PI-8130-0000-0009

Document

Uploaded by

ISQ
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
54 views52 pages

PI-8130-0000-0009

Document

Uploaded by

ISQ
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 52

CSPC NANHAI PETROCHEMICALS PROJECT

COMMISSIONING CHECK LISTS

WORK PROJECT INSTRUCTION: PI-8130-0000-0009

Project Management Contractor (BSF)

REV DATE REASON FOR ISSUE BY CHK’D APPR


A 26-SEP-03 Issued for comment MAV BRK
0328-FEB
B00 Issued for use MAV BRK RM
NOV-043
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

DOCUMENT ISSUE/REVISION INFORMATION

Document #: PI-8130-0000-0009

Current Revision #: 00

Reason for Issue/Revision:


This document is issued/revised because:

 Check lists revised to incorporate CSPC/BSF comments received.


.

Description of Change:
The following changes were made:

 Buildings and TSO valve checklist added please rReference document check
list index revised.
 General comments incorporated.
.

Applicability:
This document applies to:

 All project EPC contracts.


 All Self Perform scopes.

Note: This document is intended for guidance regarding the minimum level of
commissioning checks per item of equipment.

Name of contact person: M.A.Vaughan.

Contact Number: 0752-368556-46519097

832048896.doc
Page 2 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECKLISTSCHECK LISTS

TABLE OF CONTENTS
No. Page
1.0 SCOPE 34

2.0 PURPOSE 34

3.0 DEFINITIONS 34

4.0 RESPONSIBILITIES 34

5.0 REFERENCES 34

6.0 ATTACHMENTS INDEX OF COMMISSIONING CHECK LISTS 6

7.0 CHECK LISTS 47

Index of ChecklistsCheck lists

Commissioning ChecklistsCheck lists

832048896.doc
Page 3 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

1.0 SCOPE

This Work Instruction Project providesInstruction provides the framework to be


followed by all EPC and Self-Perform CONTRACTORS in determining the
content of Commissioning ChecklistsCheck lists.

2.0 PURPOSE

To provide a complex-wide level of detail for Commissioning ChecklistsCheck


lists which ensures consistency between the various Contracts.

3.0 DEFINITION

Commissioning checklistscheck lists Check lists are the forms that describe the
final checks made on equipment by the responsible Commissioning group
immediately prior to putting that equipment into service. These checks are
conducted after receipt of notification of Mechanical Completion from the
Contractor’s Construction group for the item of equipment concerned. The
completed checklistscheck lists form part of the final Systems Handover
DossierCompletion Manual for the system System containing the equipment in
question.

4.0 RESPONSIBILITIES

The CONTRACTOR’s Commissioning Manager shall be responsible for ensuring


that the Contractor’s Commissioning checklistscheck lists Check Lists contain, as
a minimum, the checks listed on the attached examples.

Specialised pieces of equipment not listed in this Instruction shall have dedicated
check lists prepared, the content of which shall be approved by PMT/CSPC.

5.0 REFERENCES

DEP 61.10.08.11–CSPC Field Inspection Prior to Commissioning of


Mechanical Equipment
PR-8130-0000-0006 Preparation of a System Completion Manual (EPC)
PR-8130-0000-0012 Completion and Handover Procedure

