SP-8230-0000-0003
SP-8230-0000-0003
TABLE OF CONTENTS
Page
No.
1.0 SCOPE 3
2.0 PURPOSE 3
3.0 DEFINITIONS 3
4.0 RESPONSIBILITIES 5
5.0 INSTRUCTIONS 5
5.5 Tankage
6.0 REFERENCES 44
7.0 ATTACHMENTS 45
1.0 SCOPE.
This project specification covers the spacing requirements to be used for the
layout of plant and equipment on all Onsite and Offsite Units / Areas. The 0
2.0 PURPOSE.
The purpose of the specification is to specify the requirements and practices for
the spacing of equipment and facilities on the CSPC Nanhai Petrochemical
Project. 0
1
The basis of this specification is the PRC Codes, International Standards, DEP
requirements and current industry practices. In the case of conflict, PRC
codes are to be consulted.
3.0 DEFINITIONS.
The following definitions are used throughout the specification.
3.3.1 Electrical.
Sparks or arcs may occur when current carrying contacts are separated
or through static electricity discharge.
3.3.2 Naked Lights.
E.g. fired heaters, fires, smoking, hot work, gas welding, etc.
3.3.3 Internal Combustion Engines (IC)
Spark-ignition systems and exhaust hot spots.
3.3.4 Spontaneous Combustion.
Pyrophoric materials and vapour leakage at temperatures above AIT.
3.3.5 Frictional Ignition.
Grit blasting, power tool grinding, mechanical failure of rotating
machinery.
3.4.1 The fire hazard of combustible gas shall be classified based on table
3.4.1.
4.0 RESPONSIBILITIES.
SP-8230-0000-0003 Rev 01 Page 4 of 47
Specification for Equipment Spacing.
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
4.1 The Plant Layout Engineer(s), reporting to the Engineering Manager, will
assume specific responsibility for developing the project plot plan(s).
4.2 The divisions of responsibilities for the development of the overall plot
plan and individual process unit plot plans shall be agreed by BSF. All 0
1
plot plans developed shall be the subject of formal plot plan reviews.
5.0 INSTRUCTIONS
5.1.3 Other factors may require an equipment spacing greater than the
recommended. In this case consideration should be given to:
SP-8230-0000-0003 Rev 01 Page 5 of 47
Specification for Equipment Spacing.
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
0
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
22 Ia Classification
22 Grade.
15 Ib IIa
7.5 IIb IIIa
7.5 All
Grades
FIRE TRAINING
FUTURE
TANKAGE
TANKAGE
TANKAGE
BLOCK-
BLOCK-
PRODUCT
PRODUCT
STORAGE
STORAGE
ELEVATED
ELEVATED PROCES
PIPERACK
PIPERACK S UNITS
LPG
LPG
SPHERES
SPHERES
ADMIN
BLDG.
FUTURE EXPANSION
FUTURE PROCESS UNITS
GATE REFINERY
REFINERY PROCESS
PROCESS
GATE
HOUSE BOUNDARY
BOUNDARY BLOCK
BLOCK
HOUSE
FENCE
FENCE LINE
LINE
Fig 2 shows a process block divided into areas and a process area divided
into units. Also shown are the dimensions of the unit safety clearances
required.
0
1
Fig. 3 shows the basic spacing between bunded areas for a TANKAGE
BLOCK.
(1)30m
(1) Distances are from the outside of the bottom of the bund walls, for tanks
containing flammable liquid. 0
1
(2) Distances are from tank shell to tank shell, for tanks containing liquefied
hydrocarbon.
The spacing between two similar items is given in the first box adjacent to
the item. Note that basic spacing is not required between items in the
same service.
The basic spacing of 1.5 metres provides access for operation and
maintenance. The distance between two towers is twice the basic
dimension. This provides some additional access for fire fighting and
clearance for non-coincidental access platforms.
