C 4619 401 Ivaco Met Manual
C 4619 401 Ivaco Met Manual
L’Orignal, Canada
METALLURGICAL
MANUAL
C.4619/401
METALLURGICAL MANUAL
_______________________________________________________________________
1 METALLURGICAL CONCEPT 1
IN MACHINE DESIGN
2 CASTING OPERATIONS 2
4 CASTING PARAMETERS 4
C.4619/401 Rev0
IVACO Page 1 of 1 February 2014
CHAPTER 1
METALLURGICAL CONCEPTS
IN MACHINE DESIGN
TABLE OF CONTENTS
1. MACHINE DESCRIPTION 4
1.1 STEEL PLANT DATA 4
1.2 STEEL GRADES AND PRODUCTION TABLE 4
1.2.1 STEEL GRADES 4
1.2.2 PRODUCTION MIX 4
CASTER MAIN DATA 6
1.3 DRAWINGS 8
2. TUNDISH AND TUNDISH REFRACTORY SPECIFICATION 9
2.1 DESCRIPTION 9
2.2 TUNDISH REFRACTORIES 9
2.3 PERMANENT LINING AND INSULATION 9
2.4 WORKING LINING 10
2.5 TURBOSTOP 11
2.6 SPECIAL PIECES 11
2.7 ISOSTATIC (SHAPED) COMPONENTS 11
2.8 TYPICAL OPERATION LIFE OF REFRACTORY MATERIALS 11
2.9 TUNDISH PREHEATING 12
2.10 TUNDISH POWDER 13
2.11 DRAWING AND DATASHEETS OF THE REFRACTORY MATERIALS 13
3. MOULD 14
3.1 DESCRIPTION 15
3.2 EFFECT OF MOULD COOLING 15
3.3 CONTROL OF MOULD COOLING WATER 15
3.4 WATER QUALITY 15
3.5 EMERGENCY COOLING WATER 16
4. AUTOMATIC MOULD LEVEL CONTROL 16
4.1 FUNCTION 16
4.2 THEORY OF OPERATION 17
4.3 CALIBRATION 18
3(4) strand caster producing initially 700 000 short tons per year increasing to
900 000 sht py with the addition of a forth strand
Design limit
- section range 130 mm sq. to 180 mm sq.
- cutting length 7.6 to 14 m
Mould Electro Magnetic Stirrer Rotative stirring movement of the liquid core in
order to improve billet centre soundness. The
stirrer generates a rotating magnetic field
about the casting axis.
Strand guide system 4 Segments for billet and dummy bar guidance,
Segment 1 containing 2 guide units
Secondary Cooling 4 zones. Zones 1 & 2 water only, zones 3 & 4 air
mist
Final Electro Magnetic Stirring The stirrer coils are mounted in the lower part
of the machine radius at an optimised position
(depending on section size and casting speed).
1.3 DRAWINGS
LADLE/TUNDISH/MOULD 95090
C.L. MACHINE
C.L. STRAND 1
C.L. STRAND 2
C.L. STRAND 3
C.L. STRAND 4
-2950
250
1000 CL Casting Radius
1
2
FR
Future SEMS
s1
4
5
000
0
6 R1
Future MSR
7
8
R18000
9
s2
Disconnection
10
Tangent Axis
Fixed Side
z 11
12
13 Future MSR
x
Disconnection
Cutting Start
14
15
16
17 -2000
s3 18 Passline
19 20 21
1 2 3 4 5 6 7 8 9 10 11 12 13
10662.83 13879.6
2. TUNDISH AND TUNDISH REFRACTORY SPECIFICATION
2.1 DESCRIPTION
The tundish is the last refractory-lined unit through which the steel passes before
entering the mould. Therefore it can have an important influence on the quality of
the cast product as well as on the casting yield.
The thermal conditions of the tundish are to a large degree influenced by the
conditions of the steel in the ladle (steel temperature, presence of stratification).
High-temperature preheating of the tundish is commonly used to minimise the
heat lost during the initial filling and the thermal losses through the refractory
lining.
The steel leaving the tundish flows into the mould through a nozzle. The type of
nozzle is the basis for the “Casting System”, and is chosen depending on the
quality requirements of the steel being cast, and the operational aspects of the
caster.
In general the tundish is either equipped to cast with some form of automatic flow
control, or with a metering nozzle that has no automatic flow control
Typical material
Permanent lining:
ANKOCAST SV90 0-6 C, bauxite-based low-cement vibrating mix
Thermal insulation:
PYROSTOP BOARD 1260, ceramic fibres, thermal conductivity ~0.1 W/mK
(see refractory documentation)
2.5 TURBOSTOP
A Turbostop is a specially designed refractory piece which is placed over the
Impact Area of the ladle stream. Its purpose is to equalise the flow of steel to
each of the strands, and also to direct the flow of steel upwards to enable capture
of non-metallic inclusions in the tundish surface layer. Ankoform M90S-IP 0-6 C
(see refractory documentation).
1400
1200
1000
Tem perature (°C)
800
600
400
200
0
0 30 60 90 120
Time (minutes)
The liquid steel in tundish must be covered with powder in order to:
Prevent reoxidation (especially important for Al-killed steels and for “clean
steels” generally). This is by far the most important function of the
powder.
Reduce temperature loss and limiting the radiation from the steel surface
to the ladle slide gate mechanism and stopper gear (important when
there is no tundish cover)
Tundish powder should be applied soon as the steel level is approx. 250 - 350
mm. New powder must be added during casting when necessary, especially
after a sequence change. The appearance of sparks around the ladle shroud is
a clear indication that there is not enough powder around it.
TUNDISH – TA 10044714
TUNDISH COVER 10044772
RHI REFRACTORY DOCUMENTATION PDF
VESUVIUS REFRACTORY DOCUMENTATION PDF
0.5
E E
825
5000
C C
0.5
0.2
0.2
950
65
100
1 1 Tundish Shell 1725x3058.9x5000 - 7.011 TO 546539 10044235
Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
1050 0.5 ISO 128
Instructions 9800.4 110.100 7.011 TO 1 : 20 A2
Replaced by
4040
F 3800 F
160
E E
20
20 20
C C
600 1297 1297
2
1
Total Weight Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
Total ~1804
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 110.120 290.3 KG 1 : 10 A2
Replaced by
_________________________________________________________________________________________
Table of Contents
1. General Information [page 3]
_________________________________________________________________________________________
Vesuvius is a global leader in metal flow engineering, providing a full range of engineering services and solutions to
its customers worldwide, principally serving the steel and foundry industries.
VESUVIUS Steel Flow Control and Advanced Refractories business units exist to assist Steel makers to enhance
the quality of their products, increase their competitiveness and reduce their environmental footprint.
VESUVIUS achieves this by working closely with its customers, to develop customized refractory systems,
services and technologies that enable them to improve their performance.
From ladle to mold, VESUVIUS provides the most advanced tundish refractory systems. As the market leader in
tundish refractories, VESUVIUS provides technologically advanced products for casting applications and complete
installation services and support to ensure your unique operation is optimized.
_________________________________________________________________________________________
Drawing provides overall dimensions but not the required detail to develop specific designs. For this exercise and
from this drawing:
The following pages show “sample” or “example” designs that would be a starting point for design development
based on input on the application. Development of actual designs for the application will required a detailed
understanding of the application. Should SMS wish to proceed with Vesuvius then a dialog will commence with
Vesuvius requested specific details for that purpose.
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
Various stopper nose geometries are available. To suit the application two features need to be considered. First the
mechanical arrangement needs to be suitable in terms of the interaction of the rod and the nozzle seat. Secondly
the flow characteristics of the regulating refractory must be appropriate.
The chart below serves to illustrate the impact of nose shape on steel flow. Specific calculations should be made
for the IVACO application.
_________________________________________________________________________________________
_________________________________________________________________________________________
2.1.5 VISO - Advanced designs through Flow Simulation – Actual project results
Project 1
Background: A bloom caster who’s product is used for locomotive rail was having quality issues and requested a
review of their stopper and SEN designs in pursuit of a refractory solution. Conventional Stopper and SEN’s were
being used.
Flow Simulation project: There conventional designs were modeled and compared to more sophisticated designs.
For the SEN a multi-port “Swirling” SEN was developed and the stopper developed had a “Ripple” nose geometry.
Results of modeling:
Greater flow stability seen for the stopper and more evenly distributed rotational flow predicted for the SEN.
_________________________________________________________________________________________
Project status: During trial customer saw significant steel quality advantage. They also saw improved stopper rod
position stability and reduced wear of the regulation refractories (seat & nose). See trial data below
Customer is 100% converted to the 5-port swirl SEN and Ripple Rod and has been running that combination for
several years.
_________________________________________________________________________________________
Project 2
Background: Traditional Submerged Shrouds used for billet casting are of a through-bore single exit design.
Vesuvius has developed, through Flow Simulation, advanced designs that significantly improve steel mold flow
behavior. For this project such a design was evaluated in comparison to the conventional design in use.
Flow Simulation project: Cast conditions are inputted and the flow simulation predicted key casting parameters
within the mold. The following graphics are from a recent project which was for a 160mm x 160mm billet
application.
Velocity [m/s]
Velocity [m/s]
Temperature [K]
_________________________________________________________________________________________
versus
• Non-uniform steel shell solidification • Swirling SES produces hot meniscus with
• No flow rotation, EMS is required optimized mold powder melting and
• Flow in the upper mold region controlled by free lubrication
convection • Uniform steel shell solidification
• Flow rotation, EMS is NOT required
• Improvement of steel microstructure
(dendrites vs equiaxes)
• Reduction of carbon segregation
• Improved inclusion floatation
Rotational flow induced by the 5-port swirling SEN is similar to that achieved with Electro Magnetic Stirring, without
the capital and operating expense.
Project status (June 2013): The modeling results were presented and customer has committed to a trial of the new
5 port design. Pieces are being manufactured.
_________________________________________________________________________________________
2.2 VISO: Material selection by application (most common for these applications, MANY more available)
Material Material
Application Comments
group (Mix) code
_________________________________________________________________________________________
2.2.1 VISO - Technical Data Sheet for TS365 Ladle Shroud barrel material
_________________________________________________________________________________________
2.2.2 VISO - Technical Data Sheet for TS238 Stopper and SEN barrel material
_________________________________________________________________________________________
2.2.3 VISO - Technical Data Sheet for TS1111 Stopper nose and SEN seat material
_________________________________________________________________________________________
2.2.4 VISO - Technical Data Sheet for TS240 SEN slag line material
VISO 3.1 Vesuvius Billet / Bloom Customers using Stoppers and SEN’s for Submerged casting
_________________________________________________________________________________________
Customer Country
GERDAU MANITOBA Canada
SIMEC INTERNATIONAL-TLAXCALA Mexico
TAMSA Mexico
TERNIUM MEXICO-PUEBLA Mexico
CARPENTER TECHNOLOGY USA
CHARTER STEEL CLEVELAND USA
EVRAZ PUEBLO USA
GERDAU MACSTEEL FORT SMITH USA
GERDAU MACSTEEL JACKSON USA
GERDAU MACSTEEL MONROE USA
IPSCO KOPPEL TUBULARS CORP. USA
NUCOR STEEL MEMPHIS USA
NUCOR STEEL MEMPHIS USA
REP-CANTON USA
VISO 2.3.1 Vesuvius Billet / Bloom Customers using Tundish Gates with SES’s for Submerged casting
Customer Country
ARCELORMITTAL CONTRECOEUR EAST Canada
HAMILTON SPECIALTY BAR Canada
TAMSA Mexico
ARCELORMITTAL E. CHICAGO # 1 - EAF USA
ARCELORMITTAL STEELTON USA
CMC STEEL ARIZONA USA
NAS USA
NUCOR DARLINGTON USA
NUCOR NORFOLK USA
TIMKERN HARRISON USA
USS FAIRFIELD WORKS USA
V & M STAR-YOUNGSTOWN USA
_________________________________________________________________________________________
• The VISO Caster Refractories required to operate the IVACO bloom caster would be manufactured in
North America, at either our Charleston Illinois facility or our Monterrey Mexico facility.
• NAFTA manufacturing, backed by capacity at numerous other global locations, gives us flexibility and
supply assurance.
_________________________________________________________________________________________
2.5 VISO - Product development and Technical Services “Local presence with a Global Reach”
These resources are used in concert to ensure continuous product development; and to solve applications
problems that arise, on a timely basis.
2.5.1 VISO - Vesuvius R&D resources – Caster Refractories (other product groups not shown)
_________________________________________________________________________________________
Three (3) sites – Pittsburgh, PA; Feignes France; and Suzhou, China.
All equipped with melting (steel), blending and forming (refractory) equipment with extensive analytical equipment
for both steel and refractory applications (SEM, XRD, XRF, etc.).
Six (6) sites – Cleveland, OH & Pittsburgh, PA; Borken Gmbh, Rio Brasil, Suzhou China, and Kolkata India.
5-port SES
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
1.2.1 MGR Rice Hull Ash – manufactured by our sub-contractor, Agrilectric (Louisiana, USA)
• Good insulator, cost effective; silica based
1.2.2 AFAX Tundolite TU875G – manufactured in Conneaut, OH
• Basic tundish flux, balances need for insulation with quality enhancement
1.2.3 AFAX R795 - manufactured in Conneaut, OH
• Premium product , recommended for use on quality critical grades
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
3.3: FLUXES - Vesuvius Flux Feeder – Dilute Phase, Air Assist Flux Feeder
Vesuvius can offer our dilute phase, air assist flux feeder for use - subject to agreement; picture attached for
reference. More detail can be provided at a later date, but Ivaco will provide all necessary utilities to operate the
flux feeder - 110 V electrical connection, ¾” air/nitrogen line with a minimum of 80 psi, and a suitable location for
the equipment - and Vesuvius will ensure that the unit(s) provided is within ESA compliance.
