Lecture 11
Lecture 11
SANITARY
SEWERAGE &
ENGINEERING
ENVIRONMENTAL ENGINEERING - II
INTRODUCTION
Definition of Terms
Sewage:
It is the waste of foul water of the community conveyed
by the sewer. There are three types of sewage:-
Industrial Sewage:
The liquid wastes obtained from industrial process such as
dying, papermaking, etc, are called industrial sewage.
Storm Sewage:
It is that part of surface run off which is flowing in sewer
during the rainfall.
ENVIRONMENTAL ENGINEERING - II
Sullage:
It is the waste water resulting from personal wasting,
bathing, laundry, food preparation and cleaning of
utensils. It does not include discharge from hospitals and
slaughter houses which has high content of organic
matters. Sullage is not very foul and can be disposed off
in open drain with out treatment.
ENVIRONMENTAL ENGINEERING - II
Garbage
It is used for dry refuse of town containing organic,
inorganic solids, semisolids, combustible,
noncombustible, putrecible and non-putrecible substances.
It includes sweeping from houses, streets, markets, public
places, garden etc. work paper, leaves, grass, panning of
vegetable, decaying fruits etc. with small quantities of
sand, cinder, clay and gravel constitute garbage. It is
collected separately from sewage and sullage and dispose
off separately.
ENVIRONMENTAL ENGINEERING - II
Inflow:
It is the water entering the sewer from surface source
through manholes, open cleanouts, perforated manhole
cross, and root drain of basement sumps connected to the
sewers inflow occurs only during runoff.
ENVIRONMENTAL ENGINEERING - II
Sewers.
Sewer is a pipe or conduit carrying sewage, sewage are
usually not flowing full (gravity flow). The full flowing
sewers are called fore main as the flow is under pressure.
ENVIRONMENTAL ENGINEERING - II
Types of Sewers
Sanitary Sewer:
It is a sewer carrying sanitary and industrial sewage
excluding storm sewage. It is also some time called
separate sewer.
-
ENVIRONMENTAL ENGINEERING - II
Types of Sewers
Storm Sewer:
It is the one which carried storm sewage including
surface runoff and street wash.
Continued Sewer:
It is the one carrying domestic, industrial and storm
sewage all together.
ENVIRONMENTAL ENGINEERING - II
Sewerage.
It is the science and art of collecting, treating and
disposing of sewage. There are three systems of
sewerage.
✓ Separate System
✓ Combined System
✓ Partially Separate System
ENVIRONMENTAL ENGINEERING - II
Separate Sewerage System
Advantages
➢ The load on treatment plant is less as only sewage is
carried to the plant.
➢ The size of sewers are small thus economical.
➢ When pumping is required the system process to be
economical.
➢ Natural water is not unnecessarily polluted by
sewage.
ENVIRONMENTAL ENGINEERING - II
Disadvantages
➢Cleaning of sewers is difficult due to their small size.
➢The maintenance costs are high.
➢ The self cleaning velocity is not easily achieved.
➢The storm sewers come in operation in rainy season only.
➢They may be chocked in during dry season by garbage.
➢The separate system is suitable when separate outlets for
storm water is available and the topography is such that
storm water can be dispose off in natural drains.
ENVIRONMENTAL ENGINEERING - II
Combined Sewerage System
Advantages
➢ It is easy to clean combine sewers because of large size.
➢ The maintenance cost is reasonable.
➢ It reduces strength of sewage by mixing storm water with
sewer.
➢ The system requires one sewer making it economical.
ENVIRONMENTAL ENGINEERING - II
Disadvantages
➢ In storm seasons water may overflow and the sewer may
damage causing serious health risks.
➢ The combine sewer gets silted and becomes foul in dry
days.
➢ The load on treatment plant is high because storm water is
also carried there.
➢ The storm water gets polluted unnecessarily.
➢ The system is uneconomical when pumping is need.
The system is suitable when space available for laying two
sets of sewers is less and when pumping is not required.
ENVIRONMENTAL ENGINEERING - II
Partially Separate Sewerage System
Advantages
➢ It combines the good features of both systems.
➢ The setting is avoided due to entry of storm water.
➢ The storm water from houses is easily disposed off.
➢ The sewers are of reasonable size.
ENVIRONMENTAL ENGINEERING - II
Method of Disposal of Sewage
Cost.
The system has less initial cost but the operation cost is
very high because of working labors.
Design of building.
The lavatory has to be build separate from residential
building which cause inconvenience.