The basic spacing of 4.5 metres provides access for fire fighting and
minimises damage to other equipment. The external insulation protects
the reactor shell from fires on other equipment.
Spacing from Ref. RF1 is in excess of the greater basic dimension as the
Reactor is regarded as high-risk equipment.
Since the Reactor is operating above AIT, other sources of ignition are
not a spacing consideration and basic reactor spacing of 4.5 metres will
apply (e.g. items Ref. RJ1 and R01).
The basic spacing of 7.5 metres provides access for fire fighting,
minimises damage to other equipment in event of reactor fire, and
protects exposed shell.
Spacing from RF1 is in excess of the reactor after basic dimension as the
reactor is regarded as high-risk equipment.
Since the reactor is operating above AIT, other sources of ignition are not
a spacing consideration basic reactor spacing of 7.5 metres will apply
(e.g. items R01).
Spacing from Refs. RP1, RT1, RU1. These items are not regarded as fire
hazardous – the spacing of 4.5 metres will give these items protection in
the event of reactor fires.
5.3.6 Ref. RE1 On-site Pressure Storage Vessels - Grade Ia (ref table 3.4.2),
containing less than 100m3. 0
1
(Basic Spacing 9 metres)
If the individual volume of a Grade Ia tank (ref table 3.4.2) is less than 0
The basic spacing of 7.5 metres provides protection to the Drum in the
event of fire within the unit.
Spacing from Ref. RU1 – piperacks are not regarded as fire hazardous –
spacing of 4.5 metres affords protection to the pipe rack in the event of
blow-down drum fire.
Spacing from RN1-as the fluid in the exchangers is above its AIT, a gas
compressor and expanders are considered likely to be more critical than
other equipment. Therefore spacing greater than basic is applied to
minimise damage to the exchanger.
Spacing from ref. RP1 protects equipment from a high fire risk system.
The basic spacing of 1.5 metres provides access for maintenance and
operation. There are no limitations on spacing exchangers from
piperacks – exchanger spacing applies.
Air fin coolers by virtue of their design and operations are particularly
vulnerable to fire hazard.
(a) Air fin coolers shall not be mounted over pumps, compressors, drums
or heat exchangers, containing flammable materials.
(b) There shall not be any flanges or valves in piping systems containing
0
hydrocarbons, on the piperack beneath an air fin cooler. 1
gas. 1
The distance between the outer shell of a fired heater and the edge of
maintenance access area should not be less than 3 metres.
The distance between a fired heater and its associated equipment, for
example fuel gas knock out drum or heat exchanger, should not be less
than 6 metres.
Where such restrictions are not applied, the heater location should be
selected on the downwind side of the minimum frequency wind direction
of equipment handling flammable gas, liquefied hydrocarbon, flammable
liquid Grade Ib (ref GB50160-92 section 4.2.14), close to the Unit limit
0
and as far as practicable from other equipment. Consideration shall also 1
be given to the proximity of plant and equipment outside the unit battery
limit.
When the heater has an individual stack, the top of the stack should be at
least 3 metres higher than equipment within a horizontal distance of 15
metres and at least 3.5 metres higher than any operating platform or the
top of building within a horizontal distance of 20 metres and 10 metres for
intermittent discharging stack.
Refs. RB1, RC1, RG1, RL1 are items operating above their AIT and in
these cases the fired heater is not considered to be the primary source of
ignition, spacing is based on affording protection in the event of heater
fire.
Ref. RP1 – a spacing of 4.5 metres minimises damage in the event of the
heater fire. For equipment higher than 3 metres, spacing should be
increased to 7.5 metres from heaters with liquid in their tubes. Reduced
spacing is permitted because there is no flammable material release in
the event of damage.
Pumps operating above AIT are a high fire risk. Basic spacing of 4.5
metres provides fire-fighting access and minimises damage to other
equipment.
Ref. RF1 – because of the high fire risk, spacing greater than basic
should be provided from this item.
