5. The three-time estimates (to), (tm), (tp) for each 1 L3 CO4
activity in a project are given below. i. Draw the network ii. Determine the project completion time. iii. Find the critical path. Activity Time Estimates to tm tp 1-2 9 12 21 1-3 6 12 18 2-4 1 1.5 5 3-4 4 8.5 10 2-5 10 14 24 4-5 1 2 3