832048896.doc
Page 4 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

6.0 INDEX OF COMMISSIONING CHECK LISTS


Note: Native copies of the Excel check lists can be obtained from Core Commissioning
group
Equipment Description Project Form No.
Air Fin Coolers FM-8130-0000-0001
Basins FM-8130-0000-0002
Buildings FM-8130-0000-0003
Burner Systems FM-8130-0000-0004
Centrifugal Compressors FM-8130-0000-0005
Centrifugal Pumps FM-8130-0000-0006
Columns FM-8130-0000-0007
Control Valves FM-8130-0000-0008
Desuperheaters FM-8130-0000-0009
Diesel Engines FM-8130-0000-0010
Drums FM-8130-0000-0011
Dryers (Fixed Bed) FM-8130-0000-0012
Ejectors FM-8130-0000-0013
Electric Trace Heating FM-8130-0000-0014
Extruders FM-8130-0000-0015
Fans FM-8130-0000-0016
Filters FM-8130-0000-0017
Fired Heaters/Boilers FM-8130-0000-0018
Flares FM-8130-0000-0019
Functional trip tests FM-8130-0000-0020
Gas Turbines FM-8130-0000-0021
Instruments FM-8130-0000-0022
Leak Tests FM-8130-0000-0023
Loading Arms FM-8130-0000-0024
Metering Stations FM-8130-0000-0025
Miscellaneous Equipment FM-8130-0000-0026
Mixers FM-8130-0000-0027
Motor Operated Valves FM-8130-0000-0028
Orifice Plates FM-8130-0000-0029
Piping & Valves FM-8130-0000-0030
Plate Exchangers FM-8130-0000-0031
Positive Displacement Pumps FM-8130-0000-0032
Pressure Reducing Valves FM-8130-0000-0033
Reactors (Fixed Beds) FM-8130-0000-0034
Reciprocating Compressors FM-8130-0000-0035
Equipment Description Project Form No.
Rotary (Screw) type Compressors FM-8130-0000-0036
Safety Equipment FM-8130-0000-0037
Safety Valves FM-8130-0000-0038
832048896.doc
Page 5 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

Shell and Tube Exchangers FM-8130-0000-0039


Steam Drums FM-8130-0000-0040
Steam Tracing FM-8130-0000-0041
Steam Turbines FM-8130-0000-0042
Sumps FM-8130-0000-0043
Tanks/Silos FM-8130-0000-0044
Tight Shut-off valves FM-8130-0000-0045

832048896.doc
Page 6 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

7.0 ATTACHMENTSCHECK LISTS

832048896.doc
Page 7 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR INSTALLATION OF
AIR FIN COOLERS
SYSTEM NAME:
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Check instrumentation/


checks complete alarms

2. Platforms and ladders 10. Louvres and actuators


are fixed and clear installed correctly

3. Check that adequate 11. Vents/drains capped or


handrailing installed blanked off

4. Check oil level in gear 12. Nozzle gaskets


unit (if applicable) correct

5. Check action of 13. Fan run on test for at


autovariable hub least 8 hours

6. Belts installed (or 14. Check vibration levels


coupling lubricated and
closed)

7. Belt, coupling and fan 15. Ready for service


guards in place and secure

8. Fan checked for correct


direction of rotation
(Note. If fan run in
reverse blades may be
damaged.)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0001

832048896.doc
Page 8 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR INSTALLATION OF
BASINS
SYSTEM NAME:
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Instrumentation
checks complete & alarms checked

2. Access ladders installed 10. Check lifebelts are


installed

3. Guard rails fitted 11. Check pump operation

4. Check that adequate 12. Check skim arms


handrailing installed are operable

5. Check basin clean 13. Ready for service

6. Check all basin piping

7. Weir settings checked

8. Check mixers
(If applicable)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0002

832048896.doc
Page 9 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR INSTALLATION OF
BUILDINGS
SYSTEM NAME:
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Telephone systems


checks complete operational

2. Lighting & power 11. Radio systems


systems operational operational

3. UPS system operating 12. Door keys available


(and spares)

4. Fire protection/fighting 13. Equipment installation


systems complete/tested complete

5. HVAC operating 14. Signs in place

6. Potable water
available

7. Sewage sytem
commissioned

8. Toilets/showers
operable

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0003

832048896.doc
Page 10 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR INSTALLATION OF
BURNER SYSTEMS
SYSTEM NAME:
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Burner piping checked 10. Fuel gas lines leak tested


against PEFS

2. Burner valves correctly 11. Fuel oil lines leak tested


located beside inspection
ports

3. Steam piping checked for 12. Air louvres operable


no pockets, proper
trapping etc.