Ref. RJ1 – the fired heater is not considered a source of ignition in this
case. Spacing of 4.5 metres is provided between two high-risk items.
Ref. RL1 – pumps in the same service may be spaced at 1.5 metres min
distance.
5.3.15 Ref. RN1 Gas Compressor and Expanders handling Grade I Gas (ref 0
Ref. RF1 and RJ1 - spacing greater than basic is provided because of the
high-risk nature of these items.
For items RB1, RC1, RG1, and RL1 that operate above AIT, the driver is
not considered to be the primary source of ignition. The basic spacing for
these items therefore applies.
Ref. RJ1 – spacing of 7.5 metres protects driver in event of heater fire.
Ref. RU1 – the piperack is not a hazard – piperack basic spacing applies.
5.3.18 Ref. RQ1 Central Control Building (ref GB50160-92, table 4.2.1 and DEP
43.17.10.30). 0
1
5.3.19 Ref. RR1 Field Auxiliary Room (Unit Control House) - (ref GB50160-92, 0
table 4.2.1 and DEP 43.17.10.30) 1
The location of a FAR (Unit Control House) is less critical than a Central
Control Building. It should be located at the Unit (battery) limit adjacent to
a roadway. Basic spacing minimises risk to personnel and equipment in
the event of a Unit fire.
Ref. RU1 – piperack basic spacing applies provided piping systems are
fully welded without valves or flanges.
Electrical Sub-Stations are located close to the Unit (battery) limit and
near to a roadway. The basic spacing is fixed by Area Classification
considerations and provides protection to the electrical equipment in the
event of a Unit fire.
Piperack basic spacing gives protection to the pipe rack in the event of
equipment fires within a process unit. Items Ref. RB1, RC1, RE1, RG1,
RN1 and R01 are located on this basis.
Item Ref. RJ1 – fired heater is a possible source of a major fire. Spacing
greater than basic is required in this case (n.b. This limitation does not
apply to the piperack serving the heater area).
In special cases where the hazard from the piperack must be minimised,
fittings and flanges that could be sources of leakage must be eliminated
from the piperack in the vicinity (e.g. piperacks under air fin exchangers
and piperacks in the vicinity of control houses - ref. items RI1, RQ1 and
RR1).
Pumps are also considered as a special case as, for layout purposes,
access and operability, it is usual to have pumps in close proximity to the
piperack, e.g. items Ref. RL1 and RM1 – spacing is horizontal distance
from pump stuffing box to centreline of piperack columns.
5.3.23 Ref. RV1 Emergency Valves for Shut-off, Isolation, Snuffing, Unit
(battery) limit etc.
(Basic spacing 7.5 metres)
The basic spacing is the distance between the emergency valve and the
equipment it controls. The valve can be located adjacent to other
equipment (except for Unit limit valves).
0
1
Unit (battery) limit valves should be located at the edge of a Unit and on
the Unit limit side of the surrounding access roads.
Ref. RE1 and RJ1 are exceptionally hazardous items. The basic spacing
for these items applies.
5.2.24 Ref. RW1 ‘Onsite’ Combustible liquid Grade Ib / IIa (ref section 3.4.1 and
3.4.2) storage tanks and Combustible Gas Grade I storage tanks - total 0
1
inventory volume less than 1000m3.
(Basic spacing 9.0 metres)
If the volume of an individual tank is less than 100m3 for combustible
liquid and 200 m3 for combustible gas, it may be regarded as drums (see
Ref. RD1).
5.3.25 Ref. RX1 ‘Onsite’ Combustible liquid Grade IIb / IIIa (ref section 3.4.1 and 3.4.2)
storage tanks and Combustible Gas Grade II storage tanks - total tank 0
1
5.3.26 Ref. RY1 Gas Compressors and Expanders handling Combustible Gas Grade II 0
(ref section 3.4.1). 1
Facilities outside the confines of a Process Block, e.g. boiler houses and
power stations, administration offices, workshops, effluent treatment, flare
stacks, jetty and rail loading, blending facilities etc., are referred to as “off-
site facilities”.
