FMEA- Process
FMEA- Process
2001
TRAINING MATERIAL
ON
No.36, Muktha Building, 8th Main 18th Cross, Malleswaram, Bangalore 560 055
Ph : 080-3440703 / 3440704, Fax : 080-3311622
Email: [email protected]
Origin
Common Definitions
Failure:
Failure Mode:
What is FMEA?
Why FMEA?
1. Essence is timeliness
2. Pro-Active rather than reactive
3. Before process failure mode occurs
Advantages of FMEA
Types of FMEA
QS-9000 requirements
POTENTIAL
FAILURE MODE AND EFFECTS ANALYSIS
(PROCESS FMEA)
Process Potential Potential SEV Class Potential Occ Current Current D R Recommended Responsibility & Action Results
Function Failure Effect(s) Cause(s) / ur Process Process e P Action(s) Target
Mode of Failure mechanism Control Controls t N Completion Date
(s) of Failure Prevention Detection e
c
t
R
Actions
Sev Occ Det P
Taken
N
Example
Process function / description
- Manual application of wax
inside door
- Machining of outer diameter
Requirements
- To cover inner door at minimum
thickness to retard corrosion
- Outer diameter, run-out, free
from tool mark
Example
- Cannot locate
- Cannot face
- Does not fit
- Does not match
- Scrap, re-work
- Vehicle / item inoperable
- Loss of primary function
- Customer dissatisfaction
Potential Cause(s) /
Severity Class Mechanism (s) of
Failure
mode result in a final customer and / or a mode result in a final customer and / or a
manufacturing / assembly plant defect . the manufacturing / assembly plant defect . the
final customer should always be considered final customer should always be considered
first. If both occur , use the higher of two first. If both occur , use the higher of two
severities. severities.
Low Vehicle /item operable but comfort /convenience Or 100 % of product may have to reworked, or
item (s) operable at reduced level of performance. vehicle /item repaired off line but does not go to 5
repair department
Very low Fit and finish / squeak and rattle item does not Or the product may have to be sorted ,with no
conform .defect noticed by most scrap and a portion ( less than 100 % ) reworked . 4
customers( greater then 75 % )
Minor Fit and finish / squeak and rattle item does not Or portion ( less then 100 % ) of the product may
conform .defect noticed by 50% of customers have to be reworked with no scrap , online but out 3
of station
Very minor Fit and finish / squeak and rattle item does not Or portion ( less then 100 % ) of the product may
conform .defect noticed by most customers ( less have to be reworked with no scrap , online but in 2
then 25 %) station
None No discernible effect Or slight inconvenience to operation or operator ,
1
or no effect
O
Potential
c
Cause(s) /
Classification Mechanism (s) of
c
u
Failure
r
O
Current Current
Potential Cause(s) / Mechanism c
Process Process
c
(s) of Failure Control Control
u
prevention detection
r
Contd.….
Example
Under Man
- Fails to clean
- Fails to assemble
- Fails to tight
- Mis-locate
Under machine
- inadequate lubrication
- excessive vibration
- excessive spindle run-out
Under process
- improper time / temperature
- inadequate gating / venting
Under design
- Symmetric design
- Difficult to assemble
Under Raw Material
- Mixed material
- New source
- Alternate material
- Excessive hardness
D
Current Current e
Process Process t
Occurrence Control Control e
Prevention Detection c
t
> 1.67
Remote: Failure is unlikely < 0.010 per thousand vehicles / item 1
D
Current Process Current Process e
R
t
Control Control e
P
N
Prevention Detection c
t
Type of Controls
Level Type Examples
P- Prevention of
Mistake proofing
Prevention causes
Detection of causes SPC, Visual
D- & leading to control etc. 100%
Detection corrective actions inspection, patrol
Detection of defect inspection
Examples
- Visual Check, one per shift for film thickness
- SPC chart five pieces in an hour
- On-line monitoring of crimping force
- Auto-control of temperature
- 100% on-line inspection
- Visual monitoring of Ammeter
RP Recommended
Detection N Action
Inspection Types
Detection Criteria: Suggested range of detection methods Ranking
A B C
Almost Impossible Absolute certainty of non- detection . X Can not detect or is not checked
10
Very Remote Control will probably not detect X Control is achieved with indirect or
random checks only 9
Remote Control have poor chance of detection X Control is achieved with visual inspection
only. 8
Very Low Control have poor chance of detection X Control is achieved with double visual
inspection only. 7
Low Controls may detect X X Control is achieved with charting methods,
such as SPC 6
Moderate Controls may detect X Control is based on variable gauging after
parts have left the station, or Go / No Go
5
gauging performed 100 % of the parts after
parts have left the station
Moderately High Controls have a good chance to detect. X X Error detection in subsequent operations,
or gauging performed on set up & first 4
piece check
High Controls have a good chance to detect. X X Error detection in- station , or error
detection in subsequent operations by
multiple layers of acceptable supply , 3
select , install , verify , con not accept
discrepant part
Very High Controls almost certain to detect X X Error detection in station . Can not pass
discrepant part 2
Almost certain Controls almost certain to detect X Discrepant parts can not be made because
item has been error- proofed by process / 1
product design.
Responsibility
Action
Recommended Action & Target
Results
Completion Date
D
Responsibility & Target Actions
Sev
O e
RPN
Taken cc
Completion Date t
Action Results
Follow up actions
The Process - responsible engineer is responsible for ensuring that all actions recommended have been implemented or
adequately addressed . FMEA is a living document and should always reflect the latest design level as well as the latest
relevant actions.
The Process responsible engineer has several means of ensuring that concerns are identified and that recommended actions
are implemented . they includes but not limited to followings :
1 PROCESS IMPROVEMENTS: The FMEA drives process improvement as primary objective. With an emphasis on
Error / Mistake proofing solutions
2 HIGH RISK FAILURE MODES: The FMEA address all high-risk failure modes as identified by FMEA team, with
executable action plans. All other failure modes are considered.
3 CONTROL PLANS: The pre launch and production Control Plan consider the failure modes from the process
FMEA.
4 INTEGRATION: The FMEA is integrated and consistent with process flow diagram and the process control plan.
The process FMEA considers the design FMEA, if available as part of its analysis.
5 LESSONS LEARNED: The FMEA considered all major “ lessons learned “ as input to failure mode identification
6 SPECIAL OR KEY CHARACTERISTICS: the FMEA identifies appropriate key characteristics candidates as
input to the key characteristics selection process , if applicable due to company policy.
7 TIMING: The FMEA is completed during the “ Window of opportunity “ where it could most efficiently impact the
product design of product or process.
8 TEAM: The right people participate as part of the FMEA team through out the analysis and are adequately trained in
FMEA methods
9 DOCUMENTATION: the FMEA is completely filled out “ by the book ” including “ action plan ” and new RPN
values.
TIME USAGE: Time spent by FMEA team as early as possible is an effective & efficient use of time, with a value –added
result. This assumes recommended actions are identified as required and the actions are implemented.