4. Piping insulation complete 13. Gaskets correct

5. Burner aligment and 14. Fuel oil line tracing


orientation checked commissioned

6. Burner guns easily 15. Atomising steam available/


removable commissioned

7. Burner cleaning area 16. Fuel oil/gas & pilot gas


& equipment available available

8. Fuel lines blown with 17. Atomising steam


steam or air differential controller
set up

9. Fuel gas lines purged 18. Instrumentation checks


complete

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0004

832048896.doc
Page 11 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
CENTRIFUGAL COMPRESSORS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 10. Cooling water available


checks complete

2. Check lubrication system 11. Instruments installed,


ready calibrated & ready

3. Check seal oil/gas 12. Data monitoring system


available ready (RDAS)

4. Check seal leak gas 13. Anti-surge system


routed to save location ready

5. Nozzle gaskets correct 14. Lubricant schedule


available

6. Compressor turns freely 15. Compressor wash system


tested & ready
(if applicable)

7. Operation of manual 16. Noise hood fitted and


valves satisfactory ventilation checked

8. Associated blinds swung 17. Run in on air/nitrogen


to operating position (Note 1)

9. Suction strainer installed


Note 1. Check with Supplier's
Instructions beforehand

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0005

832048896.doc
Page 12 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
CENTRIFUGAL PUMPS
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date

1. Construction QA 11. Seal pot fluid at


checks complete correct level

2. Check lubricator(s) 12. Fire protection


fitted & oil level correct tested functional

3. Gland and/or seal 13. Data monitoring


flushes lined up system ready(RDAS)

4. Pump turned by hand & 14. Remote start/stop


coupling guard refitted checked

5. Gaskets correct 15. Autostart/stop


function checked

6. Operation of manual 16. Cooling water


valves satisfactory available

7. Associated blinds swung 17. Lubricant schedule


to operating position available

8. Suction strainer installed 18. Run in on water


(Note 1)

9. Low point drains/ high Note 1.


point vents fitted Check with Supplier's instructions beforehand

10. Instruments installed

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0006

832048896.doc
Page 13 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
COLUMNS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Internally clean &


checks complete downcomers clear

2. Check ladders & platforms 10. Nozzle gaskets


correctly installed checked

3. Manways/inspection 13. Earthing strap


openings accessible connected

4. Manway davits operable 14. Vent and drain


properly connected

5. Safety valves installed 15. Distributor patterns


checked on water

6. Pressure gauges installed 16. Box-up certificate


and visible signed

7. Level instruments 17. Leak tested


correctly located

8. Painting/Insulation 18. Vessel verified by


complete Ops & Technology

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0007

832048896.doc
Page 14 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING SYSTEM No:
CHECK LIST FOR
CONTROL VALVES
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Failure action correct

3. Stroked O.K.

4. Tagged correctly
(Red tag as necessary)

5. Solenoid action correct


(if applicable)

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Failure action correct

3. Stroked O.K.

4. Tagged correctly
(Red tag as necessary)

5. Solenoid function correct


(if applicable)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0008

832048896.doc
Page 15 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
DESUPERHEATERS
SYSTEM NAME:
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Flow direction of
injection is correct

3. Piping straight length


requirements checked

4. Gaskets and bolts


checked

5. Failure action correct

6. Stroked O.K.

7. Insulation complete on
associated piping

8. Ready for service

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0009

832048896.doc
Page 16 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


DIESEL ENGINES
SYSTEM NAME:
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Manufacturer's
instructionsavailable

3. Fuel system lined up


and ready for use

4. Correct gaskets
fitted

5. Check that cooling water


is correctly lined up

6. Check that cooling water


is filled/vented

7. Check battery condition


if electrical starter

8. Check piping line up and


receiver pressure if air start

9. Verify oil level in sump


is correct

10. Barring gear operates


correctly (if applicable)

11. Check lubrication oil level


gauge is visible & functional

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0010

832048896.doc
Page 17 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
DRUMS
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date


