236.GAS
236.GAS
PAGE
I. SUMMARY 236-3
This profile envisages the establishment of a plant for the production of 6000
gas/electrical stove per year.
The present demand for gas/electric stove is estimated at 3000 pieces per
annum. The demand is expected to grow to 3509 and 4440 pieces by the
year 2000 and 2006, respectively.
The project is financially viable with an internal rate of return (IRR) of 46.76%
and net a present value (NPV) of Birr 4502.5 thousand discounted at 10.5%.
Gas/Electric stoves are cooking ranges used for cooking a number of items.
They are used in hotels, messes, restaurants, hostels, and other places for
cooking food. They are operated by electrical power or L.P. gas. Usually the
top of gas/electric stoves (cooking ranges) consists of four heating plates
individually controlled by rotary switches.
The proposed project profiles deals with cooking ranges operated by L.P. gas.
A. MARKET STUDY
Demand for stoves in Ethiopia is met through imports originating from various
countries, although the Peoples Republic of China appears to have dominance
in the market as evidenced by the huge import of small kerosene stoves from
that country. For instance, in the year 1985, out of 107379 pieces of imported
stoves, 106049 were from China. In 1987 as well, out of an import figure of
293228 pieces, 289101 were of Chinese make.
Despite the relatively large import of stoves of all kinds, gas and electric
stoves, including the table top ones, however, represent a small fraction of
the total, the market being dominated by kerosene stoves. The import data
of gas and electric stoves, which is shown in Table 3.1, is not marked by a
secular growth pattern. The highest import registered was 9296 pieces in
1990, while the lowest, i.e. 587 pieces was in 1991.
When the data set is exponentially smoothed with a smoothing factors of 0.2
it yields a forecast of 2954 pieces. The mean import over the same span of
time, however, is 4162 pieces. On the assumption that the exponentially
smoothed import data will reasonably approximates the demand, it is
considered that the present effective demand for gas and electric stoves is in
the order of 3000 pieces per annum.
236-4
Table 3.1
IMPORT OF GAS & ELECTRIC STOVES (PIECES)
YEAR ACTUAL VALUE EXPONENTIALLY
SMOOTHED
VALUE
1985 1330 -
1986 8484 1330
1987 6426 2761
1988 3484 3494
1989 7592 3492
1990 9296 4312
1991 584 5309
1992 974 4364
1993 2430 3686
1994 1020 3435
1995 - 2954
2. Demand Projection
The past decade has witnessed a marked shift in the urban population's fuel
source utilization from fuel wood to gasoline and electricity. This change in
the pattern of energy consumption is generally perceived as a favorable to
environmental conservation since it will have significant contribution in
stemming the tide of deforestation from which the country has suffered a lot.
The demand for gas and electric stoves is thus expected to grow parallel to
the urban population growth rate which is 4% per annum, and the resulting
projection is shown in Table 3.2.
Table-top gas and electric stoves currently sell in the range of Birr 650 and
1000, averaging about Birr 800. Reducing this by 15% to take account of
distributor's margin, the import parity price is considered to be about Birr 680
per piece.
The product can be distributed through the existing wholesale and retail
channels.
236-5
Table 3.2
DEMAND PROJECTION OF GAS AND ELECTRIC STOVES
YEAR PROJECTED DEMAND
(PIECES)
1997 3120
1998 3245
1999 3374
2000 3509
2001 3650
2002 3796
2003 3948
2004 4106
2005 4270
2006 4440
1. Production Capacity
The envisaged plant will have an annual production capacity of 6000o stoves.
The plant will operate single shift, 8 hours a day, and for 300 days a year. The
working days are set by deducting Sundays and public holidays in a year and
assuming that maintenance works will be carried out during off-production
hours.
2. Production Programme
The production programme of the envisaged plant is worked out based on the
forecasted demand for the product (see Table 3.3)
Table 3.3
PRODUCTION PROGRAMME
YEAR 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Production Nos. 3300 3500 3600 3700 3900 4000 4200 4400 4600 4800 4950 5100 5400 5600 5800
The major raw materials required by the plant are mild steel plates, stainless
steel sheets, angles, rods, grills, burners and knobs. Hinges, tubes, and
packaging materials are auxiliary materials required by the plant. The list of
raw and auxiliary materials is shown in Table 4.1.