We note that use of flux feeders at billet casters has been limited to date, due to very low consumption rate of mold
fluxes - it is difficult, but not impossible, to accurately regulate flow of flux material at such low levels.
_________________________________________________________________________________________
ArcelorMittal Indiana Harbor East Chicago/ IN P. Wurth 178 x 178 1.3 - 1.8 Free Cutting steel SPH-C 126/A
CMC Arizona Mesa/ AZ Danieli 130 x 130 4.0 - 6.0 C-Steel 0.20 - 0.40% C SPH-C 189/GM5
Gerdau Macsteel Monroe/ MI Danieli 152 x 152 2.1 - 3.3 C-Steel <0.08%C, 0.23 -0.45% C SPH-C 411-81E
C-Steel 0.08 -0.23%% SPH-C 176/ALS9
C-Steel >0.45%C SPH-C 189/E1
North American Stainless Ghent/ KY Danieli 160 x 160 0.7 - 1.6 AISI 303, 304, 316, 321, SPH-C 163/D2
AISI 430 SPH-C 449/2.5
AISI 400 SPH-C 412/1
V&M Youngstown/ OH Rokop 223 1.6 - 2.0 C-Steel 0.12-0.48% SPH-C 126/M5
286 1.2 - 1.4 C-Steel SPH-C 126/R1
Ipsco Koppel Koppel/ PA Mecan-Arbed 140 2.0 - 2.9 C-Steel SPH 126/K1
Ternium Puebla Puebla Concast 120 x 120 1.0 - 2.0 C-Steel 0.35 - 0.80% C SPH-C 189/E1
160 x 160 C-Steel < 0.35% C SPH-C 411-81/E
215 1.6 - 2.0 Tube SPH-C 126/F3
Ternium Tamso Veracruz SMS Demag 205, 270, 310, 370 0.6 - 2.0 C-Steel < 0.20 % C SPH-C 126 II
C-Steel 0.20 - 0.40% C SPH-C 126F4
Timken Canton/ OH SMS Demag 180 x 375 0.3 - 0.5 C-Steel 0.15 - 0.65% C GR628X
REP Canton Canton/ OH Danieli 254 x 330 0.5 - 0.8 C-Steel 0.66 - 1.00% GR675X
Danieli Flex 170 x 170 1.0 - 1.7 C-Steel 0.20 - 0.40% C GRC17R
Charter Cleveland Cuyahoga Hts/ OH Danieli 178 x 178 1.3 - 1.8 C-steel 0.15 - 0.85% C GRC17R
SDI Pittsborough/ IN Demag 254 x 381 0.8 - 1.0 C-Steel 0.18 - 0.60%C GR628X
Carpenter Technology Reading/ PA Demag 127 x 127 1.3 - 1.8 AISI 304, 316 GR636
Arkansas Steel Newport/ AR Mitsubishi 140 x 266 0.8 - 1.8 C-Steel 0.20 - 0.70% C GR676X
Simec International Apizaco Danieli 160 x 160 1.0 - 1.7 C-Steel 0.25 - 0.60% C GRC17R
120 x 120 C-Steel With Lead GR27
_________________________________________________________________________________________
Full complement of eight (8) engineers and scientists dedicated to flux technology in NAFTA.
_________________________________________________________________________________________
Section view
Working Lining
Permanent Lining
Insulating Board
Working Lining; MgO-based Dry Vibratable 1.5” thick side and end walls, 2” thick floor.
Permanent Lining; low cement, low moisture, high alumina castable , 7.4” thick.
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
Turbostop is a pre-cast & pre-fired custom designed shape to optimize tundish flow. The Vesuvius flow
simulation group uses physical water modeling and CFD mathematical modeling to optimize tundish flow for
various attributes such as reduced splash, surface directed flow for clean steel,and minimum radical grade
transition for steel yield improvements.
A custom Turbostop will be designed for this tundish. The CS-7426 Turbostop was included in this
presentation as an example. For a typical flow pattern of a Turbostop see the CFD example below.
Velocity Contours
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
Tundish refractory thermal calculation at steel making temperature using dryvibe working lining option.
_________________________________________________________________________________________
_________________________________________________________________________________________
Welded anchors
Anchors are welded prior to installing insulation board and casting permanent lining.
Vesuvius supplies a variety of tundish permanent lining products designed for cost effective performance.
Steel Form
_________________________________________________________________________________________
Dry-out Curve
1200
18 Hours
1100 FOSCAST MT
1000 Extend soak/ hold time Temp F
in 4 hour incroments if
900 dripping w ater or
12 Hours 16 hrs at this point steam is present.
800 all embedded
60' per hr thermocouples
8 hours at
700 should read +220'F
88' per hr
or extend time 4
Temp
500
12 Hours
400
Shut off dryer and
4 Hours
allow to cool
300
83' per hour
200
100
0
Start Ramp Soak/ Hold Ramp Soak/ Hold Ramp End
Step
Cycle Start Ramp up Soak/ Hold Ramp up Soak/ Hold Ramp down End
Time 0 4 hrs 12 hrs 12 hrs 18 hs 8 hrs 0
Temp F 70 F 400 F 400 F 1100 F 1100 F 400 F 70 F
83' per hour 60' per hour 88' per hour
Vesuvius supplies a variety of tundish working lining products designed for cost effective performance.
• Basivibe
_________________________________________________________________________________________
Hopper with scale and PLC for material Consumption tracking per tundish. Optional scale can be provided to
track the amount of material used for each tundish. This information can be tracked for each tundish by tundish
number
Basivibe™ Form
Vesuvius designs and builds the forms and curing units. Curing unit is unique and has the capability to be removed
from the steel form and attached to a fiber lined cover for drying out castable safety linings
_________________________________________________________________________________________
The product is installed dry in between a metal form and the tundish backup lining refractory.
The form is heated to 650 deg. F (350 deg. C) to set the Dryvibe.
Once set, the form is pulled and the tundish is ready to be sent to the caster.
_________________________________________________________________________________________
4.5.1 TUNDISH LININGS REFRACTORY - Vesuvius Turbostop® References (NAFTA – billet / bloom)
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
_________________________________________________________________________________________
6. IVACO Bloom Caster project time line (proposed) and required commitments
Note that timeline varies by product line; below is timeline for VISO, which has the longest lead time.
2013 2014
JUNE JULY AUG SEPT OCT NOV DEC JAN FEB
1 8 15 22 29 6 13 20 27 3 10 17 24 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22
CASTER START UP
Proposal *
Design
Manufacture
Cold commissioning
Hot commissioning
CONTINUOUS IMPROVEMENT
Proposal / Design
Trial
2014
MAR APR MAY JUNE JULY AUG SEPT OCT NOV DEC
1 8 15 22 19 5 12 19 26 3 10 17 24 31 7 16 21 28 5 12 19 26 2 9 16 23 30 6 13 20 27 4 11 18 25 1 8 15 22 29 6 13 20 27
CASTER START UP
Proposal *
Design
Manufacture
Cold commissioning
Hot commissioning
CONTINUOUS IMPROVEMENT
Proposal / Design
Trial
2. Design and pricing – by Mid-July 2013 for us to gain the application knowledge required and to develop
the specific designs.
4. Advanced designs – by early July 2013 if to be available for commissioning, April 2014 to be part of
developmental work (continuous improvement project).
_________________________________________________________________________________________
7. Intellectual property:
The contents of this document are the exclusive properties of Vesuvius and are subjected to copyright. Any
use, copy, dissemination of this document or its use contrary to its intended purpose is not permitted without
the prior written consent of Vesuvius.
8. Disclaimer
No warranty is expressed or implied regarding the accuracy of this information, the suitability of the product for
a particular purpose, or the results to be obtained by the use of the product. Users expressly assume all risks
and liabilities arising from the use of or reliance upon this information.
9. Contact
Same as above
Walter Graf
Account Manager Flow Control
Vesuvius GmbH
Gelsenkirchener Str. 10
46325 Borken
F.R. of Germany
Tel: +49 6172 9459986
Mob: +49 171 3356161
Fax: +49 2861 83 99840
[email protected]
www.vesuvius.com
_________________________________________________________________________________________
REFRACTORY DOCUMENTATION
FOR
IVACO Canada
FOR
SMS CONCAST AG
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 1 of 36
CONTENTS
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 2 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 3 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 4 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 5 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 6 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 7 of 36
2.4.2 Tunflow
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 8 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 9 of 36
as an Alternative:
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 10 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 11 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 12 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 13 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 14 of 36
3.5 Tunflow
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 15 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 16 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 17 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 18 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 19 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 20 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 21 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 22 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 23 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 24 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 25 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 26 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 27 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 28 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 29 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 30 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 31 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 32 of 36
6.4 Wellblock
6.4.1 Drawing and Technical Data Sheet
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 33 of 36
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 34 of 36
7 ATTACHMENTS
Please also refer to the following attachments:
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 35 of 36
RHI AG
1100 Vienna,
Wienerbergstraße 9,
Austria
This document and its attachments are confidential and may be privileged. Any unauthorised
dissemination or copying hereof is prohibited without our written permission. The copyright for this
document and its possibly accompanying enclosures remain our property. This document and its
attachments serves for information purposes only and shall not have any legally binding effect.
It is also strictly prohibited to transmit or let these papers to third persons, especially competitors.
Document Title: Refractory Documentation – IVACO Canada for SMS Concast page 36 of 36
The water jacket is an accurate machined element that guarantees uniform heat
removal and shell growth.
The mounting system for the mould tube at its upper end uses key clips that
freely allow expansion along the longitudinal axis under heat load
The design of the cartridge-type mould accommodates a common M-EMS for the
range of sections cast.
The EMS does not have to be removed or remounted during a section change.
Thus, the risk of damaging the equipment is reduced and the risk of dirt entering
the water system is eliminated.
4.1 FUNCTION
The function of the mould level measuring system is to measure the actual steel
level within the upper part of the mould and to transmit this information to the
control PLC. The signals are used by the PLC to control the steel level in two
ways, depending on the casting mode.
During Open Stream Casting the withdrawal drive speed (casting speed) is
adjusted to maintain the preset level.
During submerged casting the stopper position is adjusted to maintain the preset
level, whilst the casting speed remains constant.
The source is mounted in a protective steel housing lined with lead. The source,
which is a so-called 'Pencil Source', is a long and thin rod of Co60. It radiates
gamma particles at a relatively stable rate through the narrow slit window of the
protective housing and the resultant beam of radiation is directed through the
mould to the detector.
Mounted on the opposite side of the mould to the source is the detector or
scintillation counter. This device, which is water-cooled using mould cooling
water, produces a stable reference signal proportional to the number of gamma
particles received. This signal is transmitted to the level detection processor via
shielded cables.
Measuring range
Mould
Detector
Crystal
Source
Shielding LB 352
The amount of energy that is absorbed by the liquid steel (and therefore is not
detected by the detector) is dependent on the level of liquid steel in the mould.
With Co60, the mould water causes additional attenuation.
4.3 CALIBRATION
The level measuring system must be re-calibrated with every section size. As the
geometry of the detection devices, the properties of the source, the attenuation
factor of the steel, and the detector characteristics are known we can calculate
the level of the liquid steel in the mould as a function of the number of gamma
particles received in a given time. This is converted into a measurement from a
datum point (established during calibration) by the level measuring processor and
transmitted to the mould level controller.
A calibration block for each section size is required. The block is a rectangular
solid piece of steel with section dimensions slightly smaller than the mould, and
length greater then the length of the measuring range (e.g. 300mm). The block is
lowered into the mould to block all the radiation to simulate a full mould.
After installation of a new mould and with all the sources open and all mould and
EMS water running, the procedure for calibration of the system is as follows:
• Switch the mode selection switch to 'PREPARE' position, push the ‘MIN.
LEVEL’ push-button on the mould operator pendant (MOP) to make an ‘empty’
calibration. The mould level indication is 0%.
• Lower a calibration steel block (of a size to fit just into the mould and with a
length of 300 mm) must be inserted into the mould, so that the top of the block is
80 mm below the top of the mould copper tube.
30 6
L
B-B D-D E-E ( 1 : 1 ) L
15 21
A-A
650 5
620
14 8 13
11 6
540
K K
445
22 5
330 9
15
6 10
W 23 10
15
14
40
1
C-C 4
J J
3
36
5
24 F-F G-G ( 1 : 1 )
15
190
199
5 16
208 29
3 10
I I
20
12
28
400
397
2
2
H H
1
H-H J-J
26
6
18
of Mould
of Casting Radius
17
20
G 5 5 G
7.9
16
R9917.9 27
1 7
1093
25
F
25 F
8 13
Cu-Tube 2230020.2 9
19
F 20
E E
D 1) MOULD TO BE PRESSURE-TESTED AT 9 BAR FOR 30 MINUTES.