Effluent treatment, flare and similar high hazard off-site facilities are
generally located remote from process facilities, utility areas and
administration areas.
In general, this shall be the greater of the basic spacing dimensions for
the two items, otherwise explanatory notes can be found in Section 5.4.1.
The spacing between similar equipment / facilities is given in the first box
adjacent to the item.
5.4.1 Off-site Spacing Guide (Use with off-site spacing chart Fig. 5).
Ref. RK2 – spacing protects pipe track from possible fire in boiler house.
Ref. RO2 – railway main lines are not at risk from facilities and do not
present a risk to facilities. Boiler basic spacing applies.
Ref. RP2 – rail sidings present a minimum risk to facilities. Siding basic
spacing applies.
Items Ref. RA2, RC2, RK2, RO2, RP2 are not considered high-risk items.
Spacing less than basic building space is applied.
The lower basic spacing is for equipment that is lower than the cooling
tower.
The higher basic spacing is for equipment that is taller than the cooling
tower and where it is necessary to minimise the corrosion, visibility and
ice formation problems, resulting from the impingement of the cooling
tower exhaust plume.
Items Ref. RF2, RP2, RU2, RG2 and RO2 do not present a hazard to
these cooling towers. Cooling tower basic spacing is therefore applied.
Items Ref. RJ2, RL2, RS2 and RV2 are possible sources of fire. Higher
cooling tower basic spacing is applied to these items.
Items Ref. RM2 and RO2 do not present a hazard to the cooling tower.
Cooling tower higher basic spacing is applied for environmental
considerations.
Item Ref. RK2 – the cooling tower is not considered to be at risk from the
SP-8230-0000-0003 Rev 01 Page 23 of 47
Specification for Equipment Spacing.
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
Items Ref. RN2, RP2, RQ2 are not considered as sources of hazard.
Basic spacing for these items will apply.
Items Refs. RK2, RO2, RP2 are not considered as major sources of
hazard. Spacing less than basic is allowed.
The basic spacing provides protection to the fire station and equipment in
the event of fire in the process areas.
Items Ref. RA2, RC2, RK2, RO2 and RP2 are not considered as major
sources of hazard. Spacing less than basic is allowed.
Items Ref. RB2, RE2, RG2 and RM2 are not hazardous to the fire station.
Location is determined by access and maintenance considerations.
The basic spacing provides protection to prevent loss of pumps from fire
exposure.
Items Ref. RA2, RC2, RK2, RN2, RO2 and RP2 are not considered
sources of major hazard. Spacing less than basic is allowed.
Items Ref. RB2, RE2, RF2, RU2 and RM2 are not hazardous to fire
pumps. Location is determined by access and maintenance
considerations.
5.4.10 Ref. RJ2 Road Loading Racks for Low Flash Point Products
(Basic spacing 30 metres)
Items Ref. RK2, RN2 and RU2 are not considered hazardous with
respect to the loading area. Spacing less than loading rack basic is
acceptable in these instances.
The basic spacing of 4.5 metres minimises hazard to off-site piping in the
event of fires at major plant areas.
For items Ref. RC2, RG2, RF2, RL2, RM2, RN2, RP2, RQ2, RS2, RW2
and RR2, this criterion applies.
For items Ref. RA2, RB2, RE2, RH2, RJ2 and RO2 greater spacing is
applied for commodity criticality or personnel hazard requirement.
Items Ref. RC2, RK2, RN2, RO2 and RP2 are not considered at high
hazard from process areas. The basic spacing for these items is
therefore applied.
Where several process units are integrated, the internal spacing should
be based on maintenance, operational and fire fighting access.
facilities and residential area shall not be less than 100 metres. For
adjacent factory with enclosed wall the separation shall not be less than
50 metres (ref: GB50160-92 Table 3.1.7).
