iii48" dia pipes
32.06Cast in- situ concrete and formwork
(b) Inlet and outlet structures and skewed ends including formwork, false work, joints and class F2 surface finish
iClass C-25 Concrete for Culverts (box/slab) and ditch footing pad
iiClass C-20/20 Concrete for footing of RC salb Culverts
iiiClass C- 15/20 Concrete for footing of RC salb Culverts
32.09Steel reinforcement
(b) High tensile steel reinforcement Grade 60 in Culverts
610p3.2.
1 900mm internal Diameter RI pipe culvert on class B bedding
610p3.2.
2 1200mm internal Diameter RC pipe culvert on 150mm thick class B bedding
610p3.2.
4 1500mm internal Diameter RC pipe culvert on 150mm thick class B bedding
610p7.2: Cast in situ concrete and formwork
610p7.2. In invert slab to portals or rectangular (Box/slab) culverts, including false work,joints and class U2 surface finish
3 (Grade C-25)
In inlet and outlet structure skewed ends, thrust and anchor blocks, excluding false work, and formwork but
610p7.3 including class U2 surface finish (Grade C-25)
Concrete Gutter-
610p7.4Formwork U shape
of concrete Castpay
under in situ
itemconcrete
610p7.3(C-25)
abovewith to be constructed
(U2surface finish) on the side drain as detailed on
drawings. Price shall also include false work, Expansion joint at distance not greater thn 10m and formwork and
610p7.5 U2 surface finish. Average depth 1.0m.
610p10.0bSteel reinforcement high tensile steel (Grade420)
701p1.1 Grouted stone pitching
701p2.2 Cement mortared stone walls(Retaining wall)
701p2.2 Cement mortared stone walls(Masonry gutterl)
701p2.2 Cement mortared stone walls(Minor drainage)
Retaing wall
610p1.1 Excavating soft material situated within the following depth ranges below the surface(Retaining wall)
610p1.1i 0.0m up to 1.5m
610p1.1ii 1.5 up to 3.0m
610p1.1iii3.0m up to 4.5
610p1.1ivAbove 4.50m
610p1.2 Excavation in hard material irrespective of Depth
610 p2: Backfilling
609p2.1 Using excavated material
609p2.2 Using Imported selected material
609p4.3 Foundation fill consisting of compacted Granular material
Sheathing material
610p7.2.2Class "C" conrete (Grade C- 20) beneath masonry retaing wall
615p1: Curbing
615p1 Type A concrete Curbing (450x170mm) using (C-25) concrete. Price shall also include the necessary false work
and form works and U2 surface Finish.
616p2 Concrete Gutter Cover
617p3 Vehicle Crossing Cover (0.9mx0.2mx0.5m)
618p4 pedestrian Crossing Cover (0.9mx0.15mx0.5m)
9600Median Work and Greenary (GRASSING)
(C ) Steel railings
711p6 Pedestrian Signal Lantern including all necessary accessories and cabling (provisional Quantity)
Total carried to Summary
Octagonal
9100SUPPLY ANDsteel hot-deep
INSTALL galvanized road lighting column of 10m nominal height with 2x1.5m arm/bracket
(SU-R6)
overhang, cutout 0.6x.115m with tamper poof door, eathing terminal and fuse box hanging points and. Detail as
agreedLighing
910Street with the engineer. Each pole shall be incorporated with 10A/1P cartridge fuse with isolating fuse box
containing 3 phase insullated copper terminals for 2x4x25mm2 cable looping connection, all rail mountable.
910.01(a) Supplier and installer shall submitt 3rd party product test report and 5 years product
910.01(b) 10m spare pole with 2x1.5m arm bracket, base plate, and J- bolts with nuts. As per the detail in drawings.