593
18 B
28
27
4
12
Hex. Cap Screw
Socket Head Cap Screw
M16X50
M16X35
8.8 zinc plated
10.9
0.117
0.098
KG
KG
344871
349605
ISO4017
ISO4762
D 26 2 Socket Head Cap Screw M16X30 8.8 zinc plated 0.09 KG 317578 ISO4762
G B CASTING
19
18
1
1
O-Ring
O-Ring
400x 10
440x 10
NBR 70.5
NBR 70.5
0.105
0.148
KG
KG
420963
420960
10012356
10012353
DIN 3771
DIN 3771
17 1 O-Ring 440x 10 NBR 70.5 0.147 KG 420960 10012353 DIN 3771
DIRECTION 16 1 O-Ring 440x 10 NBR 70.5 0.146 KG 420960 10012353 DIN 3771
16
A A 15
14
1
1
O-Ring
O-Ring
459.3x 5.7
222x 10.2
NBR 70.5
VMQ 55
0.048
0,098
KG
KG
420955
538809
10012351
10039169
DIN 3771
DIN 3771
13 1 O-Ring 222x 10.2 VMQ 55 0,124 KG 538809 10039169 DIN 3771
W(1: 1) 12 1 Centre Pin 20h9x25 1.0503 / C45 0.047 KG 383277 10005993
B B
4
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 115.500 390,8 KG 1:2 A0
Replaced by
Approved
10.01.2013
12.12.2012
C603
T089
10'039'161 -
A C Sheet: 1 of 1
Material No.
A
Radius tolerance
VIEW 'X'
X
CD
Squareness
Twist
Eccentricity
Crowing
VIEW 'Y'
CD
Parallelism
Y
Wall thickness
CD
= CASTING DIRECTION
12 11 10 9 8 7 6 5 4 3 2 1
H
C-C ( 1 : 1 ) H
A-A
356 10 356 150
6
11
9
2.5 ECC.
80
G G
4.34
12
5.34
4
(386)
F F
C 5 7 3 7 5
28
D
B
65
B
D-D ( 1 : 1 )
E 2 E
D
4.84
C
(380)
D D
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 115.101 91,8 KG 1:2 A1
Replaced by
22 156 10'039'170 -
A A
Sheet: 1 of 1
Material No.
L L
930
8 4 5 4 5
5 18
K
7 19 2 K
29
14
382
399
J 10 J
519
522
OF CASTING RADIUS
11
83
120
1025
(3)
I I
462
503
1
H H
41
93.5
508
900
G G
A-A ( 1 : 2 )
12 16 17
C-C ( 1 : 2 ) D-D ( 1 : 2 ) E-E ( 1 : 2 )
680 760
F F
4 315
19 4 5
45 35
12
16
30
48
20 25
15 15
OUTLET
A
27 13
23
36
23
E E
(8
B
)
30
45
45
OF MOULD
F
270
15
B 8 A E
E 14
93.5
FIXED SIDE
55
20
950
CASTING
850
810
870
DIRECTION
3
540
8
18
D D
45
45
18
ATTENTION :
2 C CARRY
19 2 Hex.THE MOULD SUPPORT
Cap Screw M16X55 MOUNTED
8.8 zinc plated WITH TOP0.125
FLANGE
KG 344872 ONLY. ISO4017
435
18 6 Socket Head Cap Screw M10X45 8.8 zinc plated 0.041 KG 305999 ISO4762
17 1 Street Elbow B16 NPS 1/4 - 3M ASTM A182 0.066 KG 527433 ASMEB16.11
(34 16 2 Union M-F B16 NPS 1/4 - 3M ASTM A182 0.16 KG 527180 ASMEB16.11
INLET
)
B-B ( 1 : 2 ) F-F ( 1 : 2 ) 14 (1:5) 15
14
1
1
Hexagonal Nipple B16
Pipe Seamless ASME NPS 1/4
NPS 1/4 - 3M
13.7x2.24x470
ASTM A105-WP
ASTM A312
0.03
0,292
KG
KG
527020
531484
ASMEB16.11
20 25 D 4 13 1 Globe Valve NPS 1/4" 1/4" NPT F x 1/4" Bronze 0,274 KG 536077 10040013
NPT F
120
2 18 7 3 1/4" NPT 12 9 O-Ring 20x 4 NBR 70.5 0.007 KG 386708 10006417 DIN 3771
6 18 11 3 Elbow Catch 15X195DVP.LG 0.262 KG 380162 10005721
D 10 4 Screw 47.3x200 1.0577 / S355J2+N 1.95 KG 385191 10006416
40
C C
9 2 Block 30x70x145 1.0038 / S235JR+N 2.37 KG 426861 10013496
19 45 90 C 8
7
2
1
Centering Bar
Centre Pin
25x550
20h9x25
1.0577 / S355J2+N
1.0503 / C45
2.05
0.047
KG
KG
385297
383277
10006415
10005993
35 6 1 Pin 28x35 1.0503 / C45 0.098 KG 385135 10006376
5 2 Guide Bolt 25x82 1.0577 / S355J2+N 0,236 KG 540083 10041709
42
330
4 2 Guide Bolt 25x100 1.0577 / S355J2+N 0.237 KG 385327 10006442
3 1 Sealing Protection - 6.19 KG 431908 10014697
2 1 Top Flange - 129 KG 539083 10039325
630 710 50 A 1 1 Mould Support - - 621 KG 539151 10039321
Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
1415 9
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
30 90 30 UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 115.200 776,3 KG 1:5 A0
Replaced by
Approved
05.07.2013
21.06.2013
C603
U039
10'039'065 A
A Sheet: 1 of 1 A
A Mould Support mod. 20.06.2013 U039 Material No.
H A-A ( 1 : 2.5 ) H
OF MOULD
CU-Tube 268526
G G
CASTING
DIRECTION
360.5
F F
A A
108.4 92.6
OF MOULD RADIUS
B-B ( 1 : 1 ) C-C ( 1 : 1 )
7.9
E E
X(1:1)
0.5
R9817.4
920.5
R9917.9
R10018.4
D D
4
5
C C
B B 2
5
4
14
4
Hex. Socket Head Cap Screw
Hex. Cap Screw
M8X16
M8X35
A2-70
A2-70
0.01
0.02
KG
KG
362198
345140
DIN6912
ISO4017
3 4 Bush 20x24 1.4301 / X5CrNi18-10 0.033 KG 385458 10006564
2 1 Flange Plate 419.5x24 1.4301 / X5CrNi18-10 14,9 KG 538453 10039138
1 1 Cooling Jacket - - 52,6 KG 538501 10039137
Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
X THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 67,9 KG 1:2 A1
Replaced by
Approved
10.01.2013
12.12.2012
C603
T089
L L
A-A
< 0.01 Sv/h
A
K K
2
Top of Mould
(137)
B 100% 100%
-61
Working Level
J J
70%
277
B
201
400
2
0% 0%
I 1 I
1
Centerline Radius
517
H H
CASTING
DIRECTION
G G
B-B A
Thickness of:
F F
SECTION SQ.160
3 (Fe)
4 (Fe) 3 (Fe) 4 (Fe) Steel liquid 168mm
83 (H 2O) Steel (Fe) 14,0mm
73 (H 2O) 3.5 (H2O)
3.5 (H2O)
Copper (Cu) 28,0mm
Water (H2O) 163,0mm
E E
Cu
CASTING
H2O DIRECTION
Fe
50
C C
168
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 115810 29,3 KG 1 : 2,5 A0
Replaced by
Approved
17.04.2013
17.04.2013
C603
C603
10'040'707 -
A Sheet: 1 of 1 A
Material No.
5.1 FUNCTION
The mould is mounted on a mould oscillation system.
The oscillating “up and down” movement of the mould prevents the strand shell
from sticking in the mould, which could cause surface defects and breakouts,
promoting a uniform strand shell growths and good surface quality.
5.2 OPERATION
The motion is geometrically matched to the curvature of the casting machine
radius and may be adjusted in stroke and in frequency.
The mould oscillation table has a machined surface and has the water and oil
connections that are sealed with “O” rings when the mould/mould support casing
is placed onto the mould oscillation table.
A hydraulic servo cylinder, mounted on the mould operator side of the oscillator,
generated the oscillation sinusoidal movements.
A servo valve and a digital position controller (direct mounted in/on the hydraulic
cylinder) control the hydraulic cylinder. The cylinder movement is tolerance free
transmitted to the short levers system.
The actual pressure in the hydraulic cylinder is measured by means of a pressure
indicator; the oscillation force and friction in the mould can be recorded.
The mould oscillates according to a sinusoidal function, defined by:
• Frequency : from 20 to 400 stroke per minutes (0.33 to 5 Hz)
• Amplitude (stroke) : from 0 to +/- 10 mm at mould side
• Asymmetry : +/- 11°
These values are the minimum/maximum capacity of the controller, which exceed
the mould limits.
The asymmetry value indicates the deviation to the 90° and 270° points at which
the standard sinus reaches it’s maximum respectively the minimum value.
Amplitude
[mm]
270° 360°
0
0° 90° 180°
-10
For example, with an asymmetry of -30° the sinus curve will start at 0%, goes to
the maximum value (100%) at 60°, goes down and crosses the 0% at 180°, and
reaches the minimum value at 300° before the it rises and goes back to 0% at
360°.
The values nf, mf, cf and CfO are stored in the caster recipe system and these
values are casting product depended.
The values nh, mh, ch and ChO are stored in the caster recipe system and these
values are casting product depended.
h = stroke (mm)
f = frequency (cpm)
The negative strip time (NST) is the decisive figure for closed pouring with
casting tubes and mould powder:
60 1000 Vc
NST arccos
f h f
where:
f = frequency (cpm)
h = stroke (mm)
Vc = casting speed (m/min)
The aim value for the negative strip time is between 0.10 - 0.15 sec. for open
pouring and 0.08 - 0.13 sec. for submerged casting.
Beside the above considerations from the billet surface quality point of view, the
frequency / stroke selection should be such that the resulting mould acceleration
forces are below 4.0 m/s2.
Due to the free programmable oscillation curves, allowed by the hydraulic
oscillation mechanism, negative strip time can be adapted to the specific needs.
The PLC controls if the frequency and stroke values are compatible with the
mechanical limits of the machine, described by the “operational window” shows in
the graph below.
