Overview of Construction Claims and Disputes
Overview of Construction Claims and Disputes
• Lets assume that during execution phase , you found some issues - not under
your responsibility - in your project ,that will hinder your progress or incurring
you extra costs , but don't know how to claim your rights , in that case you may
• In addition , you may have some rights , but may you don’t know that you should ask for it , for
example if you found some issues in the project design , and you informed the owner (or consultant)
with these issues , but he asked you to make the redesign or to suggest a proposal , although , your
contract does not include design works , So , if you are not aware of claim management you will do
that and carry this responsibility for free , Hence the importance of Claims Management
2 – Definitions
1 - Claim
• A written demand or assertion by one of the contracting parties, seeking, as a matter of legal
right, payment of additional money, adjustment to the time of performance and/or some
other change/variation to the terms of the contract, arising under or related to the contract
2 - Change/Variation Order
• Directive from the owner/employer, or their representative, to the contractor directing him
3 - Damages
Owner/Employer
Directed Constructive
Directed
Acceleration Acceleration
Change/Variation
1 – Critical Delay • If the delay was in the critical activities so you can issue EOT
2 – Non -Critical Delay • If the delay wasn't in the critical activities and no impact on
project end date , In this case you can issue Disruption claim
Question Now : Can we compensate the contractor for any critical delay ?
Types of critical delays
1 – Compensable Delay • If the critical delay was from the client side , so contractor can ask
right only to ask about time extension with no additional cost from
owner side
Types of critical delays
3 – Inexcusable Delay • A critical delay from the contractor's side , so the contractor has no
4 – Concurrent Delay • If two (or more) critical delays arise at the same time .
5 – Pacing Delay(Deceleration) • Deceleration of the project work, by one of contract parties, due to a
delay or potential delay to the end date of the project caused by the
Delay Types
1 – Compensable Delay
2 – Excusable Delay
3 – Inexcusable Delay
4 – Concurrent Delay
1 – Direct Pacing
5 – Pacing Delay(Deceleration)
2 – Indirect Pacing
6 - Owner/Employer Claims
Liability/Entitlement
Causation
• The event or circumstance causes the contractor to do something or take some action which
otherwise would not have occurred were it not for the event.
Damages /Quantum
1 - Global impact
4 - Impacted As‐planned
8 - Windows Analysis
9 - Snapshot Technique
6 - Collapsed As-Built
(AS Built But For)
9– Monetary damages
Indirect Cost : Cost not allocable to any specific item of direct work
Direct Costs
Indirect Costs Delay Costs
O&M costs
Consumable supplies
3 - Delay Costs
• Idle equipment
• Idle personnel
• Escalation costs of labor, materials, and equipment attributable solely to the delay
4 - Impacted Costs
4 - Impacted Costs
9 – Monetary damages
4 - Impacted Costs
10 – Other Contractor Damages
Loss of early completion bonus or completed plant performance (“name plate”) bonus
Interest cost
1 – Negotiation
You should expect that owner will invite you to meet him , in order to discuss your submitted claim ,
and may he will try to reduce some of your requirement , so you should be a professional negotiator
2 – Standing Neutral
If there was no agreement between you and the owner , claim will be a dispute , then dispute should
Note that Difference between claim and dispute that dispute is unsolved claim
13 – Dispute Resolution
If parties faced a failure of agree for the dispute adjudication board, and before going to
Mediation Conciliation
If the dispute continued , so there will be only one solution , before going to court .
A binding resolution is the result of arbitration where the parties agree in advance to abide
5 – Litigation
If all attempts to claim settlement fail to reach an agreement , the disputes parties may be
Negotiation is a kind of problem solving techniques , in which people attempt to reach a joint decision in
1 - Always tell the truth. Once a contractor loses its credibility, it will
have difficulty regaining it, not only for this particular claim, but for years to
come
2 - Include visuals in the presentation of the claim. Any time a contractor can represent a point
visually, the chances are greater that the point will be comprehended and remembered
Negotiation
3 - Be prepared. A contractor must know the terms of the contract and the contract plans
in great detail. In addition, it should be able to explain its plan of building the project and
how that plan was upset by the claimed events. Finally, a contractor should be prepared
to explain and visually demonstrate the effect of those events on costs and time to
4 - Do not negotiate against yourself. Most negotiations between private parties involve some sort
of stair-step approach, with each side giving a little until an agreement is reached. Some public
owners don’t negotiate that way. They expect the contractor to guess what number they have in mind
to resolve the matter. That approach puts the contractor in a difficult negotiating position
Engineer’s Response
Red Book
Owner should response within 42 days (or agreed period) of receiving claim (or particulars supporting
a previous claim)
Gold Book
If the owner does not respond within 42 days (or agreed period) of receiving claim , contractor may
consider that , the claim has been rejected by the owner , and , he can go to the second step (Dispute
Purpose The DAB is the first step in the dispute resolution process for these contracts, and aims
to resolve disputes before they go on to more formal arbitration. If it does its job well, a
DAB can help both sides to see the truth of a situation and to accept its decision, so that
Appointment Each party nominates a member for approval by the other party. Both parties
appoint chairman
Activities:
Regular site visits at the request of either party (not less than 3 to 4 times per year)
Time Frame Within 84 days of reference of dispute to Board: Board issues decision
Within 28 days of receiving decision, Party gives notice to other Party of its
Dissatisfaction – if any -
Decision becomes final and binding upon both parties if no notice of dissatisfaction
Time Frame Within 84 days of reference of dispute to Board: Board issues decision
Within 28 days of receiving decision, Party gives notice to other Party of its
Dissatisfaction – if any -
Decision becomes final and binding upon both parties if no notice of dissatisfaction
The dispute is referred to the DAB for its decision under Sub-Clause 20.4
Does that Party give its notice of dissatisfaction Dispute is settled and the decision is final
NO
under 20.4 in the time allowed (28 days)? and binding, Sub-Clause 20.4
YES
Is the dispute
YES Dispute is settled
settled amicably?
The Parties have 56 days to resolve the
Dispute amicably, Sub-Clause 20.5
Dispute shall be finally settled by
NO
Arbitration, Sub-Clause 20.6
Mediation
A meeting between disputants and a third party called mediator to discuss settlement
Impartial Neutral
Honest Independent
Knowledge of the topic and of the law Ability to gain the trust of the parties
Cultural sensitivity (in international disputes) Good analytical and negotiation skills
Conciliation
It is the process of adjusting or settling disputes in a friendly manner through extra judicial means
So we can say that , conciliation means bringing two opposing sides together
In case of success of mediation , the mediator helps the disputing parties to finish the contract
technique the disputing parties submit the claim to an unbiased third party
Commerce) , with their prior pledge to on the third party decision. A third party
reviews the evidence in the case and imposes a decision that is legally binding
A third party reviews the evidence in the case and imposes a decision that is legally binding on both sides
Mediation Arbitration
Non-binding Binding
Litigation should be your last step , and you should think carefully before going to it , since it needs a lot
of money to cover lawyer and court expenses , in addition it also leads to bad relationship between the
two parties . In fact , Litigation shouldn't be your choice you must be forced to do it
Conclusion
42 Days
No Repose
DAB
Reject
Submit the Claim to owner
42 Days
Owner response
You Agree
Claim is Settled
Litigation Arbitration