ENVIRONMENTAL ENGINEERING - II Reasons why we are not using dry system
In sanitary Condition.
The sewage is carried once in 24 hours while sewage
becomes unsanitary after 5 – 6 hours.
Labor problems.
If the labor goes on strike the system totally fails.
Land requirement.
It requires large area for disposal of sewage thus
becoming inconvenient.
ENVIRONMENTAL ENGINEERING - II
Foul Appearance.
Open drain.
Pollution of Water.
Risk of Epidemic.
Cost.
Compact Design.
The lavatories can be accommodated inside the building
which cause compact design of house and convenience.
ENVIRONMENTAL ENGINEERING - II
Hygienic System.
The sewage is carried in covered drains thus the risk of
and break of epidemic is reduced.
Land Requirement.
The land requirement is very low which make the system
economical. (for treatment & disposal)
ENVIRONMENTAL ENGINEERING - II
Treatment.
Proper treatment of sewage is possible to make the
sewage suitable for disposal.
Storm Sewer
Combined Sewer
House Sewer
Lateral Sewer
Outfall Sewer
Collection Works:
Period of design is “Indefinite” as the system is designed to
cater for the maximum development of the area.
Disposal works:
Design period is usually 10 years. Rates of flow required
are: average daily, peak and maximum flow rated, including
infiltration.
Treatment Works:
Design period is 15 to 20 years. Flow rate required are
average and peak rates both including infiltration.
ENVIRONMENTAL ENGINEERING - II
INVERT LEVEL
1. Preliminary investigation
3. Actual design
5. Subsequent modifications
ENVIRONMENTAL ENGINEERING - II
PRELIMINARY INVESTIGATION
If the map of the area is not already available, the first step is
to carry out survey to draw a map of the project area.
Different details are marked on the map like:
• Streets
• Railway lines
• Streams
• Location of under utilities like gas, water mains etc
•Establish BENCH MARKS throughout the area and make
contour profiles
ENVIRONMENTAL ENGINEERING - II
Design Flow
• Sanitary sewer = Peak sewage flow + infil+Industrial flow
• Partially Combined = 2 x peak sewage flow + infil +
Industrial flow (WASA Criteria)
Design Equation
• Sewers are required on the basis of open channel flow
• V = 1/n R2/3 S ½ (Manning's Formula)
ENVIRONMENTAL ENGINEERING - II DESIGN CONSIDERATIONS /
FORMULATION OF DESIGN CRITERIA
Where
V = Velocity, m/sec
R = Hydraulic mean depth = Area / wetted perimeter
= D/4, when pipe is flowing full or ½ full
S = slope of sewer
N= Co-efficient of roughness for pipe (0.013 for R.C.C
pipes)
Minimum Cover:
1m is taken as minimum cover over sewers to avoid damage
from live loads coming on sewers.
ENVIRONMENTAL ENGINEERING - II
Manholes
Purpose:
1. Cleaning
2. Inspection
3. House connections
Where Provided
1. At every change in dia of pipes
2. Where two different dia of pipes are to be
connected
Spacing:
225mm – 380mm Spacing ≤ 100m
460mm – 760mm Spacing ≤ 120m
> 760mm Spacing ≤ 150m
Note: for plots, one manhole be provided for 2 plots
ENVIRONMENTAL ENGINEERING - II Qd/Qf ratios
sewers :
• Sewer joints
• Manholes
• Disposal station
Va/Vf = 0.6
Va = 0.6 x 1.57
= 0.94 m/sec
ENVIRONMENTAL ENGINEERING - II
CARRY OVER OF INVERT LEVELS
225 mm
I.L - 198
I.L = 199
M2 M3
225m I.L =
225mm
M4
N.B: Lower I.L is carried forward to maintain GRAVITY FLOW
ENVIRONMENTAL ENGINEERING - II
225 mm
I.L - 198
I.L = 199
M2 M3
225m I.L =
460mm
M4
I.L = 198 – difference of dia
= 198 – 0.235 = 197.765m
ENVIRONMENTAL ENGINEERING - II
SEWER CONSTRUCTION
5. Shifting of Levels:
Done by using levels, staff rod. Threads, pegs etc.