L
A B2248 C L
(1270)
1125
43 175 900 1090
3 562.5 562.5
24 3
(155 )
15.021
K K
180
60
Of Neutral Axis
40 61
120
120
705
J J
30mm)
835= Neutral Position (Cyl.Stroke
646.168
K
1440
(1285)
I
43.811 I
53
901.066
Articulation
(803 )
Fixed Side
580
CASTING
DIRECTION
H H
330
74 1 AN Bulkhead Union 19.1x22x57.2 Galvanized Steel 0.071 KG 541935
73 3 Male Connector with nut-ring 3/8 x 3/8 NPTF Galvanized Steel 0.108 KG 537067 S-600-1-6
72 2 Union 1/4 Galvanized Steel 0.037 KG 540962 S-400-6
71 6 Union Elbow 1/4 - 90 Galvanized Steel 0,052 KG 540959 S-400-9
70 3 Male Tube Adapter 3/8x3/8 Galvanized Steel 0.039 KG 542403 S-6-TA-1-6
69 6 Male Tube Adapter 1/4x1/4 Galvanized Steel 0.024 KG 542401 S-4-TA-1-4
45
68 5 90 Elbow Union with nut-ring 3/8 Galvanized Steel 0.142 KG 530035 S-600-9
67 2 Male Tube Adapter 3/8x3/8 NPT Galvanized Steel 0,039 KG 540928 S-6-TA-1-6
4 2
66 12 Male Connector 1/4x1/4 NPT Galvanized Steel 0.037 KG 540956 S-400-1-4
8 B 9
(28)
G 785 115 C 64
63
4
1
Hex. Cap Screw
Hydraulic Tube Seamless ASME
M8X65
6.35x1.24x13m
8.8 zinc plated
ASTM A519, ASTM A179
0.031 KG 306952
1,85 KG 544792
ISO4014
ASME A519_H_C
G
50 990
31 M30
1/4
Theoretical 62 1 Hydraulic Tube Seamless ASME 9.525x1.65x1.3m ASTM A519, ASTM A179 0,332 KG 544793 ASME A519_H_C
to adjust height 1040 1340 970 3/8
on site ass'y 61 4 Lifting Eye Bolt M30 1.1141 / C15 1.7 KG 369167 DIN580
(1270) 60 1 Hex. Cap Screw M12X40 8.8 zinc plated 0.052 KG 344833 ISO4017
2430 59 4 Washer M12 Steel 0.006 KG 353489 ISO7089
28 58 4 Washer M16 Steel 0.011 KG 353491 ISO7089
32 Shim Plate Machined 57 8 Washer M30 Steel 0.054 KG 353501 ISO7089
After Leveling Oscillation 48 56 1 O-Ring HITEC 40X3,55 NBR 70.5 0.011 KG 327273 DIN3771
Support Beams 55 1 Hex. Nut 0.8d M12 8.0 zinc plated 0.016 KG 306634 ISO4032
29 54 4 Hex. Cap Screw M10X45 8.8 zinc plated 0.038 KG 306955 ISO4014
23 53 20 Hex. Cap Screw M16X40 8.8 zinc plated 0.101 KG 344869 ISO4017
52 4 Hex. Cap Screw M30X160 8.8 zinc plated 1.15 KG 345001 ISO4017
F F
590
25 51
50
4
16
Hex. Cap Screw
Hex. Nut 0.8d
M30X180
M30
8.8 zinc plated
8.0 zinc plated
1.26
0.253
KG
KG
306801
306642
ISO4017
ISO4032
49 56 Socket Head Cap Screw M10X80 8.8 zinc plated 0.062 KG 306005 ISO4762
48 12 Socket Head Cap Screw M12x20 8.8 zinc plated 0.03 KG 420829 DIN7984
For Mould Support Fixation 24 47 2 Socket Head Cap Screw M12X50 8.8 zinc plated 0.063 KG 306031 ISO4762
and Transport 46 22 Hex. Cap Screw M6X12 8.8 zinc plated 0.005 KG 306910 ISO4017
45 1 O-Ring HITEC 75X5,3 NBR 70.5 0.044 KG 327349 DIN3771
44 2 O-Ring 142.2x6.99 NBR 70.5 0,141 KG 443327 10018682 DIN-ISO 3601
43 4 Socket Head Cap Screw M16x200 8.8 zinc plated 0.359 KG 422765 10012688 ISO4762
43 42 6 Spacer - Pipe Clip 12x20x28 1.0038 / S235JR+N 0,051 KG 540043 10041673
7 41 22 Pipe Clip 6,35x6,6 1.0038 / S235JR+N 0,007 KG 539082 10041473 DIN 1592
40 1 Flexible Hose 3/8" 0,335 KG 543448 10043223
110
260
39 2 Flexible Hose 3/8" 0,278 KG 540078 10041676
38 2 Plate 15x76x80 1.0038 / S235JR+N 0.71 KG 507665 10033160
E E
6 37 2 Grease Distributor 4 Outlets 4 Outlets Galvanized Steel 0.000 KG 507500 10033014
26 36 2 Axle Guard 140/40x10 1.0038 / S235JR+N 0.82 KG 479951 10024166 DIN 15058
35 2 Spacer 80x17.5 1.0577 / S355J2+N 0,125 KG 538601 10041157
28 29 34 4 Cylindrical Roller Bearing 100/150x67 - 4.15 KG 420725 10012330 NNF 5020
500 54 59 33
32
4
2
Cylindrical Roller Bearing
Shim Plate
80/125x60
28x210x380
Standard 80
1.0577 / S355J2+N
2.76
16,2
KG
KG
420724
440841
10012326
10017197
NNF 5016
4 29
28
3
2
Center Pin
Bolt
20x25
40x200
1.2510 / 100MnCrW4
1.0503 / C45
0.045
1,66
KG
KG
421064
421063
10012442
10012441
G G 2
51 50 57 27
26
2
4
Bolt
Bolt
80x167
100x145
1.0503 / C45
1.0503 / C45
5,37
5.87
KG
KG
538600
421016
10041155
10012406
=
Strand
1270
52 50 57
915
810
540
750
1010
1220
=
50
E E 15
14
4
4
Flange
Flange
180x16
180x16
1.0038 / S235JR (St37-2)
1.0038 / S235JR (St37-2)
1.85
1.74
KG
KG
421060
421059
10012437
10012429
13 1 Flange 210x14 1.0038 / S235JR (St37-2) 1.72 KG 421023 10012412
56 12 3 Flange 210x14 1.0038 / S235JR (St37-2) 1.76 KG 421040 10012423
11 1 Flange 210x14 1.0038 / S235JR (St37-2) 1.85 KG 421030 10012415
C
3 10 3 Flange 210x14 1.0038 / S235JR (St37-2) 1.89 KG 421042 10012424 C
9 1 Front Splash Guard - - 69.1 KG 545133 10044009
8 1 Rear Splash Guard - 68,2 KG 545144 10044020
29 61 7 1 Template - 3,84 KG 541471 10042292
6 1 Fine Adjusting - - 22,8 KG 439261 10016682
5 1 Oscillation Transport Tool - - 27.3 KG 424109 10013212
4 2 Lever - 91,5 KG 541723 10039218
3 1 Bell Crank - 802,6 KG 541799 10039216
2 1 Oscillation Frame - 964,9 KG 542832 10039215
1 1 Oscillation Table - 868,7 KG 541942 10039217
23 Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
260
48
B B
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
(75) 540 115 Standard Workshop
ISO 128
Section Weight Main Scale Format
Instructions 9800.4 115.600 3.245 TO 1:5 A0
615 Replaced by
Approved
22.01.2013
10.01.2013
C603
SCBR
10'039'208 -
A Sheet: 1 of 3 A
Material No.
D
H
A-A ( 1 : 10 ) B-B ( 1 : 10 ) 12 D-D ( 1 : 10 )
H
562.5
12 20
C-C ( 1 : 10 )
562.5 16
12 19 1270
13 10 = =
17 10 Z 20
18
19
7
Fixed Bearing Loose Bearing Fixed Bearing Loose Bearing
H
24 24
G 25 25 27 6 G
40
16 H
20 11
10 15 15
15 22
22
21 X 21
Loose Bearing Loose Bearing
Fixed Bearing Fixed Bearing 5
26
( Template For
26 26 26
F Y Transportation)
J F
15 21 22
22
21 14 14
14 J
14
1270
D
= =
E
H-H ( 1 : 2,5 ) E
J-J ( 1 : 2,5 )
E-E ( 1 : 2,5 ) F-F ( 1 : 2,5 ) G-G ( 1 : 2,5 )
79
56 29 45 44 (15) 49 15
14 61
125 58
3 53
47
27
D D
65
70
30
M12
80
65
70
Z ( 1 : 2,5 )
( Fixed Bearing ) 27
145
35
Y ( 1 : 2,5 ) 53
X ( 1 : 2,5 ) 98
15 19
M10
14 22 19
21 26 K ( 1 : 10 )
17 60 (17)
60 15.5 67 (15.5)
100
80
70
100
80
70
100
80
B B
210
15 22
26
33 25 25 THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
21 33 2.5 2.5 49 UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
34 53 Standard Workshop
ISO 128
Section Weight Main Scale Format
145 145
1010
= =
Mould Oscillation Assembly Released
Approved
22.01.2013
10.01.2013
C603
SCBR
80 10'039'208 -
A A
Sheet: 2 of 3
Material No.
SMS group
542462
12 11 10 9 8 7 6 5 4 3 2 1
EKI Old File Name: File Name: 10039208_DRF_000.idw
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
L L
K 66 66 66 K
71
72
J
69 J
O
69
71
I 69 I
71
L 70 71 39
71
63 63
40 39
66
74 68
H H
G G
73 Q ( 1 :2,5 )
O ( 1 : 2,5 ) P ( 1 : 2,5 )
S
64 37 R
66 66
66
F F
63 63
63
GREASING ASSEMBLY L-L
69 ( 1:5 ) 38
71
71
a5
66 66
E
65 65 E
N
( 1 : 2,5 ) 70
39 R ( 1 : 2,5 )
68
37 39 65
39 65 39
62 M M 40 62 64
N 66 66
66
73 73
Mould Oil
Greasing
Greasing
67
66
68
68
62 67
C 66 Q C
74
62 68
63 M-M 40
a5
68 ( 1 : 2,5 ) 40
GREASING ASSEMBLY REMARKS:
Mould Oil
MIN. HOLE THREAD DEEP FOR THE FIXATION OF PIPE CLIPS MAT.N 539082,
Greasing
Greasing
Approved
22.01.2013
10.01.2013
C603
SCBR
10'039'208 -
A Sheet: 3 of 3 A
Material No.
SMS group
542462
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
EKI Old File Name: File Name: 10039208_DRF_000.idw
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
L L
K K
J Air G1/8" J
ISO 1179-1
I I
R8
346.5 2
H H
164
G G
ca. 37.5
P
SAE 6000 PSI
1"
SAE J518
115 ca. 37.5 ca. 37.5
53 165 53
563 150
F F
T
SAE 6000 PSI
1"
SAE J518
E E
70 +- 00.015 70 +- 00.015
0
Piston: 90
49 +- 00.15
49 +- 00.15
55
55
Piston rod: 50
C Specification Data: C
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 115600 0.000 KG 1:2 A0
Replaced by
10'043'374 -
A Sheet: 1 of 1 A
Material No.
6.1 INTRODUCTION
Secondary cooling is provided by water sprayed directly onto the bloom surface.
Heat removal from the billet surface occurs by a combination of the following
processes:
- Spray cooling (heat transfer by film boiling)
- Contact with the supporting rolls (solid – to – solid)
- Heat removal by the excess water (especially above the supporting rolls)
- Radiation (the additional contribution of natural convection can be neglected
in comparison with the others)
Due to the relatively low thermal conductivity of steel, the effect of spray cooling
on solidification diminishes as the shell thickness increases. Finally, at some
distance from the mould, depending on the size of the section being cast and the
casting speed, cooling water is no longer useful for solidification.
The purpose of secondary cooling is to produce a billet free of cracks and without
bulging or other shape defects. This is achieved by applying the correct quantity
of secondary cooling water, with the correct distribution in the casting direction.
Q
I
L P VC
The secondary cooling water equipment is designed to give the necessary range
of flows and therefore intensities for the operating parameters of all the section
sizes.
SK t
6.5 CONTROL
Three methods of control are possible:
• Automatic;
• Semi Automatic;
• Manual.
The normal method of control is Automatic: the flow set point of each cooling
zone is calculated based on the casting speed.
In Semi Automatic mode the proportional valve is operated automatically in order
to achieve a certain value of water flow.
In Manual mode, the proportional valve is actuated directly by setting the desired
valve opening.
More information about these three control modes are given in the functional
description.
When Automatic mode is selected, the cooling flow for each zone is defined
according to the mathematical formula for a straight line:
Q m Vc C
300
250 m
200
150
100
C.O. 50
CASTING SPEED Vc
0
c
-50 0 1 2 3 4 5 6
in M/MIN.
As the cooling flow increases proportionally with the casting speed, the cooling
intensity (l/kg) remains constant. (C is usually set to zero. This function is only
used if there is a very wide range of casting speed.)
The flow rate must not be reduced below the one where the pressure at the
nozzle would be so low that the spray cone fan collapses.
This minimum flow is called cut off point (c.o.).
Thus, a cooling curve is defined and stored in the PLC by the following three
figures: m, C and c.o.
Relationship between Water Flow versus Water Pressure at nozzle Tip – single
fluid nozzle (water)
The relationship between the pressure at the nozzle tip and the flow produced
which is defined as follows;
Q1 Q2
or Q1 P 2 Q 2 P1
P1 P2
EXAMPLE
Nozzle type = 3.0 l/min
e.g. From the nozzle type it is known that at the reference pressure of 2.8 bar
the reference flow is 3.0 l/min
If the flow is increased to 4.0 l/min
Q1 P 2 Q2 P1
3 P 2 4 2.8
2
4
P 2 2.8
3
P 2 5 bar
Using this formula it is possible to add up the total reference flows of the nozzles
in a zone and from the total flow in the zone, calculate the pressure in the zone.
The relation between water flow rate and water pressure for air mist nozzles is
not easily described by a simple equation; moreover the relation is different when
different air pressures are used.
For these reasons air/water flow rates versus air/water working pressures are
given as diagrams.
The alternated current and the magnetic field together form the stirring torque.
These two units are connected according to the law of induction and transferred
contactless into the liquid steel core inside the billet.
The direction of the rotating field can be changed by setting a parameter on the
frequency converter.
The current intensity and frequency need to be adjusted if one of the following
parameters is modified:
Casting size
Steel grade
Casting speed
General description
The EMS-housing is inserted into the mould support. The mould and the stirrer
can be removed and replaced from above the casting platform. Electrical
connections are made from the casting platform via flexible cables.
To generate a rotating magnetic field the stirrer uses a six pole, three phase
circuit operating at Error! Reference source not found.. The field penetrates in
the liquid steel inside the mould. Here it sets up a circular motion of the liquid
steel, so that stirring in the mould up to the meniscus level is achieved.
Due to the location underneath the mould cover, the stirrer is well protected
against steel overflows and other casting problems.
400
CL Casting Radius
Zone 1 Row 1&2 Zone 1 Row 3&4
(Water Only) (Water Only)
1 A 95
120
A
2
Zone 1 3 B
4 B
75
70
C
5
C
6
Zone 2a
7
D
95
120
8
D
9
10 75 70
11 CASTING
Zone 2b DIRECTION
12
E
13 C-C ( 1 : 5) D-D ( 1 : 5 )
14 E Zone 2a Zone 2b
15
(Water Only) (Water Only)
16
140
17 F
100
Zone 2c
18
19
F
20
21
100
Zone 3a 140
22
23 CASTING
G DIRECTION
E-E ( 1 : 5 ) F-F ( 1 : 5 )
24 Zone 2c Zone 3a&b
(Water Only) (AirMist)
Zone 3b 25
150
z
26
100
Fixed Side
x
28
Zone 4
29
100 150
CASTING
DIRECTION
G-G ( 1 : 5 )
Zone 4
(AirMist)
150
150
A-A ( 1 : 5) B-B ( 1 : 5)
400
CL Casting Radius
Zone 1 Row 1&2 Zone 1 Row 3&4
(Water Only) (Water Only)
1 A 95
120
A
2
Zone 1 3 B
4 B
75
70
C
5
C
6
Zone 2a
7
D
95
120
8
D
9
10 75 70
11 CASTING
Zone 2b DIRECTION
12
E
13 C-C ( 1 : 5) D-D ( 1 : 5 )
14 E Zone 2a Zone 2b
15
(Water Only) (Water Only)
16
140
17 F
100
Zone 2c
18
19
F
20
21
100
Zone 3a 140
22
23 CASTING
G DIRECTION
E-E ( 1 : 5 ) F-F ( 1 : 5 )
24 Zone 2c Zone 3a&b
(Water Only) (AirMist)
Zone 3b 25
150
z
26
100
Fixed Side
x
28
Zone 4
29
100 150
CASTING
DIRECTION
G-G ( 1 : 5 )
Zone 4
(AirMist)
150
150
6 5 4 3 2 1
Air
Gasket
10 M8x16/20
22
D 38 D
L=Longitudinal
9
50
12
11
15
Water
14
C C
Vendor: Jato
T=Transversal
Material: 2.0401 (CuZn39Pb3) 17660
B B
ALL RIGHTS RESERVED, COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER
Cap Nut Nozzle Tip
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST
NOT BE MADE PUBLIC OR COPIED UNLESS AUTHORISED BY IT AND IS SUBJECT TO RETURN UPON DEMAND
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 175.260 0.91 KG 1 : 1.5 A3
Replaced by
Drawn . . C603
6 5 4 3 2 1
Old File Name: AM4R LONG.IDW File Name: 10035188_DRF_000.idw
A closed water circuit cools the stirrer. The heat is removed by an external
water/water heat exchanger. Flexible hoses connect the stirrer to the supply
pipes. The inlet hose leads first to a strainer which prevents dirt to be transported
into the housing.