Table 4.1
ANNUAL MATERIAL REQUIREMENT
AT 96.6% CAPACITY UTILIZATION
NO DESCRIPTION QUANTITY COST('000
BIRR)
Electricity and water are the inputs required by the plant. Electricity required
by machinery and equipment, lighting and other auxiliary services is
estimated to be 30 kw, and at 80% efficiency, the annual energy consumption
will be 558400 kwhrs, which costs Birr 14815. Annual water consumption will
be 485 m3 which costs Birr 485 at the rate of Birr 1.0 per m 3. Thus, The total
expenditure on plant utilities will be Birr 15300.
VI. TECHNOLOGY AND ENGINEERING
A. TECHNOLOGY
1. Production Process
Since the end product has got several components to be assembled together
it is advisable to check them at every stage of operation. In press machines
strict vigilance is necessary to assure quality of finish by way of proper setting
of tools and timely maintenance of them.
2. Source of Technology
The technical data and information are compiled from a document provided
by the National Research Development Corporation of India.
B. ENGINEERING
The list of machinery and equipment required by the plant, together with
quantity and costs is presented in Table 5.1. The total cost of machinery and
equipment is estimated at Birr 83.6 thousand out of which Birr 63.6 thousand
will be required in foreign currency.
The total area required for land site will be 1000 m 2. The built up area for
production offices and other facilities will be 400 m2. Estimating that a unit
area (per m2) of building costs Birr 1400, the total expenditure on plant
building will be Birr 560,000. The total expenditure on land as per Region 14
lease rate will be Birr 260,000. Thus, the total expenditure on land, building
and civil works is Birr 820,000.
A. MANPOWER REQUIREMENT
The complete list of manpower required by the plant is presented in Table 6.1.
B. TRAINING REQUIREMENT
Table 5.1
LIST OF MACHINERY AND EQUIPMENT
NO ITEM QUANTITY
(NOS)
1. Shearing machine 2
(Power-operated)...
2. Hand-operated lever 2
type shearing machine
3. Flexible shaft grinder 2
4. Portable drilling m/c 2
5. Arc welding m/c 2
6. Gas 2
7. Double-ended bench 1
grinder
8. Spray painting 1 unit
equipment (with
compressor, spray gun,
motor, etc)...
9. Baking oven (oil fired) 2
10. Cutting tools, hand set
tools, etc...
236-9
Table 6.1
MANPOWER REQUIREMENT
Sub-total 11
Sub-total 10 - 33000
Depreciation
A. INVESTMENT
The total investment cost of the project including working capital (See Table
7.l) is estimated at Birr 1993.53 thousand. Owners are assumed to contribute
40% of the finance in the form of equity while the remaining 60% is expected
to be financed by long term bank loan.
236-11
Table 7.l
TOTAL INITIAL INVESTMENT
IN 'OOO BIRR
No. Items L.C F.C Total %
The major component of the investment are plant machinery and equipment,
building and civil works, pre production expenses accounting for 4.2% 28%
and 8.7% respectively. The foreign component of the project accounts for
36.2% of the total investment.
B. PRODUCTION COSTS
Table 7.2
PRODUCTION COST
'OOO BIRR
Items Year 15 16 17
*
Cost of feasibility study, licensing, training, commissioning and interest
during construction.
236-12
C. FINANCIAL EVALUATION
1. Profitability
According to the projected income statement (see Table 7.A.1) the project will
generate profit beginning from the first year of operation. Important ratios
such as the percentage of net profit to total sales, net profit to equity (Return
on equity) and net profit and interest on total investment (return on total
investment) are 30.3%, 146.6% and 46.7% in the first year of operation. The
income statement and other profitability indicators show that the project is
viable.
2. Break-even Analysis
3. Payback Period
Investment cost and income statement projection are used in estimating the
project payback period. The project will pay back fully the initial investment
less working capital in 2 years.
Simple rate of return is the ratio of net profit after tax plus interest to the total
profit calculated for one year at full capacity utilization.
Based on cash flow statement (see Table 7.A.2) the calculated IRR of the
project is 46.7% and the net present value at 10.5% discount is Birr 4502.5
thousand.
236-13
D. ECONOMIC BENEFITS