Item refs. RC2 and RK2 are reduced hazard items. Spacing less than the
basic boundary spacing is acceptable in these instances.
Item refs. RB2, RE2, RF2 and RG2 are not hazardous. Spacing from
boundary fence is based on access or environmental consideration.
The basic spacing affords protection to pump areas in the event of fire or
explosion in process facilities and allows access for fire fighting.
Spacing less than basic item spacing is therefore permitted from these
items, e.g. items Ref. RD2, RJ2, RL2, RO2, RQ2, RK2, RM2, RP2, RS2,
RU2 and RV2..
The basic spacing protects personnel and railway property from fire or
explosion inside plant.
Items Ref. RA2, RC2, RJ2 and RN2 present a reduced hazard to railway
property. Spacing less than basic is permitted in these cases.
Rail sidings are railway lines in the complex for loading, unloading,
storage etc.
The spacing(s) between effluent oil tank and other facilities should be
reduced by 25%, and between effluent oil pump (or pump house) and
other facilities should be reduced by 50%.
Items Ref. RA2, RB2, RC2, RE2, RF2, RG2 and RH2 fall in this category.
Item Ref. RK2, off-site pipe tracks, is a minimum risk item. Its basic
spacing applies.
5.4.19 Ref. RS2 Rail Loading Racks for Low Flash Point Products.
(Basic spacing 35 metres).
Items Ref. RK2, RN2 and RU2 are not considered hazardous with
respect to the loading area. Spacing less than loading rack basic spacing
is acceptable in these instances.
Road for transporting raw material and products shall be located outside
areas considered as a major fire hazard.
5.5 TANKAGE.
This section gives basic guidance for the spacing and bund capacities of
storage tanks, storage spheres and cylinders.
For specific spacing direction, particularly for LPG and LNG duties,
refer to the relevant listed standard(s). P.R.C GB 50160-92, DEP
30.06.10.12 and 13-CSPC.
Other types of bulk storage, e.g. underground caverns, are not covered
by this standard.
Other grades of product may be stored in this type of tank, provided that
the vapour pressure at storage temperature is less than atmospheric 0
pressure (e.g. refrig. atmosphere storage of LPG/LNG). 1
If the boiling point of Grade Ib flammable liquid is below 450C, the liquid
shall be stored in a pressurized storage tank.
5.5.2.4 Table 1
Notes:
1. Certain produce classifications may change if operational
temperatures are increased.
5.5.3 Definitions
5.5.4.1 It is desirable to group tanks for the storage of the same or similar
products in one group within a bund area, subject to the prescribed
limitations of the bunded capacity.
5.5.4.4 Account should be taken of the possibility of storing more than one class
of material in certain tanks or of changing the tank service at some future
date. Where future changes of service of the storage tanks are
anticipated, the layout and spacing should be for the most stringent case.
5.5.4.5 Whenever possible storage tanks should not be located on high ground
overlooking the facilities. This prevents spillage of flammable liquid
flowing downhill and endangering the operating plant.
5.5.4.6 If the volume of an individual storage tank for Grade III b flammable liquid
is less than or equal to 1000m3, it is acceptable to have up to 4 rows of 0
1
5.5.4.7 Intermediate bunds may be provided to divide the tankage into groups of
a convenient size so as to contain small spillage and act as firebreaks.
If the individual tank volume is less than or equal to 5,000m 3, the total
tankage volume separated by the secondary bund shall not be more than
20,000m3.
SP-8230-0000-0003 Rev 01 Page 31 of 47
Specification for Equipment Spacing.
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
If the individual tank volume is from 5,000 to 20,000m 3, every four tanks
should be separated by a secondary bund.
If the individual tank volume is from 20,000 to 50,000m 3, every two tanks
should be separated by a secondary bund.
If the individual tank volume is more than 50,000m 3, each tank shall be
separated by a secondary bund.