Stirrer Design
The stirrer consists of two main parts: the housing and the core. The housing is
made of laminated stainless steel while the core consists of the six copper coils.
The stirrer housing and the cover are made of stainless, non magnetic steel. The
connection hose, the filter housing and the in- and outlet pipes are welded to the
housing. For lifting the complete assembled stirrer three threads M16 in the top
plate of the housing are foreseen (eyebolts shall be screwed in). The stirrer is
placed flat on the mould support.
The core consists of sheet metal rings with six poles to hold the copper coils. The
complete core is held by means of two rings of anti-magnetic steel and the
appropriate connecting rods. The windings of the copper coils are made of a
specially insulated type of copper wire, and after their attachment to the core, the
complete core with coils is impregnated with special resin.
Cooling
The stirrer casing is flowed through by cooling water of specified quality. This
primary water circuit is closed against the environment and run by a water
station. The station consists of circulation pumps, a water tank, a filter, a plate
heat exchanger and several measuring instruments. The piping of the cooling
circuit must be made of antimagnetic (austenitic) stainless steel, in order to
prevent rust form entering into the water circuit.
8.1 INTRODUCTION
The dummy bar and the cast strand are driven and guided by various machine
components. In the direction of casting from the mould are the following: -
The roller apron serves as a support for the cast strand and as guide for the
rigid dummy bar during insertion and withdrawal.
At this plant each strand of the CCM is fitted with 4 strand guiding and strand cooling
containments (segments). The segments are curved, corresponding to the casting radius.
Segment 1
Segment 2
Hinged roller
F-EMS
Segment 3
Segment 4
Slide tubes as
strand support
at fixed side
At segment 2 is a
roller assembly
mounted with an
additional roll at loose
side. This roller
assembly allow the
strand and dummy
bar, to pass in a
Segment 3:
F-EMS
Slide tubes as
strand support
at fixed side
At segment 3 is a
roller assembly
mounted with an
additional roll at
loose side. This
roller assembly
Slide tubes as
strand support
at fixed side
The Withdrawal & Straightening System is a modular type with 2 modules per strand
located after the cooling chamber. The last module is located before the disconnection
device of the dummy bar.
It inserts the dummy bar into the mould before casting start.
It holds the dummy bar head in preparation position above the mould.
It holds the dummy bar in the start position in the mould up to the casting
start.
The last module is also a straightening module and additional the strand
fixation, when the dummy bar disconnection takes place.
Each MSR-module consists of one driven and one idling roll at the loose side, which
can be hydraulically pressed against the strand and fix rolls at the fix side. For dummy
bar insertion the rolls at the loose side can be lifted and lowered. The upper rolls are
guided in linear guides. The motion is done by the same hydraulic cylinder, which is
used for pressing the roll against the strand. The rolls are internally water cooled.
Additional to their function for transport, the hydraulically actuated rolls can be used as
a future option for soft reduction.
The continuously arranged modules straighten the strand out of the casting radius.
The automatic operation of the Withdrawal & Straightening System needs the co-
operation with the whole CCM. The control of these functions needs a high grade of
software co-ordination. The detailed description of the control you will find in the
electrical function description FD291 in chapter 56.
I
m
The 'UP' position is the inactive position while 'DOWN' is the working position.
With the control pushbuttons mounted on the torch cutting desk, the gear motor
and the hydraulic cylinder can be controlled independently in manual mode. In
automatic mode the movement of the crop end pinch roll rocker arm and the
speed of the roll will be controlled accordingly to the casting speed and the hot
F F
2
5784
1
Disconnection device
E E
see section
4721
132200-01
Support structure
see section
130100-03
301
Disconnection
Tangent Axis
Cutting Start
CASTING
16.4
DIRECTION
48.5
-1337.34 -2000
Passline
46.8
C 1 2 3 4 5 6 C
15.9
Strand 4
Strand 3
4 6 Platform 191,2 KG 539059 10041428
3 3 Idle Roller 2,053 TO 538853 10041308
6000
6480
Strand 1
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 130100 70,349 TO 1 : 50 A2
Replaced by
Approved
28.01.2013
28.01.2013
C603
U039
0
480
1510
1990
3020
3500
L 24 18 L
43 A ( 1 : 10 )
C E B-B ( 1 : 10 ) C-C ( 1 : 10 )
2
49
B
57
K 70 61 K
16
58
57 16
17 10
15
15 29
55
42 a4
26
56
F 52 46
8
J J
41 7 14 6 45
67
22 19 64
71
33 54 A H 23
50
11
G
69
I
H 53
I
53 59
20
4 12
21
11 68
5
CASTING
DIRECTION 3
H H
60
Sheet 1 - Part List
51 Sheet 2 - Dimensions
38 13 73 1 Washer M36_ 37/66X5 8 0.092 KG 368227 ISO7089
72 2 Hex. Nut 0.8d M36 8.0 zinc plated 0.434 KG 306644 ISO4032
71 12 Hex. Nut 0.8d M24 8.0 zinc plated 0.129 KG 306640 ISO4032
70 8 Hex. Nut 0.8d M20 8.0 zinc plated 0.075 KG 306638 ISO4032
69 4 Hex. Nut 0.8d M12 8.0 zinc plated 0.016 KG 306634 ISO4032
39 68
67
4
12
Socket Head Cap Screw
Socket Head Cap Screw
M30X80
M24X180
10.9
8.8 zinc plated
0.75
0.79
KG
KG
349695
317656
ISO4762
ISO4762
66 6 Socket Head Cap Screw M24X160 8.8 zinc plated 0.72 KG 317655 ISO4762
G 65 6 Socket Head Cap Screw M24X90 8.8 zinc plated 0.474 KG 317666 ISO4762
G
32 64 23 Hex. Cap Screw M16X90 8.8 zinc plated 0.18 KG 306709 ISO4017
63 16 Socket Head Cap Screw M16X65 8.8 zinc plated 0.146 KG 317584 ISO4762
62 16 Socket Head Cap Screw M16X25 8.8 zinc plated 0.083 KG 317577 ISO4762
61 8 Hex. Cap Screw M36X300 10.9 2.85 KG 349050 ISO4014
1 60 8 Hex. Cap Screw M24X240 8.8 zinc plated 0.98 KG 307039 ISO4014
59 8 Hex. Cap Screw M24X130 8.8 zinc plated 0.59 KG 307032 ISO4014
58 4 Hex. Cap Screw M24X60 8.8 zinc plated 0.342 KG 306566 ISO4017
57 8 Hex. Cap Screw M20X45 8.8 zinc plated 0.186 KG 306739 ISO4017
36 56 4 Hex. Cap Screw M16X30 8.8 zinc plated 0.085 KG 306699 ISO4017
D 55
54
4
2
Hex. Cap Screw
Hex. Cap Screw
M12X40
M12X30
8.8 zinc plated
8.8 zinc plated
0.052
0.043
KG
KG
306671
306669
ISO4017
ISO4017
44 53 8 Hex. Cap Screw M12X25 8.8 zinc plated 0.038 KG 306668 ISO4017
52 4 Lifting Eye Bolt M36 1.1141 / C15 2.73 KG 369166 DIN580
F F
51 3 Pipe Plug 1" Stainless Steel 0.27 KG 545357 SS-16-P
37 50
49
2
1
Rival Y Ring
Clevis Pin with Head
20-173
12X100
NBR 70
Steel
0.02
0.097
KG
KG
528836
350948
SN 853
ISO2341
48 4 Spring Cotter (Double Coil) 7x130 Standard 00 0.014 KG 476840 DIN 11024
47 3 Precision Dowel Pin 20H8X40 Steel 0.094 KG 339159 ISO2338
C B 46
45
2
2
Sleeve
Sleeve
115x10
115x10
1.0577 / S355J2+N
1.0577 / S355J2+N
0,187
0,162
KG
KG
546864
546862
10044801
10044800
44 4 Shim for Bolt 61x5x26 1.0330 / DC01+LC 0,18 KG 535311 10042457
43 1 Spring cotter 3.2 DIN 11 024 8.5x25.9x61 - 0.000 KG 539023
42 2 Numbering 1.0038 / S235JR+AR 0.211 KG 540306 10041741
E ( 1 : 10 ) F(1:5) 41
40
2
1
Name Plate
Shim Foot
1.5x85x170
68x140x145
3.3535 / AlMg3 (EN AW-5754)
1.4301 / X5CrNi18-10
0.052
6,59
KG
KG
393987
538996
10007717
10041214
48 39 4 Sleeve 23x20 CC493K / CuSn7Zn4Pb7-C 0,037 KG 539010 10041403
E 25 without Protecting Plate G ( 1 : 10 ) 38 4 Sleeve 27x20 CC493K / CuSn7Zn4Pb7-C 0,045 KG 539007 10041401
E
35 37 4 Wedge 14.1x58.5x250 1.0503 / C45 1.37 KG 320814 10000888
7 without Roller Support 36
35
4
4
Bolt
Bolt
50x75x719
36x120
1.7225 / 42CrMo4 + QT
1.0577 / S355J2+N+Z15
7,42
0.92
KG
KG
539000
535218
10040794
10039484
34 1 Bolt 40x80x150 1.7225 / 42CrMo4+QT 1.89 KG 535219 10039139
66 33 1 Protection Plate 1004.1x250x1.5 1.4841 / X15CrNiSi25-20 2.67 KG 538570 10041168
28 32 8 Round 69x60 1.7225 / 42CrMo4+QT 1,47 KG 535217 10039140
65 31 2 Shim Foot 68x140x145 1.4301 / X5CrNi18-10 10.18 KG 535216 10039477
D ( 1 : 10 ) 51
27 30
29
1
1
Shim Foot
Plate
68x140x145
30x300x555
1.4301 / X5CrNi18-10
1.0577 / S355J2+N
6.09
36.7
KG
KG
318468
535220
10000775
10039479
47 62
28
27
4
4
Plate
Plate
41x240x330
28.5x130x220
1.0503 / C45
1.7225 / 42CrMo4+QT
25.3
5.88
KG
KG
539021
537408
10041420
10040732
30 9 26 2 Bolt 102x102x238 1.7225 / 42CrMo4+QT 14.6 KG 535889 10039483
C
31 51 H-H ( 1 : 5 ) 11
10
1
2
Holding
Cylinder Assembly
- 259,8
390,4
KG
KG
538583
539040
10039064
10041424 C
9 1 Torsion Compensator 166,1 KG 538743 10038617
8 1 Roller Support - 320,3 KG 538582 10038647
7 1 Guide right 87,8 KG 538747 10039487
6 1 Guide left 87,8 KG 538756 10041255
5 1 Drive Roller 655,9 KG 540048 10041557
4 1 Idle Roller upper 616 KG 539249 10041510
3 2 Idle Roller bottom 695,4 KG 538744 10041509
2 1 Gear and Motor unit 906,1 KG 538999 10040043
1 1 Fixed Frame - 4,383 TO 542689 10039615
Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
B B
CASTING
72 73 1 34 2
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 10,532 TO 1 : 10 A0
Replaced by
Approved
28.01.2013
28.01.2013
C603
U039
10'041'249 -
A Sheet: 1 of 2 A
Material No.
H H
I ( 1 : 15 )
MSR-Modul Nummer - ....
G
lifting eye M36 G
Position for Segment both Sides
Numbering (track welded) 1.1 Pressure test hydraulic
Signature/Date ........................
5mm Shim Package
NPT 1/4"
+170 mm Stroke
for Lubrication
3256
I 2.0 Pressure test water
NPT 1" Signature/Date ........................
NPT 1/4" for Water MPa Time (min) Result
F for Lubrication move 0.8 30 F
CASTING
(145) 3.0 Pressure test lubrication
DIRECTION Signature/Date ........................
120 calibration
250
MPa Time (min) Result
20 10
5mm Shim Package
0.25
fix
958
61
51
L
50
900 1175
D D
L ( 1 : 15 )
657.5 70
C 207.5 37 C
NPT 1"
for Water
NPT 1"
for Water fix (heat expansion)
K
J
676
516
J(1:5) 70 37 THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
NPT 1" 52.5 1315 Standard Workshop Section Weight Main Scale Format
for Water ISO 128
40 Instructions 9800.4 10,532 TO 1 : 10 A1
Replaced by
32
Approved
28.01.2013
28.01.2013
C603
U039
10'041'249 -
A Drilled together with frame and fixed by dowel pin A
Sheet: 2 of 2
Material No.