1. Construction QA
checks complete

2. Internals correctly
installed

3. Nozzles and inlet/outlet


piping clear

4. Ladders and platforms


correctly installed

5. Internal coating/cladding
applied (if applicable)

6. Safety valves installed

7. Instruments installed
correctly & accessible

8. Nozzle gaskets correct

9. Vent/drain and instrument


isolation valves operable

10. Internally clean and


boxed up

11. Vessel verified by


Ops & Technology

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0011

832048896.doc
Page 18 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


DRYERS (FIXED BED)
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Dessicant support
grid correctly installed

3. Dessicant loaded to
suppliers requirements

4. Check correct gaskets


installed

5. Dryer isolation valves


access

6. Vents and drains properly


connected

7. Safety valves installed

8. Instruments installed
correctly & accessible

9. Dryer leak tested

10. Painting/insulation
complete

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0012

832048896.doc
Page 19 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


EJ ECTORS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Vacuum test


checks complete conducted

2. Check that valves, 10. Ready for service


instruments accessible.

3. All instruments installed.

4. All piping flushed and


ejector nozzles clean

5. Steam supply available.

6. Leak test process part of


system.

7. Steam strainer(s)
installed.

8. Cooling water available


and lined up

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0013

832048896.doc
Page 20 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


ELECTRICAL TRACING
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).

Line Nos.

Sign & Date Sign & Date Sign & Date


1. Construction QA
checks complete

2. Check circuit no. ID on


distribution panel

3. Check if secured to pipeing


/equipment correctly

4. Check tracing for damage

5. Check clearance around


flnges & spools

Line Nos.

Sign & Date Sign & Date Sign & Date


1. Construction QA
checks complete

2. Check circuit no. ID on


distribution panel

3. Check if secured to pipeing


/equipment correctly

4. Check tracing for damage

5. Check clearance around


flnges & spools

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0014

832048896.doc
Page 21 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


EXTRUDERS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Any additional manufacturers checks


List
Sign & Date Sign & Date

1. Construction QA 8.
checks complete

2. Check all lubricant 9.


levels are correct

3. Check that cooling 10.


system is ready for use

4. Check that safety valves


are installed and set

5. Check internals for


cleanliness

6. Check that safety devices


have been function tested

7. All instruments installed.

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0015

832048896.doc
Page 22 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


FANS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Air filtration system


checks complete correct

2. Check fan and driver for 10. Fan casing drained


freedom of rotation

3. Coupling guard in place 11. Inlet Guide Vanes set


and secured correctly & operable

4. Gear unit oil level 12. Outlet damper


checked(if applicable) operates correctly

5. Fan & driver oil levels 13. Fan test run for 4 hr
checked

6. All controls, protective 14. Electrical load


devives and auxiliary Vibration levels
systems correct Bearing temperatures
satisfactory
7. Steam supply available.
(if applicable)

8. Cooling water available


and lined up

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0016

832048896.doc
Page 23 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
FILTERS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Spare filter elements


checks complete available

2. Filter cover fitted 10. Ready for service

3. Lifting device for cover


(if required)

4. Installed in direction
of flow

5. Drain/vent valves &


associated piping fitted

6. Filter element(s) installed

7. Correct gaskets installed

8. Leak test

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0017

832048896.doc
Page 24 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
FIRED HEATERS/BOILERS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Ducting and air preheater


checks complete checked

2. Check against supplier's 10. Clearances for thermal


drawings expansion checked

3. Ladders, platforms and 11. Skin thermocouples and all


stairways checked instruments installed &
calibrated

4. Damper cable checked and 12. Final check on tube


indicator checked against supports and guides
actual position

5. Damper operation checked 13. Sootblowers aligned,


cleaned and lubricated,
steam/drain piping correct

6. Refractory sound and 14. Refractory dried out


correct thickness

7. Expansion joints per 15. Refractory inspected


drawing

8. All debris and foreign 16. Refractory repairs


materials removed complete, scaffolding
removed

Note: See also checklists for Burners (FM-8130-0000-0004)


Fans (FM-8130-0000-0016)
Steam Drums (FM-8130-0000-0040)
AS APPLICABLE
Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0018

832048896.doc
Page 25 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST
FOR FLARES
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