The number of tanks separated by a secondary bund for the boil / rollover
liquid shall not be more than 2.
A secondary bund shall be provided between tanks for Ib, IIa liquid and
for other grades of flammable liquid.
A secondary bund shall be provided between tanks for water soluble and
for water insoluble flammable liquid.
5.5.5.1 Bund capacity shall comply with the requirements summarised below. 0
1
C.R. Tanks.
The bund capacity shall not be less than the volume of the largest
storage tank in the bund.
IFR/EFR Tanks.
The bund capacity shall not be less than 50% of the volume of the largest
storage tank in the bund.
5.5.5.2 The effective height of the bund used in calculating the capacity of the
enclosure shall be the constructed height less an amount sufficient to
allow for future consolidation, settlement and possible erosion of the fill.
This “freeboard allowance” shall be 200mm for flammable liquid vertical
storage tank. In general the height of bund shall be in the range of
1.0~2.2 m.
For horizontal storage tanks containing flammable liquid, the bund height
shall not be less than 500mm.
5.5.5.3 For liquefied hydrocarbon pressurized storage tank, the bund height
should not be higher than 600mm. Bund Walls shall generally be
constructed using earth embankments having a crest of 600mm minimum
width.
5.5.5.5 In the event that there is inadequate space for construction of earthen
bund walls due to restricted site dimensions, the use of reinforced
concrete retaining walls will be permitted.
5.5.5.6 Ethylene oxide tank shall be laid out separately form other tanks within
dedicated bund wall.
‘A’
CR ‘B’ CR
CR ‘B’ CR
DIM ‘A’ INSIDE
BOTTOM OF
‘A’ BUND
‘E’ ‘C’
Tankage Limitation.
When the individual tank capacity is greater or equal to 10,000m 3, the number of tanks in
one tank group shall not be more than 6. 0
1
When the individual tank capacity is less than 10,000m 3, the number of tanks in one tank
group shall not be more than 16.
When all the individual tank capacity is less than 1,000m 3, the number of tanks in one tank
group shall not be restricted.
The number of tanks for Grade III b flammable liquid shall not be restricted.
Spacing.
‘A’ to suit construction and operating conditions but not less than half tank shell height.
‘B’ Refer to Table 2.
‘C’ Not less than 7m
‘E’ See Table 4
Note:
The spacing between a horizontal tank and the inside bottom line of a bund wall shall not
be less than 3 metres.
SP-8230-0000-0003 Rev 01 Page 34 of 47
Specification for Equipment Spacing.
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
‘A’
CR ‘B’ CR
‘A’
‘B’ ‘B’
‘A’
‘A’
‘E’ ‘C’
Tankage Limitation
When the individual tank capacity is greater or equal to 10,000m 3, the number of tanks in one
tank group shall not be more than 12.
When the individual tank capacity is less than 10,000m 3, the number of tanks in one tank
group shall not more than 16.
When all the individual tank capacity is less than 1,000m 3, the number of tank in one tank
group shall not be restricted.
The number of tanks for Grade III b flammable liquid shall not be restricted.
Spacing
‘A’ to suit construction and operating conditions but not less than half tank shell height.
‘B’ Refer to Table 2.
‘C’ Not less than 7m
‘E’ See Table 4
Note:
The spacing between a horizontal tank and the inside bottom line of a bund wall shall not be
less than 3 metres.
Example 3 Cone Roof Tanks (CR) and Floating Roof IFR/EFR within a
Common Bund
‘A’
CR ‘B’ CR
‘B’ ‘B’
‘A’ ‘A’
FR ‘B’ FR
INSIDE BOTTOM OF
BUND
‘A’
‘E’ ‘C’
Tankage Limitation
When the individual tank capacity is greater or equal to 10,000m 3, the number of tanks
in one tank group shall not be more than 12.
When the individual tank capacity is less than 10,000m3, the number of tanks in one
tank group shall not be more than 16.