6. Laying and Jointing of Pipes
Joints: (1) Bell & Spigot 225mm – 610mm
(2) Tongue and Groove > 610mm
7. Backfilling
Manual backfilling up to 2 feet. Afterwards with tractor
8. Construction of Appurtenances (Accessories)
ENVIRONMENTAL ENGINEERING - II
APPURTENANCES
4’ Brick work 9”
Thick
Variable
6”
6”
4’ dia
(Int) PCC(1:2:4)
ENVIRONMENTAL ENGINEERING - II DROP MANHOLES
Drop
Manhole
Benching
ENVIRONMENTAL ENGINEERING - II
INLETS
Footpath
CURB INLET
Vertical
Inlet
Road
Sewer
Horizontal
GUTTER INLET Water Grating Footpath
SEWER
ENVIRONMENTAL ENGINEERING - II SEWER PROFILES / L-SECTIONS
MH
NSL
I.L
Pipe Dia (mm)
Slope
M.H
Length (m)
Trench Bed (m)
Types of pipes:
PVC
AC
P.C.C
R.C.C
C.I & Steel pipes are used under unusual loading condition
ENVIRONMENTAL ENGINEERING - II
P.C.C Pipes
Normally used for small storm desires and sanitary sewers.
Specifications used are ASTM.
Class: I II III
Weakest →Strongest
Wall Thickness: Wall A, B, C,
Normally used
ENVIRONMENTAL ENGINEERING - II
R.C.C Pipes
Wall Thickness:
Wall A Wall B Wall C
Min Thickness Normally used Max thickness
ENVIRONMENTAL ENGINEERING - II
STRENGTH OF R.C.C PIPE
Pipe
L.F = 1.1
Quadrant
L.F = 1.5
ENVIRONMENTAL ENGINEERING - II
Velocity in Sewers
The deposition of solids in sewer is undesirable. The
velocity of sewage in sewer should be such that there is no
setting of solid in sewer for a wide range of discharge.
The self cleaning velocity largely depended on the scope
or gradient of sewer and the size of suspended solids in
sewage and size of sewer and the material of sewer.
ENVIRONMENTAL ENGINEERING - II Minimum Self-cleaning velocity
Purpose:
These are required to ELEVATE and TRANSPORT
wastewater when
• Continuation of gravity flow is no longer feasible and
there is a need to raise the HGL of sewer.
• Any obstacle lies in the path of sewer (e.g. river, canal
etc)
• Receiving stream is higher than the sewer.
ENVIRONMENTAL ENGINEERING - II
Pumps
Outfall sewer
Well Curb P
Suction Pipe
ENVIRONMENTAL ENGINEERING - II GENERAL DESIGN CONSIDERATIONS
Diff w.r.t Q
dt /dQ = -1 V(P-Q)-2 (-1) – 1 x VQ-2
dt / dQ = 0 for min cycle time
0 = V / (P-Q)2 – V/Q2
V / (P-Q)2 = V / Q2
P2 = 2PQ
Q = P/2
t = tmin when Q = P/2
Put Q = P/2 and t = tmin in Eqn. I
tmin = V / (P-P/2) + V/(P/2)
= V / (P/2) + V / (P/2)
= 4V/P
V = P tmin/4
ENVIRONMENTAL ENGINEERING - II PROBLEM
All techniques for estimating storm flow are based upon use of rainfall
data – either directly or indirectly and rational method is not an
exceptional to it.
Where
Q = amount of rainfall which appear as runoff , m3 / hr.
i = intensity of rainfall , m / hr
A = Area upon which the rainfall, m2
C= Runoff coefficient, i.e the fraction of incident rainfall
which appear as surface flow. It depend upon the nature of
area.
ENVIRONMENTAL ENGINEERING - II
Typical values of ‘C’
The max rate of runoff for a given rainfall intensity will occur
when the rainfall has continued for a period sufficient to
permit flow to reach the inlet from the most remote point of
the drainage area. Consider the rectangular water shed
shown below:-
ENVIRONMENTAL ENGINEERING - II TIME OF CONCENTRATION
C
5 min
B
5 min A
5 min
Inlet
Sewer
Inlet Time
I1
Time of
I2 Flow in
sewer
ENVIRONMENTAL ENGINEERING - II
Where.
I = intensity of rainfall, mm / hr
t = duration of rainfall, minutes
A,B = Constants, determined using rainfall data
ENVIRONMENTAL ENGINEERING - II
Constants ‘A’ & ‘B’
A B C
4 ha 3 ha 2 ha
0.8 0.7 0.8
Inlet time for each area = 8 minutes
Time of flow between manholes = 5 minutes
Rainfall intensity I = 2670/(T + 15) mm/hr
4 3 2 1
ENVIRONMENTAL ENGINEERING - II
Solution
Using rational formula
• Q = Ci A