PI-8130-0000-0009
PI-8130-0000-0009
Document #: PI-8130-0000-0009
Current Revision #: 00
Description of Change:
The following changes were made:
Buildings and TSO valve checklist added please rReference document check
list index revised.
General comments incorporated.
.
Applicability:
This document applies to:
Note: This document is intended for guidance regarding the minimum level of
commissioning checks per item of equipment.
832048896.doc
Page 2 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
TABLE OF CONTENTS
No. Page
1.0 SCOPE 34
2.0 PURPOSE 34
3.0 DEFINITIONS 34
4.0 RESPONSIBILITIES 34
5.0 REFERENCES 34
832048896.doc
Page 3 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
1.0 SCOPE
2.0 PURPOSE
3.0 DEFINITION
Commissioning checklistscheck lists Check lists are the forms that describe the
final checks made on equipment by the responsible Commissioning group
immediately prior to putting that equipment into service. These checks are
conducted after receipt of notification of Mechanical Completion from the
Contractor’s Construction group for the item of equipment concerned. The
completed checklistscheck lists form part of the final Systems Handover
DossierCompletion Manual for the system System containing the equipment in
question.
4.0 RESPONSIBILITIES
Specialised pieces of equipment not listed in this Instruction shall have dedicated
check lists prepared, the content of which shall be approved by PMT/CSPC.
5.0 REFERENCES
832048896.doc
Page 4 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 6 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 7 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR INSTALLATION OF
AIR FIN COOLERS
SYSTEM NAME:
PEFS/Drwg No(s).
832048896.doc
Page 8 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
1. Construction QA 9. Instrumentation
checks complete & alarms checked
8. Check mixers
(If applicable)
832048896.doc
Page 9 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR INSTALLATION OF
BUILDINGS
SYSTEM NAME:
PEFS/Drwg No(s).
6. Potable water
available
7. Sewage sytem
commissioned
8. Toilets/showers
operable
832048896.doc
Page 10 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 11 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 12 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
832048896.doc
Page 13 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 14 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING SYSTEM No:
CHECK LIST FOR
CONTROL VALVES
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s).
ITEM Nos.
3. Stroked O.K.
4. Tagged correctly
(Red tag as necessary)
3. Stroked O.K.
4. Tagged correctly
(Red tag as necessary)
832048896.doc
Page 15 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
2. Flow direction of
injection is correct
6. Stroked O.K.
7. Insulation complete on
associated piping
832048896.doc
Page 16 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Construction QA
checks complete
2. Manufacturer's
instructionsavailable
4. Correct gaskets
fitted
832048896.doc
Page 17 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
2. Internals correctly
installed
5. Internal coating/cladding
applied (if applicable)
7. Instruments installed
correctly & accessible
832048896.doc
Page 18 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Construction QA
checks complete
2. Dessicant support
grid correctly installed
3. Dessicant loaded to
suppliers requirements
8. Instruments installed
correctly & accessible
10. Painting/insulation
complete
832048896.doc
Page 19 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
7. Steam strainer(s)
installed.
832048896.doc
Page 20 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
Line Nos.
Line Nos.
832048896.doc
Page 21 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
1. Construction QA 8.
checks complete
832048896.doc
Page 22 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
5. Fan & driver oil levels 13. Fan test run for 4 hr
checked
832048896.doc
Page 23 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
4. Installed in direction
of flow
8. Leak test
832048896.doc
Page 24 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 25 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
CHECK LIST
FOR FLARES
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).
832048896.doc
Page 26 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No.
FOR
FUNCTIONAL TRIP TESTS
SYSTEM NAME:
PEFS/Drwg No(s).
CHECKED AND WITNESSED BY
TAG NUMBER(s) TEST OBJ ECTIVE & DESCRIPTION (Sign & Date)
(Provide Attachments as necessary) BSF CLIENT
832048896.doc
Page 27 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
13.
8. Water wash system ready
for operation
14.
9. Check fire protection
system is ready
832048896.doc
Page 28 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
FOR INSTALLATION OF
INSTRUMENTS
SYSTEM NAME:
PEFS/Drwg No(s).
832048896.doc
Page 29 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
REMARKS
832048896.doc
Page 30 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Construction QA
checks complete
2. Hydraulic system
checked
3. Earthing checked
4. Vacuum breaker
installed
6. Instruments/alarms
checked
6. Movement checks
complete
7. Counterweight
balanced
832048896.doc
Page 31 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
1. Construction QA
checks complete
3. Confirm computer/inst.
and computer/computer
interfaces tested
832048896.doc
Page 32 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
1.
2.
3.
4.
5.
6.
7.
8.
832048896.doc
Page 33 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
8. Instruments installed
832048896.doc
Page 34 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Limit/Torque switches
settings complete
ITEM Nos.
1. Limit/Torque switches
settings complete
832048896.doc
Page 35 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
2. Bore checked by
Inst. Dept
3. Tagged correctly
(Red tag as necessary)
ITEM Nos.
2. Bore checked by
Inst. Dept
4. Tagged correctly
(Red tag as necessary)
832048896.doc
Page 36 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 37 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Construction QA
checks complete
6. Temporary strainers
installed (as applicable)
7. Check gaskets
are correct
832048896.doc
Page 38 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR
POSITIVE DISPLACEMENT PUMPS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).
5. Lubricator fitted
7. Pulsation dampener
installed on discharge
832048896.doc
Page 39 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING SYSTEM No:
CHECK LIST FOR
PRESSURE REDUCING VALVES
SYSTEM NAME:
PEFS/Drwg No(s). ITEM Nos.
ITEM Nos.
3. Tag correct
ITEM Nos.
3. Tag correct
832048896.doc
Page 40 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 41 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 42 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 43 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST UNIT No:
FOR INSTALLATION OF
SAFETY EQUIPMENT
UNIT/AREA:
PEFS/Drwg No(s).
832048896.doc
Page 44 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Valve calibrated to
correct set pressure
ITEM Nos.
1. Valve calibrated to
correct set pressure
832048896.doc
Page 45 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Construction QA
checks complete
8. Thermowells fitted
10. Painting/insulation
complete
832048896.doc
Page 46 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
832048896.doc
Page 47 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
FOR
STEAM TURBINES
SYSTEM NAME:
PEFS/Drwg No(s). ITEM Nos.
ITEM Nos.
1. Construction QA
checks complete
8. Instruments installed
832048896.doc
Page 48 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
Line Nos.
Line Nos.
832048896.doc
Page 49 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
ITEM Nos.
1. Construction QA
checks complete
4. Pressure instruments
fitted
6. Closure seals/gaskets
correct
7. Boxed up/ready
for service
832048896.doc
Page 50 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING CHECK LIST SYSTEM No:
FOR INSTALLATION OF
TANKS & SILOS
SYSTEM NAME: ITEM No.
PEFS/Drwg No(s).
832048896.doc
Page 51 of 52
CSPC Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler BSF
COMMISSIONING SYSTEM No:
CHECK LIST FOR
TIGHT SHUT-OFF VALVES
SYSTEM NAME: Page 1 of 1
PEFS/Drwg No(s). ITEM Nos.
ITEM Nos.
3. Stroked O.K.
Stroke time O.K.
4. Tag correct
ITEM Nos.
3. Stroked O.K.
Stroke time O.K.
4. Tag correct
832048896.doc
Page 52 of 52