When all the individual tank capacity is less than 1,000m 3, the number of tank in one
tank group shall not be restricted.
The number of tanks for Grade III b flammable liquid shall not be restricted.
Spacing
‘A’ distance shall not be less than half height of tank shell.
‘B’ Refer to Table 2
‘C’ Not less than 7.0m
‘E’ Refer to Table 4
Note:
The spacing between a horizontal tank and the inside bottom line of a bund wall shall
not be less than 3 metres.
Notes:
1. D indicates the diameter of the greater volume of adjacent tanks. If the
individual volume is greater than 1000m3, the greater value shall be selected
between the height and diameter of the tank.
2. The greater value shall be selected from the table when adjacent tanks are
stored for different grades of flammable liquid or they are different types of
tanks.
3. The spacing for overhead tanks shall not be less than 0.6m.
4. The spacing between two rows of vertical tanks shall be in accordance with
Table 2, and shall not be less than 5.0m. The spacing between two rows of
horizontal tanks shall not be less than 3.0m.
Example 4.
Refrigerated Storage (LPG Products at low temperatures) Fixed
Roof Tanks (CR) should not more than 2 tanks in one compound.
‘A’
‘A’ CR ‘B’ CR ‘A’
A
INSIDE BOTTOM
OF BUND
‘A’
‘E’
SECONDARY BUND
Refrigerated LPG storage tank shall not be located within a bund enclosing any
other type of tank. Each refrigerated storage tank shall have an individual bund.
Spacing
‘A’ Dimension is the resultant value obtained by deducting the height of the
bund wall from the highest liquid level in the tank.
‘B’ Refer to Table 3
‘E’ See Table 4
Note:
Between the adjacent refrigerated storage area the spacing between the
adjacent tank shell shall not be less than 16m.
Grade
Liquefi of fluid
Full- Exhaust 0.5 D 1.0 D and
ed pressur to flare should not
hydroc ized be greater
arbon tank than 1.5m
Not 1.0 D
exhaust
to flare
Full refrigerated tank 0.5 D
Combustion-supporting gas 0.5 D 0.65 D and
should not
be greater
than 1.5m
Flammable Wet type gas 0.5 D
gas tank
Dry type gas 0.65 D
tank
Spherical tank 0.5 D
Notes:
1. D indicates the diameter of the greater volume of adjacent tanks.
2. The spacing between a spherical tank and a horizontal tank in one tank group
shall be selected from the greater value in the table.
3. The spacing for liquefied ammonia tanks shall be same as that for liquefied
hydrocarbon. The spacing for liquefied oxygen tanks shall be executed
complying with the relevant rules from “Code for design of building fire
protection” GBJ 16-87.
4. The spacing for a semi-refrigerated tank for liquefied hydrocarbon should be
same as the requirement of a fully-pressurized tank for liquefied hydrocarbon.
5. The spacing between two rows of adjacent horizontal tanks in one tank group
shall not be less than 3 metres.
‘D’
‘D’ ‘B’
‘D’
‘D’
BL BL BL
SP SP
Notes:
1. LPG tanks shall not be formed into groups of more than 12 tanks each.
Horizontal vessels used to store LPG should be oriented so that their
longitudinal axes do not point towards other containers, process
equipment, control rooms loading or unloading facilities, or flammable or
combustible liquid storage facilities located within the vicinity of the
horizontal vessel.
Spacing.
‘B’ Reference Table 3.
‘E’ See Table 4.
Table 4.
Maximum Tankage Spacing (Dimensions in metres - See tankage spacing
examples 1, 2, 3, 4 and 5).
Dimension ‘E’ is a dimension from facility / equipment reference line to
tank shell.
Refer to the listed Standards (IP Refinery Safety Code, Model Code of
Practice-Part 3, section 5.1.8 and PRC standard GB50169-92 section
5.2.17) for more detailed spacing requirements regarding spillage
catchment (impounding) areas and drainage. Spacing will need to be
considered for individual cases.
m
e
It
Table 4 Dimension ‘E’.