1. FLARE TIP 2. FLAME FRONT GENERATOR PANEL


Sign & Date Sign & Date

1.1 Construction QA 2.1 Nameplate data correct


checks complete

1.2 Ladder and platforms 2.2 Visual inspection of


installed and complete gauge glass

1.3 Check dispersion steam 2.3 Hand valves operable


nozzles

1.4 Check steam lines 2.4 Blow out piping


complete

1.5 Steam lines blown clear 2.5 Pipe leak tested

1.6 Instrumentation ready 2.6 Air and gas filters clean


for operation

1.7 Warning lights in 2.7 Power energised from


operation control panel

2.8 Check air flow through


each flame front
generator pipe
2.9 Igniter operation
checked

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0019

832048896.doc
Page 26 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No.
FOR
FUNCTIONAL TRIP TESTS
SYSTEM NAME:
PEFS/Drwg No(s).
CHECKED AND WITNESSED BY
TAG NUMBER(s) TEST OBJ ECTIVE & DESCRIPTION (Sign & Date)
(Provide Attachments as necessary) BSF CLIENT

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0020

832048896.doc
Page 27 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


GAS TURBINES
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 10. Inlet air system


checks complete checked and ready

2. Check cooling system is 10. HRSG ready to


flushed, filled & receive exhaust gas
ready for use

3. Check lube oil system is 10. HRSG outlet damper


flushed, filled & open
ready for use

4. Check hydraulic system 10. Initial run complete


clean & ready for use (non-fired)

5. Check liquid fuel system is 11. Motoring run complete


flushed and clean (Liquid fuel)

6. Check gaseous fuel system 12. Data monitoring


is flushed and clean system ready(RDAS)

Any additional manufacturers checks


7. Pre-start function checks List
complete

13.
8. Water wash system ready
for operation

14.
9. Check fire protection
system is ready

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0021

832048896.doc
Page 28 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:

FOR INSTALLATION OF
INSTRUMENTS
SYSTEM NAME:
PEFS/Drwg No(s).

Sign & Date

1. Orifice plates and in-line


equipment correctly installed

2. Trips, overrides and alarms


set and tested

3. Check pneumatic system has


been pressurised and adjusted

4. Check electronics & electrical


systems are energised

5. Instruments have been


calibrated and adjusted

6. Check all loops have been


function tested (inc ESD's)

7. Check analysers have been


tested and calibrated

8. Check instrument impulse lines/


sealpots are filled with seal fluid

9. Check that tapping and isolation


valves are operable

10. Check purges and heat tracing


have been tested and isolated

11. Check fire and gas detection


systems are operational

12. Check functionality of


solenoid if fitted

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0022

832048896.doc
Page 29 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

LEAK TESTING SYSTEM No:


RECORD
SHEET
PEFS/Drwg No(s). Page 1 of 1
PEFS No.s (Attached)

LEAK TESTING RECORD

TEST MEDIUM TEST PRESSURE

REMARKS

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0023

832048896.doc
Page 30 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
LOADING ARMS
SYSTEM NAME:
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Hydraulic system
checked

3. Earthing checked

4. Vacuum breaker
installed

5. Quick release action


checked

6. Instruments/alarms
checked

6. Movement checks
complete

7. Counterweight
balanced

8. Gaskets & bolting


checked

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0024

832048896.doc
Page 31 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


METERING STATION
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date

1. Construction QA
checks complete

2. Check connections for


correct gaskets

3. Confirm computer/inst.
and computer/computer
interfaces tested

4. Check Vendors tests have


been performed

5. Proof test with innocent


medium

6. Check proof test witnessed


and approved by
Statutory Authority

7. Ready for service

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0025

832048896.doc
Page 32 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


MISCELLANEOUS EQUIPMENT
SYSTEM NAME:
PEFS/Drwg No(s).

EQUIPMENT TAG EQUIPMENT TYPE CHECK Sign & Date

1.

2.

3.

4.

5.

6.

7.

8.