SMS group
538742
12 11 10 9 8 7 6 5 4 3 2 1
CZH Old File Name: File Name: 10041249_DRF_000.idw
12 11 10 9 8 7 6 5 4 3 2 1
H H
A ( 1 : 10 )
3
CASTING 11
DIRECTION
17
10
Disconnection device 3
G see section G
132200-01 4
16
1
15
A
9
F F
12
13
8
E B E
D D
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 130.100 2,053 TO 1 : 10 A1
Replaced by
7 7 Released 23.01.2013 C603
Idle Roller Approved 21.01.2013 V627
10'041'308 -
A A
Sheet: 1 of 2
Material No.
H
385 690 250 C ( 1 : 10 ) H
232
CASTING
DIRECTION
lifting eye
20
753 (+200mm Stroke)
NPT 1"
958
G G
for Water
733
C
NPT 1/4"
for Lubrication
NPT 1/4"
for Lubrication
water outlet NPT 1" water inlet
26mm (Shim)
for Water
469
F F
61
D 51
Cylinder 1
900 A,B 50
730 816
1460 1175
E E
MSR-Modul No - ....
C
D ( 1 : 10 ) 3.0 Pressure test lubrication C
516
14
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 130.100 2,053 TO 1 : 10 A1
Replaced by
Drilled together with frame and fixed by dowel pin
Released 23.01.2013 C603
Idle Roller Approved 21.01.2013 V627
Drilled together with frame and fixed by dowel pin Drawn 20.11.2012 SCMC
Document No. Version
10'041'308 -
A A
Sheet: 2 of 2
Material No.
SMS group
538853
12 11 10 9 8 7 6 5 4 3 2 1
EKI Old File Name: File Name: 10041308_DRF_000.idw
16 15 14 13 12 11 10 9 8 7 6 5 4 3 2 1
L 23 17 L
E 40 A ( 1 : 10 ) B-B ( 1 : 10 ) C-C ( 1 : 10 )
2
47
C B
54
K 67 57 K
15
55
54 16 10 15
28 14
14 52
39
a4 25 42
F 49
53 8
J J
6 43
38 7 13
77
21 18 60
68
32 51
A H 22
48
11
G
66
I
H 63
50
I
50 56
19
4 71
20
11 65
CASTING 5
DIRECTI
ON
Sheet 1 - Part List different from MSR2
76
H Sheet 2 - Dimensions H
73 3
77 6 Socket Head Cap Screw M24X140 8.8 zinc plated 0.65 KG 317653 ISO4762
76 4 Hex. Cap Screw M24x290 8.8 zinc plated 1.02 KG 500592 10030558 ISO4014
74 64 75 4 O-Ring HITEC 34,5X3,55 NBR 70.5 0.009 KG 327251 DIN3771
74 6 Sleeve 27x20 CC493K / CuSn7Zn4Pb7-C 0,045 KG 539007 10041401
72 12 73 6 Sleeve 23x20 CC493K / CuSn7Zn4Pb7-C 0,037 KG 539010 10041403
72 2 Plate 48x110x460 1.0577 / S355J2+N 18.4 KG 538922 10041352
71 1 Holding - 176,5 KG 542402 10041346
70 1 Washer M36_ 37/66X5 8 0.092 KG 368227 ISO7089
69 2 Hex. Nut 0.8d M36 8.0 zinc plated 0.434 KG 306644 ISO4032
75 68
67
12
8
Hex. Nut 0.8d
Hex. Nut 0.8d
M24
M20
8.0 zinc plated
8.0 zinc plated
0.129
0.075
KG
KG
306640
306638
ISO4032
ISO4032
66 4 Hex. Nut 0.8d M12 8.0 zinc plated 0.016 KG 306634 ISO4032
G 65 4 Socket Head Cap Screw M30X80 10.9 0.75 KG 349695 ISO4762
G
44 31 64 4 Hex. Cap Screw M24X240 8.8 zinc plated 0.98 KG 307039 ISO4014
63 6 Socket Head Cap Screw M24X180 8.8 zinc plated 0.79 KG 317656 ISO4762
62 6 Socket Head Cap Screw M24X160 8.8 zinc plated 0.72 KG 317655 ISO4762
61 6 Socket Head Cap Screw M24X90 8.8 zinc plated 0.474 KG 317666 ISO4762
1 60 23 Hex. Cap Screw M16X90 8.8 zinc plated 0.18 KG 306709 ISO4017
59 16 Socket Head Cap Screw M16X65 8.8 zinc plated 0.146 KG 317584 ISO4762
58 16 Socket Head Cap Screw M16X25 8.8 zinc plated 0.083 KG 317577 ISO4762
57 8 Hex. Cap Screw M36X300 10.9 2.85 KG 349050 ISO4014
35 56 8 Hex. Cap Screw M24X130 8.8 zinc plated 0.59 KG 307032 ISO4014
D 55
54
4
8
Hex. Cap Screw
Hex. Cap Screw
M24X60
M20X45
8.8 zinc plated
8.8 zinc plated
0.342
0.186
KG
KG
306566
306739
ISO4017
ISO4017
41 53 4 Hex. Cap Screw M16X30 8.8 zinc plated 0.085 KG 306699 ISO4017
52 4 Hex. Cap Screw M12X40 8.8 zinc plated 0.052 KG 306671 ISO4017
F F
51 2 Hex. Cap Screw M12X30 8.8 zinc plated 0.043 KG 306669 ISO4017
36 50
49
8
4
Hex. Cap Screw
Lifting Eye Bolt
M12X25
M36
8.8 zinc plated
1.1141 / C15
0.038
2.73
KG
KG
306668
369166
ISO4017
DIN580
48 2 Rival Y Ring 20-173 NBR 70 0.02 KG 528836 SN 853
47 1 Clevis Pin with Head 12X100 Steel 0.097 KG 350948 ISO2341
C B 46
45
4
3
Spring Cotter (Double Coil)
Precision Dowel Pin
7x130
20H8X40
Standard 00
Steel
0.014
0.094
KG
KG
476840
339159
DIN 11024
ISO2338
44 3 Pipe Plug 1" Stainless Steel 0.27 KG 545357 SS-16-P
43 2 Sleeve 115x10 1.0577 / S355J2+N 0,162 KG 546862 10044800
42 2 Sleeve 115x10 1.0577 / S355J2+N 0,187 KG 546864 10044801
E ( 1 : 10 ) 41
40
4
1
Shim for Bolt
Spring cotter 3.2 DIN 11 024
61x5x26
8.5x25.9x61
1.0330 / DC01+LC
-
0,18
0.000
KG
KG
535311
539023
10042457
E
46 F(1:5) 7 G ( 1 : 10 )
39
38
2
2
Numbering
Name Plate 1.5x85x170
1.0038 / S235JR+AR
3.3535 / AlMg3 (EN AW-5754)
0.211
0.052
KG
KG
540306
393987
10041741
10007717
E
24 37 1 Shim Foot 68x140x145 1.4301 / X5CrNi18-10 6,59 KG 538996 10041214
34 without Protecting Plate without Roller Support 36
35
4
4
Wedge
Bolt
14.1x58.5x250
50x75x719
1.0503 / C45
1.7225 / 42CrMo4 + QT
1.37
7,42
KG
KG
320814
539000
10000888
10040794
34 4 Bolt 36x120 1.0577 / S355J2+N+Z15 0.92 KG 535218 10039484
62 27 33 1 Bolt 40x80x150 1.7225 / 42CrMo4+QT 1.89 KG 535219 10039139
32 1 Protection Plate 1004.1x250x1.5 1.4841 / X15CrNiSi25-20 2.67 KG 538570 10041168
61 31 8 Round 69x60 1.7225 / 42CrMo4+QT 1,47 KG 535217 10039140
26
D ( 1 : 10 ) 30
29
2
1
Shim Foot
Shim Foot
68x140x145
68x140x145
1.4301 / X5CrNi18-10
1.4301 / X5CrNi18-10
10.18
6.09
KG
KG
535216
318468
10039477
10000775
45 44 58 28
27
1
4
Plate
Plate
30x300x555
41x240x330
1.0577 / S355J2+N
1.0503 / C45
36.7
25.3
KG
KG
535220
539021
10039479
10041420
29 26 4 Plate 28.5x130x220 1.7225 / 42CrMo4+QT 5.88 KG 537408 10040732
B B
CASTING
69 70 1 33 2
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Section Weight Main Scale Format
Standard Workshop
ISO 128
Instructions 9800.4 10,482 TO 1 : 10 A0
Replaced by
Approved
28.01.2013
28.01.2013
C603
U039
10'041'821 -
A Sheet: 1 of 2 A
Material No.
H H
I ( 1 : 15 )
MSR-Modul Nummer - ....
G
lifting eye M36 G
Position for Segment both Sides
Numbering (track welded) 1.1 Pressure test hydraulic
Signature/Date ........................
5.4mm Shim Package
+170 mm Stroke
for Lubrication for Water
3256
I 2.0 Pressure test water
NPT 1/4" Signature/Date ........................
for Lubrication
MPa Time (min) Result
48.5
F move 0.8 30 F
CASTING
DIRECTION
(145) 3.0 Pressure test lubrication
122.2 calibration
250 Signature/Date ........................
46.8
fix
1004.7
61
51
L
50
900 1175
D D
L ( 1 : 15 )
657.5 70
C 207.5 37 C
NPT 1"
for Water
NPT 1"
for Water fix (heat expansion)
K
J
676
516
K(1:5)
J(1:5) THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
NPT 1" 52.5 1315 70 37 Standard Workshop Section Weight Main Scale Format
for Water ISO 128
10,482 TO 1 : 10 A1
37 Instructions 9800.4
Replaced by
32
Approved
28.01.2013
28.01.2013
C603
U039
Drilled together with frame and fixed by dowel pin 45 Document No. Version
10'041'821 -
A A
Drilled together with frame and fixed by dowel pin Sheet: 2 of 2
Material No.
SMS group
542812
12 11 10 9 8 7 6 5 4 3 2 1
CZH Old File Name: File Name: 10041821_DRF_000.idw
CHAPTER 2
CASTING OPERATIONS
TABLE OF CONTENTS
In most cases a basic gunning mix is used for the working lining, with a
composition that is chemically inert towards liquid steel. (normally, MgO,
which ensures longer casting time).
It is also possible to use dry settling mixes, which are poured in place around
a template. Heating the template makes the mix sinter and form a monolithic
layer.
The working lining facilitates cleaning after use and is to be newly applied
after every cast.
The thickness of the spray-gunned layer is about 30 mm and about 50 mm on
the slag-line.
After spraying the tundish should be dried in the drying station according to
the curve given by the refractory supplier. After drying the tundish can be let
cool down to room temperature without prejudice for the refractory lining.
The typical drying sequence is:
Raise the temperature to 600°C in 1 hour
Hold tundish at 600°C for 2.5-3 hours
600
500
400
Tem perature (°C)
300
200
100
0
0 30 60 90 120 150 180
Time (minutes)
2.1. INTRODUCTION
The Dummy Bar (D/B) is a rigid bar which has the same radius of crvature as
the casting machine. The purpose of the Dummy bar is to seal the mould at
the start of a cast, and after the first liquid steel is poured into the mould, to
withdrawn the solidifying shell.
When the connection between the Dummy Bar and strand reaches the raised
straightener roll, the roll is lowered and the disconnection is made. The
Dummy Bar plays no further part in the casting process, and is raised into its
storage device and parked, ready for the start of the next cast.
The front end of the Dummy Bar has a transition piece, which is changed for
different section sizes.
2.2. DESCRIPTION
The Dummy Bar system consists of a solid bar made up of several sections
and a section dependent transition piece with a permanent Dummy Bar head.
Located behind the Withdrawal / Straightening unit is the storage device
consisting of a cassette with a built in Dummy Bar pinch roll. The cassette can
be lowered and raised by a hydraulic cylinder.
The steel plates protect the D/B head from the first steel, which enters the mould during
mould filling. The initial steel poured into the mould melts immediately the plastic material
1
3
After a cast the mould has to be well cleaned and inspected for possible
damage. Before commencing the mould walls must be dry, i.e. free of
Scheme of the Conseal IV Assembled and scheme of the assembled Pin (at
the bottom of the picture)
Some extra chill material is necessary to seal the mould. Scrap may prevent
to form a proper claw and with this cause a premature disconnection of the
D/B and strand of the D/B and strand.
I
f
t
h
e
D
/
B is inserted too far
inside the mould it must
be removed completely
and another CONSEAL head installed before re-insertion.
The CONSEAL condition should always be checked inside the mould with
flashlight. If it is torn or in any way distorted it should be replaced.
Before accepting a first ladle of a sequence onto the Ladle Turret the Casting
Supervisor should check that all the necessary conditions are present to allow
permission to cast.
The correct Section Size and Casting Mode should be selected on the HMI in
the Main Control Room and if Level 1 Recipe control is being used then the
correct Recipe for the Steel Grade should be selected.
A Ready To Cast condition will be given when all the Necessary to Cast
permissives are shown as Green on the Ready to Cast screen shown below.
Should any of the necessary conditions that are mandatory to cast not be met
then the operator can interrogate the fault by using the relevant drop down
dialogues, to rectify it. Obviously the ladle should not be opened without a
Ready to Cast condition.
