Rate Analysis - Road, Causeway, Drain

Uploaded by

Jagdish Ghogare
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 8

SR. NO.

ITEM DESCRIPTION UOM QTY RATE AMOUNT


Cause Way RMTR. 120.00 108,211 12,985,317
1 Excavation Cum 622.00 450.00 279,900

Backfilling & Removal


2 Cum 622.00 150.00 93,300
of Surplus Earth

Rubble Soling at the


3 Cum 159.60 1,900.00 303,240 1,888.21
Bed
4 PCC in the bed Cum 39.10 6,500.00 254,150
Stone Pitching at the
5 Cum 338.00 5,700.00 1,926,600 5,662.80
bed
6 RCC Footing Cum 57.60 7,400.00 426,240
7 Shuttering for Footing Sqm 144.00 550.00 79,200

RCC HUME PIPE -


8 Nos. 26.00 18,500.00 481,000
1200
9 RCC Encasement Cum 31.20 7,400.00 230,880
Shuttering for
10 Sqm 341.12 550.00 187,616
Encasement
11 RCC for Wall Cum 151.20 7,400.00 1,118,880
12 Shuttering for Wall Sqm 378.00 550.00 207,900
13 RCC for Side Wall Cum 7.77 7,400.00 57,498
Shuttering for Side
14 Sqm 19.42 550.00 10,684
Wall
Boulder / Murram
15 Cum 1,650.00 1,200.00 1,980,000 1,201.61
Backfilling on top
Stone Pitching at Side
16 Cum 472.00 5,700.00 2,690,400
wall
Road Work - Cross
17 Rmtr. 60.00 8,250.00 495,000
sectiion (CONCRETE)
Road Work - Cross
18 Rmtr. 60.00 4,250.00 255,000
sectiion (WMM)
REINFORCEMENT
19 MT 24.78 77,000.00 1,907,829
COST
Length
1,000.00 CONCRETE ROAD
(m)
Width
4.50
(m)
L B H
SR. NO. DESCRIPTION UOM Quantity
(m) (m) (m)
1 Excavation cum 1,000.00 5.00 - -
Layer - 1 (Boulder -
2 cum 1,000.00 4.50 0.150 675.00
Murram)
3 Layer - 2 (RCC) cum 1,000.00 4.50 0.125 562.50
Layer - 2
4 MT 45.00
(Reinforcement)

5 Layer - 2 (Shuttering) Sqm - - -


4 Murram Shoulder cum 0.50 - -
TOTAL
Per Rm Rate
Rate Amount
220.00 -
990.00 668,250
7,300.00 4,106,250
77,000.00 3,465,000

550.00 -
-
8,239,500
8,240
Length
1,000.00 WMM ROAD
(m)
Width
3.50
(m)
L B H
SR. NO. DESCRIPTION UOM Quantity
(m) (m) (m)
1 Excavation cum 1,000.00 4.50 0.300 1,350.00
Layer - 1 (Boulder -
2 cum 1,000.00 3.50 0.150 630.00
Murramm)
3 Layer - 2 (GSB) cum 1,000.00 3.50 0.200 770.00
4 Layer - 3 (WMM) cum 1,000.00 3.50 0.150 577.50
Layer - 3.5 (Quary
5 cum 115.50
Dust)
6 Murram Shoulder cum 1,000.00 0.50 0.35 175.00
TOTAL
Per Rm Rate
Rate Amount
450.00 607,500
990.00 623,700
1,890.00 1,455,300
2,070.00 1,195,425
1,440.00 166,320
990.00 173,250
4,221,495
4,230
TW m 1.50 0.55
BW m 0.50
H m 0.90
SR. NO. ITEM DESCRIPTION UOM QTY RATE AMOUNT
STORM WATER
RMTR. 1,000.00 3,041 3,041,164
DRAIN
1 Excavation Cum 1,150.00 550.00 632,500 633

Backfilling & Removal


2 Cum 1,150.00 150.00 172,500
of Surplus Earth
173
3 PCC M10 bed Cum 48.75 6,500.00 316,875 317
4 Stone Pitching Cum 300.09 5,700.00 1,710,529 1,711
5 Stone Pointing Sq.m 2,609.50 80.00 208,760 209
1.0547512

3,345.28 -86,844,000