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0026

832048896.doc
Page 33 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST
FOR MIXERS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 12. Stirrer run for 12hrs on water


checks complete at normal level
Parameters recorded
2. Coupling fitted & mixer 13. Vessel drained
moves freely

3. Coupling guard fitted 14. Vessel boxed up with


correct gaskets

4. Lube oil levels correct

5. Seal piping connected

6. Safety valve installed

7. Vents and drains properly


connected

8. Instruments installed

9. Nozzle gaskets correct

10. Manway open for test run


observations

11. Stirrer run for 2hrs with


vessel empty
Parameters recorded

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0027

832048896.doc
Page 34 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
MOTOR OPERATED VALVES
SYSTEM NAME:
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Limit/Torque switches
settings complete

2. Check open and closed


position indications

3. Valve stroked remotely


& locally

4. Check manual operation


with handwheel

5. Check interlock function


(as applicable)

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Limit/Torque switches
settings complete

2. Check open and closed


position indications

3. Valve stroked remotely


& locally

4. Check manual operation


with handwheel

5. Check interlock function


(as applicable)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0028

832048896.doc
Page 35 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST FOR SYSTEM No:


INSTALLATION OF ORIFICE PLATES
(FLOW & RESTRICTION)
SYSTEM NAME:
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Bore checked by
Inst. Dept

3. Tagged correctly
(Red tag as necessary)

4. Tag No. correct

5. Ready for service

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Bore checked by
Inst. Dept

3. Tapping valves operable

4. Tagged correctly
(Red tag as necessary)

5. Ready for service

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0029

832048896.doc
Page 36 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR INSTALLATION OF
PIPING & VALVES
SYSTEM NAME:
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 13. Correct bolts & gaskets fitted


checks complete Bolts lubricated

2. All pipe supports have been 14. Hydraulic, elect. pneumatic


correctly installed actuators checked

3. Spring supports have been 15. Piping free to expand


installed, set and released

4. Instrument connections are 16. Temporary strainers, filters,


properly orientated. blinds installed as required

5. Sample connections 17. Locks, car seals or


correctly installed. interlocks fitted

6. Vents and drains properly 18. Reasonable access to all


connected. equipment and valves

7. Drain & vent caps, plugs 19. Instruments correctly


or blanks fitted installed

8. All valves installed in. 20. Protective devices installed


correct direction of flow as required.

9. All valve handles checked 21. Painting / insulation


for full turn/stroke completed as required

10. Valve handwheel bearings, 22. Earthing (if required)


and spindles lubricated connected and tested.

11. Valve gearboxes lubricated 23. Steam/electrical tracing is


(if applicable) complete where required.

12. Valve gland follower 24. Identification signage


nuts adjusted correctly applied (as applicable)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0030

832048896.doc
Page 37 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
PLATE EXCHANGERS
SYSTEM NAME:
PEFS/Drwg No(s).

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Inlet/outlet nozzles piped


correctly

3. Check earthing connected

4. Check vents and drains


installed

5. Check piping orientation


is correct

6. Temporary strainers
installed (as applicable)

7. Check gaskets
are correct

8. Check tightening bolts


are covered with root
preventer and sleeves

9. Plate depth measurement


recorded (Note here)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0031

832048896.doc
Page 38 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR
POSITIVE DISPLACEMENT PUMPS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 12. Instruments installed


checks complete

2. Coupling fitted 13. Run in on water


(if applicable)

3. Coupling guard fitted 14. Check action of capacity


adjustment

4. Lube oil levels correct 15. Stroke/volume


calibration plot provided

5. Lubricator fitted

6. Safety valve installed

7. Pulsation dampener
installed on discharge

8. Suction stainer installed

9. Pump suction and discharge


valves operable

10. Associated blinds swung


to operating position

11. Vents and drains properly


connected

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0032

832048896.doc
Page 39 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING SYSTEM No:
CHECK LIST FOR
PRESSURE REDUCING VALVES
SYSTEM NAME:
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Failure action correct

3. Tag correct

4. Check set pressure

5. Ready for service

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Flow direction correct

2. Failure action correct

3. Tag correct

4. Check set pressure

5. Ready for service

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0033

832048896.doc
Page 40 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR
REACTORS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 12. Internals installed


checks complete

2. Ladders and platforms 13. Catalyst support grid


are correctly installed installed

3. Check earthing 14. Load catalyst


(Load record attached)