910.02Concrete plinth for lighting pole column
C30 type concrete foundation for 10m lighting column (0.6*0.6*1.2m) including ecxavation, concrete ancher bolt
asspmbly, conduit cable joint pit all as specified and/or shown on drawings
Energy
910.03TYPE saving IP66
PHILIPS, rateDISANO
THORN, road light
ORfitting luminaires
EQUIVALENT in die-castEQUAL
APPROVED aluminum housing type LED x 280 watts, 30000
1m/fitting, comolete with power driver and surge protection standard SPI Luminaries shall have a minimum
onerating life of 50000 hours
910.04Supply and Lay Conduits
910.04(a) Trench for cable not exceeding 450mm wide depth not less than 600mm tobe filled before and after 110mm
internal UPVC diameter conduit laying with minimum debth of 100mm ordinary sand
Trench for duct not exceeding 450mm wide depth not less than 1.2m and lay 2x100mm internal UPVC diameter
910.04(b) duct with concrete bed and sround in trench debth not exceeding 150mm concrete.
910.05Supply and Lay Cable
Cu/XLPE/PVC, with extruded or taped bedding/filling, PVC insulation shall be rated 90oc. VDE 0271(VYRGby), IEC
910.05(a) 502, 0.6/1 KV
i 3x25/16mm2
ii NYY 3x2.5mm2
Standared warning tape engraved with 'ELECTRICAL'
910.06Feeder pillar, electrodes and Duct Access
1pc CONTACTOR rate oprational power in AC3 380/400V is 50KW/3p, Rated operational voltage is 1000V.
Comlete with auxiliary contacts for solar awitches.
Photo electric control unit set to swich on a 70lux
25% reserve space
1x with
910.07Earth copper16mm2
electrode bare copper cable (2m) from board earthing point to 1500x16mm dia. Copper bond earth
arrangement
road with copper fixing clamp(manhole measured elsewhere) and other accessories. Price include for the cable
rod with accessories. Earthing arrangement as shown in the drawing to comply 5 ohm overall resistance
910.08Manholes(Duct Access)
910.08(a) Concrete duct access UPVC chamber 1000x1000x700mm internal dimension with 5mm galvanized iron sheet
cover on an average lin concrete 100mm.
910.08(b) Concrete duct access UPVC chamber 600x600x700mm internal dimension with 5mm galvanized iron sheet cover
on an average lin concrete 100mm.
910.08(c Concrete duct earthing manhole 500x500x500mm internal dimension with 5mm galvanized iron sheet cover on
) an average lin concrete 100mm.
9000 ANCILARY WORKS-TOTAL (carried forward to summary)
Project: Awaday Town AC(Granda Bile-Rasho) Road Piroject (2.4km)
Client: Awaday Town Administration
Contractor:
Consultant: East harerge Roads Authority
Subject : LABOUR SCHEDULE
LABOUR SCHEDULE
WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 WK10 WK11 WK12 WK13 WK14 WK15 WK16 WK25 WK26 WK 27 WK 28 WK29 WK30 WK 31 WK 32 WK33 WK34 WK 35 WK 36 WK37 WK38 WK 39 WK 40 WK41 WK42 WK 43 WK 44 WK45 WK46
8 Chief Surveyor
9 Laboratory/material technicial
10 Hydraulic Engineer
11 Material Engineer
Contractor:
MACHINE SCHEDULE
Activity
Code Activity Description Starting Ending Duration MONTH 1 MONTH2 MONTH3 MONTH4 MONTH 5 MONTH 6 MONTH 7 MONTH 8 MONTH 9 MONTH 10 MONTH 11 MONTH 12 MONTH 13
WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 WK10 WK11 WK12 WK13 WK14 WK15 WK16 W17 W18 W19 W20 WK21 WK22 WK23 WK24 WK25 WK26 WK27 WK28 WK29 WK30 WK31 WK32 WK33 WK34 WK35 WK36 WK37 WK38 WK39 WK40 WK41 WK42 WK43 WK44 WK45 WK46 WK47 WK48 WK49 WK50 WK51 WK52
A Construction plant
B VEHICLES
MATERIAL SCHEDULE
WK1 WK2 WK3 WK4 WK5 WK6 WK7 WK8 WK9 WK10 WK11 WK12 WK13 WK14 WK15 WK16 WK25 WK26 WK 27 WK 28 WK29 WK30 WK 31 WK 32 WK33 WK34 WK 35 WK 36 WK37 WK38 WK 39 WK 40 WK41 WK42 WK 43 WK 44 WK45 WK46 WK47 WK 48 WK49 WK50 WK51 WK 52 WK45 WK46 WK47 WK 48 WK49 WK50 WK51 WK 52