It is advisable also that all Suggest to Cast conditions are fulfilled also,
however if one of these permissives is not met a Ready to Cast condition is
still fulfilled.
5.1. INTRODUCTION
When the liquid steel has been prepared and the casting machine is ready to
cast, the ladle is transferred from ladle treatment to the ladle turret.
This module gives information on the operations concerning the ladle and
tundish. Specific information on the casting technique is given in a separate
module
With a preheated tundish practice the most important aim is to retain as much
heat as possible in the tundish refractory from the time the preheat ends to the
time the ladle is opened.
This manual describes the automatic methods available on the casting floor.
Full details of the manual options should be obtained from the functional
descriptions.
Time-consuming operations like tundish transport and preparation at the
casting position (alignment, centring of casting tubes, etc.) must take as short
a time as possible. Automatic cycles are provided to reduce these times to a
minimum, and to reduce the possibility of errors.
After the casting leader has checked that all necessary preparation work has
been done ("ready to cast" status available in the VDU and on the MOP (
Mould operators Panel), protection devices and ladle shrouds in position etc.),
the command is given to open the ladle slide gate. In principle the tundish
should be filled as fast as possible, although in the case of a machine with
many strands it may be necessary (depending on the casting system) to
throttle back the ladle slide-gate such that the tundish does not become
completely full before all the strands have been opened.
The following duties are usually the responsibility of the ladle operator.
Connection and disconnection of hydraulic and pneumatic
couplings for the slide gate, and mounting and removing of
the slide gate hydraulic cylinder
Ladle car operation
Tundish filling by manual or automatic slide gate control
If the slide gate is manually controlled, maintaining the
tundish steel working level to +/- 1.0 t steel weight
Executing tundish temperature measurements and taking
steel samples
Liaison with the casting foreman and the mould operators
Checking that steel bath insulation is maintained
Maintaining a safety watch for slide gate oil leakage’s and for
hot spots on the ladle shell
Using a slide gate, the opening position can be chosen so that an equilibrium
between steel quantity flowing out of the ladle and being cast into the moulds
can be achieved, e.g. the slide gate remains at a constant setting and its
For using the ladle shroud the following actions have to be performed.
Start of cast
Put Ladle Shroud Tube in the manipulator
Bring tube with the manipulator into tundish after tundish lowered into
casting position
Turn ladle into casting position
Attach ladle shroud
If ladle opens lower ladle into normal casting height
If not, put ladle shroud side-ways and lance open
Cast approx. 2 min with open stream, close slide gate, connect shroud,
open slide gate and lower ladle
Note1: the tundish weight drops quickly when only slag is teamed
Note2: the value of the closure weight of the liquid steel remaining in ladle at
the empty ladle time is considered as in the customer official procedures
(usually 3-6 tons)
The oxygen lancing of the slide gate nozzle at start or during teeming has to
be performed from the area between ladle car support and tundish just below
the ladle, i.e. at the hot metal side where no protection guard against
splashing steel can be installed.
Sequence casting is the casting of more than one ladle through the same
tundish increasing the yield and the machine utilisation. Ideally the following
conditions need to be fulfilled:
Only similar steel qualities should be cast in sequence;
The ladle changing time, i.e. the time between emptying one ladle and opening
the slide gates of the next ladle must be such that the tundish weight never
drops below a critical level at which quality problems can occur (A critical
aspect of successful sequence casting is that the ladle opens without the need
for lancing).
If the ladle nozzle becomes blocked by cold steel or inclusion build up it can
be opened again by oxygen lancing. The level in the tundish should, as in the
case of a sequence casting ladle changeover, not drop below a critical level
for quality reasons.
Any oxygen lancing will have a negative influence on the level of steel
cleanness.
If the ladle requires repeated lancing to maintain the necessary flow, it may be
necessary to decide to stop the cast depending on the quality requirements of
the steel being cast.
A. CHEMICAL PRECONDITIONS
Open casting is normally used for non-demanding Si-killed commercial steels.
Aluminium total content must be minimised to prevent alumina deposits on the
metering nozzles, which interfere with the open stream and eventually block
the nozzles. Generally, the following limits are applied;
B. OPERATIONAL CONCEPT
Flow rate from the tundish is a function of the nozzle diameter and the liquid
steel level in tundish
Automatic mould level control is achieved by control of withdrawal speed.
Mould lubrication is achieved by vegetal oil or suitable mineral oil.
The tundish nozzles have to be properly aligned with the moulds. To shorten
the preparation time immediately before casting, it is recommended to pre-
align the tundish before preheating by driving it over the moulds to check the
alignment. Visual nozzle alignment checking can be achieved using the simple
tool shown in the appended drawing 16244.4.
During handling and preheating, the tundish nozzles are susceptible to
becoming blocked with loose refractory material and/or low melting point
materials, which have melted during preheating.
Difficulties, particularly during the start of casting, will thus result, unless some
precautions against blockage are taken.
In addition to this problem, reliable self-opening of the nozzles after steel flow
from the ladle commences is not guaranteed, particularly on the outer nozzles
D. STARTING METHOD
This sealing method is generally used in combination with the CNM, because
the design of the fixed nozzle in this case allows reliable positioning of the disc
(see drawings).
A steel disc is placed flat on the nozzle prior to start tundish preheating:
Thickness 2 – 2.5 mm
Diameter Depending on nozzle design (normally 40 mm)
This disc should be fixed by mortar to ensure a good seal. The disc should
not be covered with the mortar, since this will make strand opening much
more difficult. The disc can be positioned before preheating, but care must
be taken to avoid burning it open with the nozzle preheater flames.
Normally, the disc needs a short blow with the oxygen lance to be opened.
25
READY TO CAST A RUN OUT BILLET LENGTH
OPTIMIZATION
MODE SELECTOR
CASTING
PREPARE
RUN-OUT
DUMMY
BAR
POURING TUBE MOULD SLAG NOT SPECIFIED OFF
FAULT FAULT FAULT
BILLET ACTUAL LENGTH
MAX. LEVEL
FULL CALIBR.
1 6 14
SET-POINT m/min
SOURCE
OPEN
7 12 13 15
ALARM READY MIN. LEVEL DECREASE INCREASE
CALIBRATION SET-POINT SET-POINT
2 3 8 16 17
CLEANING LOCAL REMOTE
CLOSE MANUAL AUTOMATIC MOULD FILL
CYCLE CONTROL CONTROL
4 5 9 10 11 18 19
STOP START
WITHDRAWAL WITHDRAWAL
POWDER
OFF
POWDER
ON
CONTROL
ON/OFF 20 21
MOULD OSCILLATION
22
STOP START
AMOUNT
23 LAMP TEST
24
Hand box
connector
From To MOP
CC = 0÷30mm
After arrival of the tundish to the mould ensure, the alignment is correct.
Switch the selector on the MOP to “Casting”.
Select "Automatic" on the MOP. (Auto button flashing on MOP). No operator
input will then be required to start the withdrawal drive.
Check if "Ready" lamps are on and "Alarm" lamps are off. If these conditions
are not available it is necessary to check on the VDU screen in the control
room.
Open the Ladle.
When the correct tundish level has been reached, open the strands.
If the stream is not compact, the flow is too slow, or in the worst case, it freezes
completely, the emergency launder must be swung in position.
With the Oxygen lance the nozzle shall be burned free and, after a good steel
stream is steady, the emergency launder can be swung out so that casting can
actually start in Automatic mode.
10 END OF CASTING
After the ladle has been emptied, the casting speed steadily decreases due to
the dropping metal level in the tundish.
When casting with metering nozzles, the pouring must be stopped at the latest
when the steel stream becomes unstable.
This is achieved by inserting a copper plug into the nozzle bore. (see
appended drawing 15156.4). If available, the emergency launder must be
swung in position just before plugging the strand.
This operation must be performed before the steel stream becomes too
unstable, as this signifies that slag could enter the mould very soon.
Note: when casting with CNM the strand is stopped by firing in a blind block. If
this is not available for some reason, the strand should be stopped
manually as described above.
11 CASTING IRREGULARITIES
A. OPEN-NOZZLE LANCING
Oxygen is a valuable tool for the mould operator if used carefully. Only skilled
operators should perform this operation. Lances must be free of oil or grease.
Oxygen lancing should be applied only as a "last measure" due to the adverse
effect on steel internal cleanness and the erosion of the refractory metering
nozzle.
B. MOULD OVERFLOW
If the strand becomes stationary for any reason, an overflow can result. The
mould level control system detects this event and fires in the blind block. If this
is not available for some reason, the action to be taken is the same described
above (with open casting without CNM).
If the steel has overflowed over the top of the mould, no attempt should be
made to withdraw the strand, as the shell could be torn resulting in metal
spillage beneath the mould area.
If there is no way to remove the strand quickly, it must be cut beneath the
mould, so that the rest of the strand can be withdrawn from the machine. The
mould can be changed later and the shell removed in the mould shop.
If the strand solidifies fully in the mould, the machine (oscillation) geometry
can be distorted.
C. BREAKOUTS
A strand breakout is a spillage of liquid steel from the cast strand anywhere
beneath the mould area, mostly just beneath the mould in the top zones.
Its severity depends on the point of rupture, and usually those occurring far
down the metallurgical length are the most damaging due to the amount and
pressure of liquid steel above.
system and the blind block will be fired in. If there is no blind block, or the
CNM is not in use, the first action must be to swing the emergency launder in
D. MOULD HANGER
If the steel stream is not compact, it is possible that sparks or small splashes
can build up on the mould walls, mould top plates or cover-plates. This can
slowly increase in severity and grow downwards toward the liquid level in the
mould. This build up must be removed with a steel bar or in the worst case
oxygen lance before it becomes a critical size.
If the hanger is allowed to progress down to the meniscus level it will become
connected to the steel shell and a tear will occur possibly resulting in a
breakout.
12 METERING NOZZLES
Zirconia is now widely used for metering tundish nozzles and gives long and
reliable service without significant erosion.
Where increased erosion and chemical attack resistance is required, i.e. long
term casting, low-carbon steels with high oxygen content, free cutting Si-Mn
steels etc., zirconia provides the necessary properties.
h 6
G 2 g F
1000 100
Values:
= 0.90 ÷ 1.0
g = 9.81 m/sec2
= 7.2 kg/cm3
The factor is dependent on the fluidity of the steel. A commonly used value
for is 0.92, however it may be found that after some experience the value
can be optimised due to local conditions.
When open casting, the casting speed can be changed to a certain degree by
increasing or decreasing the bath level in the tundish. This is not
recommended as a regular practice due to the adverse effect on the product
quality caused by the unstable conditions in the tundish.
After De-sculling the Tundish should be cleaned of any remaining steel, slag or
adhered refractory material. The permanent lining should then be visually
inspected and repairs effected if necessary.
The Tundish furniture can then be installed e.g. Turbostoppers, Dams and Weirs
etc.
If required new well blocks can also be installed at this stage.
Once the Tundish has cooled down to approximately 90°C, the sprayed working
lining can be applied, ensure that a sealing cone is inserted into the well block to
prevent spray mass sticking to its internal surfaces.
Generally a coating thickness of 30mm over the whole surface is sufficient with
the area of the slag line increased to approx. 50mm depending on the intended
sequence length.
When spraying is complete ,the cones should be removed and the tundish
transferred to the drying station, and dried in accordance with the refractory
supplies drying curves.
Once dried the SEN or Tundish Nozzle can be installed and fixed with refractory
mortar.
The stopper installation takes place with the covers and tundish nozzles / SEN’s
in place and with the stopper already fitted with its threaded rod.
The threaded rod with all its bolts and washers must be secured to the stopper
rod before mounting the latter into the cross arm. The following drawing displays
the correct position of all the needed parts.
IMPORTANT: Before installing the stopper rod, bring the cross arm in the
intermediate position by turning the hand wheel. The position of the cross arm is
indicated by the arrow in the viewing window of the stopper box. The
intermediate position is necessary for the correct installation.
Unfix the cross arm bolt: this bolt blocks the cross arm horizontal movement
around the stopper arm (vertical).
Move the cross arm sufficiently to insert the stopper rod.
Insert the stopper rod through the cover hole taking care that the rod tip does
not enter the SES/SEN bore.
Using the hand wheel on the stopper control box, move the cross-arm up or
down until it is approximately in the middle of the stroke. This is indicated in the
window of the stopper box.
Put the stopper tip in the SEN top and the Rod End in the fork of the cross-
arm, hand tighten the cross-arm nut.
Align the cross-arm such that it is aligned vertically over the SEN bore.
Raise the stopper with the hand wheel and tighten the cross-arm nut with a
spanner.
Hand tighten the stopper rod top and bottom nut and the align stopper such
that it is vertical over SEN. Check by opening and closing.
Close stopper and hold closed, tighten top nut with spanner.
With the hand-wheel, open and close for final check stopper to verify that:
the stopper can move vertically
the Stopper tip can enter and block the opening of the SES / SEN without any
lateral movement of the stopper when entering or leaving the closed position. No
STOPPER SETTING 2
8
Drive tundish car over moulds and align the tundish “front to back” and check
the alignment of the SEN “side to side” with the moulds.
Return to preheating position.
Final check of stopper alignment by opening and closing the stopper with the
hand wheel.
Raise to fully open position and lock the hand wheel.
Connect cooling air and nitrogen pipes to stopper box.
Plug power and signal cables for stopper control to sockets in stopper box.
On Casting Floor:
Removing of stopper box and fork arm from the tundish (and SEN/SES and
slide gates if not already removed)
Remove tundish lids.