(ref; GB50160-92, table 3.2.11) 0
1
100m3< V 1000m3
500 m3< V 1000 m3
Class B 40 35 25 20 30 25 20 15 55 45 35 55
Class C 35 30 20 15 25 20 15 10 50 40 30 50
(Table 4) Notes:
The spacings are determined by the largest tank capacity adjacent to other
facilities or process area.
1. Important facilities include: central control house, boiler house and power
station, main electric substation, main office building, communication
station, air compression station fire fighting pump house, laboratories, etc.
In the event of fire within the complex, the above facilities could be
affected resulting in lost production coupled with a risk of personnel injury.
2. These spacings should be reduced by 25% for Class III flammable liquid.
4. These items can be used for the storage of flammable gas and
combustion supporting gas cylinders
The spacing for Class II and III should be reduced by 25%, and for Class
III flammable solids stored in packing area, the spacing should be reduced
by 50%.
5. The pumps specially used for tankage shall be located outside the tank
bund. The spacing is not less than 15m for Class I a, not less than 12m for
Class I b and II, not less than 10m for Class III and floating roof tanks, not
less than 8m for the tank with a volume equal or less than 500m3.
7. Railway lines and roads shall be located outside the fire explosion area.
Typical maximum thermal radiation flux values* for refrigerated storage of LPG are:
Typical maximum thermal radiation flux values for pressure stored LPG are:
Typical maximum thermal radiation flux values for LNG storage are:
Where multiple groups are required, each group shall be separated from
unprotected adjacent groups by a minimum horizontal shell-to-shell distance of 50
metres for heights up to 10m (increase to 60m for unprotected items above 10m).
General:
Where space is limited in tank layout areas, the use of thermal protection screens,
etc. may be considered.
Special spacing is required between the listed items and oxygen and/or gaseous
hydrogen storage. Refer to the relevant standard or guide.
6.0 REFERENCES
PRC Engineering Standard / Specification Index.
GB 50160-92 Fire Prevention Code of Petrochemical Enterprise Design
7.0 ATTACHMENTS.
Attachment 1.
SP-8230-0000-0003 Rev 01 Page 45 of 47
Specification for Equipment Spacing.
CSCP Nanhai Petrochemicals Project
Bechtel – SEI – Foster Wheeler PMC
BASIC SPACING
ITEM Fig. 4 - 'On Site' Spacing Chart
RA1 REACTORS ABOVE AIT EXTERNALLY INSULATED 4.5 This chart to be used with 'On-site spacing guide.
10.5 4.5 7.5 10.5 22.5 15 9 10.5 10.5 7.5 9 10.5 X X RP1 CENTRAL CONTROL HOUSE 30
15 15 15 15 15 15
15 15 15 15 22.5 15 15 15 15 15 15 15 15 15 X 10 X RS1 MAIN EQUIPMENT STRUCTURES NA
9 9 9 9 9 9
15 15 15 15 15 15
15 15 15 15 22.5 15 15 15 15 15 15 15 15 15 X 10 X X RT1 ON SITE PIPE RACKS 4.5
9 9 9 9 9 9 EMERGENCY VALVES FOR SHUT-OFF
ISOLATING, SNUFFING, UNIT (BATTERY) LIMIT ETC
X 4.5 4.5 X 15 X 4.5 X X 15 4.5 3 7.5 X X 30 15 15 X RU1 7.5
Attachment 2.
FIG 5, “Off Site” Spacing Chart.
BASIC SPACING
FACILITY
Fig. 5 - 'Off Site' Spacing Chart
REF. BOILER HOUSES AND P OWER STATIONS 30
X X 40 40 X RF2 MAIN FIRE WATER PUMPS 45 See note in section 5.4: 'Off-site' spacing guide.