Rfi Summary For 20-12-2024
Rfi Summary For 20-12-2024
7) on Itarsi -
Nagpur section of Central Railway
Client:- Central Railway
PMC:- Technogem Consultants Pvt. Ltd.
EPC Contractor:- KEC International Limited
Raising Date :-19-12-2024
Earthwork
Chainage Inspection Inspection Requested by
SN RFI NO. Description Length (M) Layer RFI Date RFI Time Remarks
From To Date Time (Mob.)
Santosh Kumar
1 CR/CCD-MJY/EW/2024/6996 FDD testing for embankment 863+400 863+500 100 5th 19-Dec-24 4:51 PM 19-Dec-24 10:00 AM
(6396000566)
Santosh Kumar
2 CR/CCD-MJY/EW/2024/6997 FDD testing for embankment 863+640 863+860 220 2nd 19-Dec-24 4:51 PM 20-Dec-24 11:00 AM
(6396000566)
Santosh Kumar
3 CR/CCD-MJY/EW/2024/6998 FDD testing for embankment 865+840 865+980 140 4th 19-Dec-24 4:51 PM 20-Dec-24 1:00 PM
(6396000566)
Santosh Kumar
4 CR/CCD-MJY/EW/2024/6999 FDD testing for embankment 867+000 867+100 100 14th 19-Dec-24 4:51 PM 20-Dec-24 2:00 PM
(6396000566)
Santosh Kumar
5 CR/CCD-MJY/EW/2024/7000 FDD testing for embankment 868+360 868+480 120 1st 19-Dec-24 4:51 PM 20-Dec-24 3:00 PM
(6396000566)
Santosh Kumar
6 CR/CCD-MJY/EW/2024/7001 FDD testing for embankment 868+520 868+640 120 5th 19-Dec-24 4:51 PM 20-Dec-24 4:00 PM
(6396000566)
Santosh Kumar
7 CR/CCD-MJY/EW/2024/7002 FDD Testing for Subgrade 873+060 873+300 240 1st 19-Dec-24 4:51 PM 20-Dec-24 11:00 AM
(6396000566)
Santosh Kumar
8 CR/CCD-MJY/EW/2024/7003 FDD Testing for Subgrade 873+300 873+560 260 1st 19-Dec-24 4:51 PM 20-Dec-24 11:00 AM
(6396000566)
Santosh Kumar
9 CR/CCD-MJY/EW/2024/7004 FDD Testing for Subgrade 855+700 855+900 200 1st 19-Dec-24 4:51 PM 20-Dec-24 10:00 AM
(6396000566)
Santosh Kumar
10 CR/CCD-MJY/EW/2024/7005 FDD Testing for Subgrade 855+280 855+600 320 3rd 19-Dec-24 4:51 PM 20-Dec-24 10:00 AM
(6396000566)
Bridge Work
Chainage Inspection Inspection Requested by
SN RFI NO. Description Br. No. Section RFI Date RFI Time Remarks
From To Date Time (Mob.)
Checking of reinforcement shuttering
Atif
1 CR/CCD-MJY/BRW/2024/7006 for Retaining Wall 3rd lift both end 861+000 862+000 861/2 MALK-BYS 19-Dec-24 4:28 PM 20-Dec-24 10:00 AM
(8293659009)
and allow for casting
897/1 (Up
Checking of ground improvement Lalit
2 CR/CCD-MJY/BRW/2024/7007 897+000 897+100 line JKR-MTY 19-Dec-24 4:35 PM 20-Dec-24 2:00 PM
level & allow PCC for bottom slab (97191 33527)
Extention)
Checking of reinforcement, Shuttering
Lalit
3 CR/CCD-MJY/BRW/2024/7008 & allow concrete work for Dirt wall ET 897+100 897+200 897/2 JKR-MTY 19-Dec-24 4:57 PM 20-Dec-24 11:00 AM
(97191 33527)
end.
Building Work
Inspection Inspection Requested by
SN RFI NO. Description Structure Location RFI Date RFI Time Remarks
Date Time (Mob.)
3rd Row footing reinforcement and
Piyush Shukla
1 CR/CCD-MJY/BLDG/2024/7009 shuttering checking and allow for EI Building Barsali 19-Dec-24 4:12 PM 20-Dec-24 2:00 PM
(8839800846)
casting work.
Checking of steel & shuttering and
Abhishek
1 CR/CCD-MJY/BLDG/2024/7010 allow for casting of staircase below EI Building Multai 19-Dec-24 4:58 PM 20-Dec-24 5:00 PM
(9835416167)
plinth beam column
OHE & GE Work
OHE Mast no. Inspection Inspection Requested by
SN RFI NO. Description Location RFI Date RFI Time Remarks
from To Date Time (Mob.)
Abhishek
1 CR/CCD-MJY/OHE/2024/7011 Foundation Casting km 859/860 MALK-BSY 19-Dec-24 6:22 PM 20-Dec-24 10:30 AM
(9835416167)
Abhishek
2 CR/CCD-MJY/OHE/2024/7012 Foundation Casting km 870/869 BYS-AMLA 19-Dec-24 6:22 PM 20-Dec-24 11:30 AM
(9835416167)
Narendra Pal
3 CR/CCD-MJY/OHE/2024/7013 OHE mast erection/grouting km 893/892 JKR-MTY 19-Dec-24 6:22 PM 20-Dec-24 11:00 AM
(9354736995)
Narendra Pal
4 CR/CCD-MJY/OHE/2024/7014 Material checking for MRC. MTY store 19-Dec-24 6:22 PM 20-Dec-24 11:00 AM
(9354736995)
PLC 33 kv
Satendra
5 CR/CCD-MJY/OHE/2024/7015 160mm HDPE pipe laying work for KM 899/20-22 MTY-HTN 19-Dec-24 6:22 PM 20-Dec-24 10:30 AM
(9412444911)
track crossing .