Microsoft Project Simplified
Microsoft Project Simplified
1. Scheduling Definition
2. Quick Links – Menu Bar
3. Look Ahead Filter
4. GNATT Chart
5. Tasks and WBS
6. Critical and non Critical tasks
7. Cheat Sheet – How to build a schedule
8. Cost Loading
The process of breaking down ‘work’ into manageable tasks as per the available
resources within the available work area with advanced construction methods and
organizational constraints is scheduling.
A schedule is the complete reflection of your thought process on the project as per
the scope. The way you want to approach, handle, overcome, coordinate and
complete all the milestones within the time frame and budget.
Setting up a baseline schedule
1. Scope – Remodel current office room – CPFC SRF
2. Review Drawings, understand architectural and structural modifications.
3. Defined Scope – Remove current furniture, ceiling, carpet and install new ones. Also install new partitions – Gypsum board.
Step 1 – Select all the tasks from Line 3 to line 9, Click on the ‘Link tasks’ icon on the menu bar. – Please see the picture in page 6.
Step 2 – Select tasks from Line 11- Line 18 – Click on the ‘ link tasks’ on the menu bar.
Step 3 – Select Line 20 – Line 45 - Click on the ‘ link tasks’ on the menu bar.
Once the connection is done – Make sure there are connections between wbs (work breakdown structure) – Demo – Rough in and Finishes.
Some tasks starts after its pre tasks finishes (by default the program is set up with Finish to stat relationship).
Then you will have a legitimate schedule – Please see that the tasks are connected – to ensure this key feature – please open the columns ‘predecessor and
successor’ and see they are tied.
Schedule Building
1. To Create a new project – Open
Micro Soft Project – New Page
Status Bar –
Updated as of
Today
Project Name with PA number Work Break Down Structures (WBS) GANTT Chart
Legend
TASK
SAVE
Tasks
Very Imp - Make sure you have the right tasks including in-progress tasks in your filter and it (tasks) makes sense to you!!!
NOTE: Please update the schedule before performing this filter. Add “Change Orders” as needed to fill the delay gap as necessary
Very Imp - Make sure you have the right tasks including in-progress tasks in your filter and it (tasks) makes sense to you!!!
**Always adjust your tasks as per their occurrence. Drag and drop all 100% and stack them in order.
Look ahead will show your future tasks. You would not see any task with 100% progress (Reason – 100% done task in the past)
NOTE: Please update the schedule before performing this filter. Add “Change Orders” as needed to fill the delay gap as necessary
Print Schedule
Line 58, 59 shows the variation that exceeds allocated amount for door installation
Please make sure that you have a clear picture of the project before starting with a schedule.
Please read the drawings thoroughly, and come up with the project driving activities (for ex: long lead).
The driving tasks/activities/packages becomes critical for the project and defines the COSC date.
Understand all the packages and calculate their lead time to start the task. Taylor the tasks in a sequence.
For a smooth project flow, please prepare submittal ahead of the task as needed (Start task=Material at site)
Prepare RFI’s if you are not clear on any of the drawings – RFI clears your way in achieving the ‘cosc’ dates.