4. Manway davits operable 15. Verify correctness & closure


of distributors after loading

5. Pressure gauges installed 16. Check insulation


and visible (as applicable)

6. Thermowells have correct 17. Close up reactor


projection with correct gaskets

7. Instruments fitted 18. Leak test

8. Insulation complete 19. Reactor under purge


(as applicable)

9. Reactor clean inside

10. Vent and drain properly


installed

11. Suitable access for


loading/unloading catalyst

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0034

832048896.doc
Page 41 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST FOR
RECIPROCATING COMPRESSORS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 11. Lube oil system lined up


checks complete and levels correct

2. Coupling and guard fitted 12. Relief valves set and


installed

3. Pipe supports fitted and 13. Suction and discharge


properly secured piping drained

4. Suction and discharge 14. Instruments installed


block valves accessible & calibrated. RDAS
available

5. Associated blinds swung 15. All machine trips


to operating position functionally tested

6. All vents and drains 16. Suction valve loaders


correctly routed. checked

7. Crankcase vents and 17. Leak tested on


drains clear innocent fluid

9. Suction strainer(s) 18. Lubricant schedule


installed available

10. Cooling system filled & 19. Machine run on load


commissioned on innocent for fluid
for 4hrs
(Supplier to advise)
Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0035

832048896.doc
Page 42 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


ROTARY TYPE COMPRESSORS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 9. Instruments installed


checks complete & calibrated

2. Suction line cleanliness 10. Data monitoring


verified system ready(RDAS)

3. Suction strainer installed 11. Anti-surge system


ready

4. Compressor turns freely 12. Associated blinds swung


to operating position

5. Check lubrication system 13. Run in on air/nitrogen


ready, levels correct (Note 1)

6. Check seal oil/gas 14. Bearing temperatures


available checked

7. Operation of manual valves 15. Vibration levels


satisfactory checked

8. Cooling water available Lubricant schedule


and lined up available

Note 1. Check with Supplier's


Instructions beforehand

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0036

832048896.doc
Page 43 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST UNIT No:
FOR INSTALLATION OF
SAFETY EQUIPMENT
UNIT/AREA:
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Central Fire Call Points 10. Escape Routes posted


identified

2. Emergency Shutdown 11. Fire Extinguishers


Buttons identified located properly

3. Stretchers 12. Fireman's Cabinet


inventory complete

4. Eye Bath available 13. Steam Hoses/Lances


in place

5. Safety Showers 14. Foam Systems ready


operational

6. First Aid Kit available 15. Fire Alarm tested

7. Breathing Apparatus 16. Fire spray syatems


in place tested

8. Safety Signs in place & 17. Assembly areas


equipment tagged identified

9. Life Buoys installed 18. Wind socks installed


(as applicable) (as applicable)

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0037

832048896.doc
Page 44 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:


CHECK LIST
SAFETY VALVES
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Valve calibrated to
correct set pressure

2. Valve tagged correctly


& seal intact

3. Bolting & gaskets


correct, gag removed

4. Bonnet vent pipe


fitted (balanced type only)

5. Locking devices fitted


to isolation valves correctly

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Valve calibrated to
correct set pressure

2. Valve tagged correctly


& seal intact

3. Bolting & gaskets


correct, gag removed

4. Bonnet vent pipe


fitted (balanced type only)

5. Locking devices fitted


to isolation valves correctly

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0038

832048896.doc
Page 45 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING SYSTEM No:

CHECK LIST FOR


SHELL AND TUBE EXCHANGERS
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Inlet/outlet nozzles piped


correctly

3. Check expansion slots on


sliding feet

4. Sliding end plates


installed and lubricated

5. Check earthing connected

6. Adequate clearance for


bundle removal

7. Lifting beams and davits


provided (as required)

8. Thermowells fitted

9. Thermal safety valves


fitted

10. Painting/insulation
complete

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0039

832048896.doc
Page 46 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR INSTALLATION OF
STEAM DRUMS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 11. Inspected after boil out


checks complete

2. Check ladders & platforms 12. Internals correctly


correctly installed installed (after boil out)

3. Start-up vents fitted and 13. Close up drum with correct


easily accessible gaskets

4. All blowdown valves easily 14. All chemical dosing


accessible facilities commissioned

5. Check room for expansion 15. Level alarms functionally


in drum supports tested

6. Manways/inspection 16. Level instruments fitted,


openings accessible and ready for use

7. Manway davits operable

8. Safety valves installed

9. Pressure gauges installed


and visible

10. Blowdown system


commissioned

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0040

832048896.doc
Page 47 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:

FOR
STEAM TURBINES
SYSTEM NAME:
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Steam line blown out and


clean

3. Cooling water correctly


piped up and commissioned

4. All vents and drains


correctly routed

5. Governor and overspeed


trip finally adjusted

6. Lube oil system complete


and clean

7. Relief valve fitted

8. Instruments installed

9. Seal steam system


ready (if applicable)

10. All machine trips


functionally tested

11. Machine tested on load

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0041

832048896.doc
Page 48 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR
STEAM TRACING
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).

Line Nos.

Sign & Date Sign & Date Sign & Date

1 Check header valves are


tagged correctly

2 Check if secured to piping/


equipment correctly

3. Check for damage


(e.g. crushing or pinching)

4. If spacers are used, check


material and gap

5. Check steam traps/NRV


in correct orientation and
flow position

Line Nos.

Sign & Date Sign & Date Sign & Date


1 Check header valves are
tagged correctly

2 Check if secured to piping/


equipment correctly

3. Check for damage


(e.g. crushing or pinching)

4. If spacers are used, check


material and gap

5. Check steam traps/NRV


in correct orientation and
flow position
Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0042

832048896.doc
Page 49 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF

COMMISSIONING CHECK LIST SYSTEM No:


FOR
STRAINERS
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date

1. Construction QA
checks complete

2. Check correct strainer


mesh is fitted

3. Check mesh is secured to


support mesh

4. Pressure instruments
fitted

5. Vent/drain valves and


piping correct

6. Closure seals/gaskets
correct

7. Boxed up/ready
for service

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0043

832048896.doc
Page 50 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR INSTALLATION OF
TANKS & SILOS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).

Sign & Date Sign & Date

1. Construction QA 12. Pressure/vacuum safety


checks complete valves fitted

2. Ladders and platforms 13. Tank calibrated


correctly installed

3. Earthing connected and 14. Close up tank


tested

4. Manways/inspection 15. Painting/Insulation


openings accessible complete

5. Manway davits operable 16. Check operation of floating


(if applicable) roof (as applicable)

6. Gaskets and bolting 17. Blinds in correct


correct position for operation?

7. Internally mounted level 18. Tank fire protection


floats free present and functional?

8. All instruments fitted 19. Identification signage


and ready for use applied (as applicable)

9. All valves free to 20. Anti-skid coating


operate applied at tank roof

10. Internal lining or


painting applied

11. Tank clean and all


drains & nozzles clear

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0044

832048896.doc
Page 51 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING SYSTEM No:
CHECK LIST FOR
TIGHT SHUT-OFF VALVES
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s). ITEM Nos.

ITEM Nos.

Sign & Date Sign & Date Sign & Date


1. Flow direction correct
(pressure sealing)

2. Valve has been


tightness tested

3. Stroked O.K.
Stroke time O.K.

4. Tag correct

5. Limit switches operate

ITEM Nos.

Sign & Date Sign & Date Sign & Date


1. Flow direction correct
(pressure sealing)

2. Valve has been


tightness tested

3. Stroked O.K.
Stroke time O.K.

4. Tag correct

5. Limit switches operate

Contractor Commissioning BSF Commissioning CSPC

Sign: Date Sign: Date Sign: Date

Name (Print) Name (Print) Name (Print)

Form No. FM-8130-0000-0045

832048896.doc
Page 52 of 52