Bring tundish to tundish tilting station and tilt for dismounting emergency slide
gates and removal of slag, skull, working lining and rest of nozzles. This work is
usually done within 1 hour after end of casting
Transport tundish to parking or lining stands
Cool down with ventilator unit to a temperature that allows stepping into
tundish
Check impact area (change impact bricks if damaged)
Mount the intermediate walls
Set new SEN’s/SES’s, ensuring proper alignment
Cover the SEN tops
Apply the working lining
Drying according to the refractory supplier specification
Position tundish lids
2.1. MAINTENANCE
New moulds rarely give problems initially, although it is always a good practice to
record the mould cavity dimensions when new as a basis for subsequent
evaluation of the mould's condition.
The mould geometry is of greatest importance to the achievement of a perfect
cast product. The steel plant needs to keep a check on the actual dimensions of
the mould tube and of the taper throughout its service life. This should be
measured in the new condition and during the life of the tube at periodic intervals,
such checking enables the engineer to establish criteria for replacement by
setting up lifetime records.
Inspection record sheets should be used for keeping track of the mould history by
entering number of strand, date and cast numbers the mould has been used for
and to note incidents like breakouts and possible strand defects.
Cavity checks approximately every 100 casts when casting open and every 50
heats when casting submerged will provide a picture of mould performance and
be the basis for re-ordering and re-conditioning.
Mould life depends upon many factors:
• Cooling water quality
• Handling care (physical damage)
• Lubrication medium
• Breakout and overflow rate (physical damage)
Correct assembly of the moulds is very important. Particular care must be taken
when installing a new tube in a water jacket to ensure that the lower seal permits
the mould to expand during casting.
The limit for the mould wear in the bottom part is approximately 1 mm (compared
with the new tube), measured 25 mm above the tube exit (measure between
curved faces must be taken in the radial direction).
3.1. DESCRIPTION
The foot rolls are attached to the mould bottom flange. Their purpose is to
support the solidifying shell of the bloom as it leaves the mould, so that the risk of
breakouts is minimised.
In addition, the foot rolls keep the bloom in the centre of the mould.
These two actions contribute to reduce the wear of the mould plates in the lower
part of the mould.
3.2. SETTING
The foot rolls must be accurately aligned with reference to the actual dimensions
of the mould (at its bottom end).
An alignment template is provided for this purpose. It gives the possibility to
align the rolls with the mould pass-line.
Foot rolls alignment is performed with the mould and the template placed on the
mould alignment stand.
The position of the foot rolls compared to the strand can be changed by acting on
two alignment bolts for each roll.
Generally the foot rolls are aligned flushed with the mould exit, i.e. they are
placed on the theoretical prolongation of the mould faces. Alignment starts from
the outer radius, where the foot rolls are aligned on the machine radius (16500
mm.)
The reference surface of the template in the foot rolls area is 0.5 mm inside the
pass-line. Intermediate settings from 0 to -0.5 mm (for each side) can be
obtained by inserting a feeler gauge between the template and the roll.
The following instructions must be followed for foot rolls alignment:
Feeler Gauge
Foot Roll
4. DRAWINGS
H H
CASTING
DIRECTION
C/L RADIUS
G G
F F
600
600
E E
D D
360
R9834.8
C C
R10000
0.5 0.5 0.5
R9999.5
0.5 R9835.3
(164.2)
THIS DRAWING AND ALL INFORMATION THERE ON IS THE PROPERTY OF CONCAST AND IS CONFIDENTIAL AND MUST NOT BE MADE PUBLIC OR COPIED
(165.2) UNLESS AUTHORISED BY CONCAST AND IS SUBJECT TO RETURN UPON DEMAND.
ALL RIGHTS RESERVED COPYRIGHT AS PER DRAWN DATE SHOWN IN DRAWING HEADER.
Weight
0.5 162.2 0.5 Standard Workshop
ISO 128
Section Main Scale Format
Instructions 9800.4 115.912 7,08 KG 1 : 2,5 A1
Replaced by
163.2
Approved
18.04.2013
18.04.2013
C603
C603
10'043'539 -
A A
Sheet: 1 of 1
Material No.
2 1
12 2
F 5 F
A-A ( 1 :2 )
9
15 7
6 4
1
12
30
1
2 3
55
E E
B
D-D ( 1 : 2 )
B-B ( 1 : 2 ) 30.9
1
18
B 30
47
9
30
227.4
43 43
15
3
1
4
7 8
775
8
798.5
2
6 8 4 5
11
10
3 4 3 Pin 15x45 1.4301 / X5CrNi18-10 0.062 KG 433834 10015039
3 1 Threaded Rod - 0,418 KG 544677 10043608
2 1 Template-Parallel Side Left - 1,36 KG 544682 10043544
1 1 Template-Parallel Side Right 12x60x775 3.2315 / ALMgSi1 (EN AW-6082) 1,07 KG 544681 10043545
Item Qty Description Dimension Basic Material Weight Ut. MM-No. DRW-No. Norm/Remark
C Replaced by
50
Template Assembly Released
Approved
18.04.2013
18.04.2013
C603
C603
1 2 1 2
F 12 5 F
A-A ( 1 : 2 )
6 7
12
30
8
1
1 3
11
E 7 D-D ( 1 : 2 ) E
46.8
B B-B ( 1 : 2 ) 30.9
47
18 30
30
60
8
B 15
11
15.5
3
15
233.9
42 42 6
11
775 8 4
801.21 10
3
6 1 Clevis 30x30x83.5 3.2315 / ALMgSi1 (EN AW-6082) 0.095 KG 433870 10015043
5 1 Pin 18x50 CC764S / CuZn34Mn3Al2Fe1-C 0.098 KG 433836 10015041
R9999.5
361.36
10
3 1 Threaded Rod - 0,418 KG 544677 10043608
2 1 Template-Loose Side 12X82.9X775 3.2315 / ALMgSi1 (EN AW-6082) 1,24 KG 544669 10043542
-
12 10 1 1 Template-Fixed Side
Item Qty Description Dimension Basic Material
1,33 KG 544667
Weight Ut. MM-No.
10043541
DRW-No. Norm/Remark
Approved
18.04.2013
18.04.2013
C603
C603
544678
8 7 6 5 4 3 2 1
EKI Old File Name: File Name: 10043540_DRF_000.idw
CHAPTER 4
CASTING PARAMETERS
TABLE OF CONTENTS
Family. A set of grades within a group with exactly the same casting
parameters (cooling, mould level, mould powder etc) and event handling.
Effectively all steel grades in a family can be cast in exactly the same way.
A Group is denoted by a letter from A to Z, and a family by the group letter and a
number from 01 to 99.
A casting recipe is allocated to each family and all steel grades in the family are
cast using this same recipe.
A casting recipe is a full set of parameters (machine set-points) needed to cast
the family with optimum metallurgical results.
To simplify data entry recipes or parts of recipes can be inherited.
This is explained in detail later in this module.
1.2.1 GROUPS
The table below lists the steel groups according to CONCAST subdivision.
Within each group, the families are allocated mainly based on the carbon content
(rows of the following tables).
This table can also be used as a template to attribute any new steel grade to a its
family.
This method of organisation is designed to simplify the allocation of new steel
grades into existing families, avoiding the need to create new casting parameters
and eliminating the risk of loosing control over the structure of the recipes
actually used in the plant.
The system is not rigid and the database structure will allow expansion of the
classification or to increase the number of families or even sub-families as
desired. Therefore, the database can adapt to different customer’s needs and
does not limit customer’s freedom to classify steel grades according to internal
uses.
< 0.09 0.10-0.17 0.18-0.25 0.26-0.42 0.43-0.59 0.6-0.69 0.70-0.79 0.80-0.94 > 0.94
Mn/S<28 B15 B25 B35 B45 B55 B65 B75 B85 B95
C Rimming steel
C10 - - - - - -
substitutes
Mn/S≥28 D10 D20 D30 D40 D50 D60 D70 D80 D90
Al-killed special steels,
D not alloyed or with total Boron - D22 D32 D42 - - -
alloy content ≤ 2.5 wt%
Mn/S<28 D15 D25 D35 D45 D55 D65 D75 D85 D95
Al-killed and Si-killed Mn/S≥28 E10 E20 E30 E40 E50 E60 E70 E80 E90
E alloyed steels with total
alloy content > 2.5 wt% Mn/S<28 E15 E25 E35 E45 R55 E65 E75 E85 E95
%C x 90.4 %C x 65
%Si x 8 %Si x 8
%Mn x 5 %Mn x 5
%P x 34 %P x 34
%S x 40 %S x 40
%Sn x 10 %Sn x 10
%As x 14 %As x 14
%Ni x 4 %Ni x 4
%Nb x 7 %Nb x 7
%V x 2 %V x 2
%B x 60 %B x 60
%Mo x 2 %Mo x 2
%Ti x 17 %Ti x 17
%W x 1 %W x 1
Grade C Mn Si P S Cr Ni Mo
A 0.15 .47 .19 .025 .020 .10
B .84 .55 .22 .020 .025 .10 .10 .05
Reduction of liquidus temperature (°C) for grade A due to the presence of:
Reduction of liquidus temperature (°C) for grade B due to the presence of:
The actual steel temperatures required in the ladle and the tundish will be finally
established on site by the CONCAST engineer responsible for hot
commissioning. This provision is taken to allow for the prevailing on-site
conditions and actual analysis.
The following is given as a guide to give an understanding of the principles
behind the selection of tundish temperatures. However the final tundish
temperatures will not deviate substantially from those mentioned.
The steel temperature in the tundish can be, according to specification, in the
range of approximately 15 - 60 °C above liquidus. The effect of casting conditions
such as section size and distribution, tundish to mould teeming technique and the
steel grade will influence the optimum tundish steel temperature for a particular
grade of steel.
Operating at higher temperatures than necessary to compensate for poor
operating technique is not only bad "castmanship" but can be dangerous. From
most aspects, high superheat in the mould is deleterious to billet quality.
One exception to this basic principle occurs when low carbon steels are cast.
Due to the solidification behaviour of this steel it is necessary to cast with a high
temperature in the tundish to ensure fluidity of the steel into the mould. This is
even more necessary when casting Aluminium killed steels where nozzle
clogging may be an issue.
From the safety viewpoint, a serious emergency such as a total power failure will
require that the steel flow from tundish to mould is promptly terminated. In open
casting this operation proceeds far more comfortably and safely with "on-spec."
steel temperatures.
Exceeding the upper limit increases the potential for breakouts exponentially.
Poor casting machine condition is accentuated by high superheat due to the
hotter and thus weaker steel shell emerging from the mould. Slight imperfections
in mould geometry, as a result of use, will cause defects in the cast strand at high
superheats. These defects may be absent or insignificant at specification
temperatures, but coupled with a hot weak shell, they may become breakout
initiators. Non-perfect alignment between the mould and the foot rolls, or a less
than optimum mould oscillation characteristic - which would otherwise pass
unnoticed, may break a weak, sensitive strand shell.
The difference between the temperature of the liquid steel in the tundish and the
liquidus temperature is called “tundish superheat” or simply “superheat”.
The optimum value of superheat is a function of steel composition, casting mode
and operational considerations.
Reducing casting speed can to some extent compensate the effects of high
superheat. In the same way, one can increase casting speed to compensate for
low superheat.
This is especially important because both superheat and casting speed concur to
determine the length of the liquid pool and therefore the optimal position of the
soft reduction.
The dynamic spray cooling and the dynamic control of MSR can compensate the
effect of superheat and speed changes but the best practice is to keep these two
parameters as constant as possible.
The induction heating system in the tundish has the function to keep superheat
constant when the conditions of the steel arriving from the ladle vary.
Carbon Content < 0.09 0.10-0.17 0.18-0.25 0.26-0.42 0.43-0.59 0.60-0.69 0.70-0.79 0.80-0.94 > 0.94
A10 A20 A30 A40 A50 A60 B70 B80 B90
A Structural steels, C-Mn-Si 40 40 35 35 35 30 25 25 25
B10 B20 B30 B40 B50 B60 B70 B80 B90
Mn/S≥ 28
35 30 30 30 25 25 25 25 25
Special Si-killed Mn/S≥28 B62 B72
B
carbon steels Special uses 25 25
B15 B25 B35 B40 B55 B65 B75 B85 B95
Mn/S<28
35 30 30 30 25 25 25 25 25
D10 D20 D30 D40 D50 D60 D70 D80 D90
Mn/S≥ 28
Al-killed special 35 35 30 30 25 25 25 25 25
steels, not alloyed or D22 D32 D42 D52 D62
D Boron
with total alloy content 35 30 30 25 25
≤ 2.5 wt%
D25 D35 D45 D55 D65
Mn/S<28 35 30 30 25 25
The caster should always operate at the indicated casting speed, which constitutes the optimum value for each steel grade.
Too high casting speed results in:
- Face bulging that may exceed tolerances
- Increased degree of centre porosity and segregation
Too low casting speed results in:
- Rougher surface and increased frequency of bleeds
0.10-
Carbon Content < 0.09 0.18-0.25 0.26-0.42 0.43-0.59 0.60-0.69 0.70-0.79 0.80-0.94
0.17
A10 A20 A30 A40 A50 A60 A70 A80
A Structural steels, C-Mn-Si 3.4 3.4 3.4
B10 B20 B30 B40 B50 B60 B70 B80
Mn/S≥ 28 3.0 3.0 3.0
Special Si-killed Mn/S≥28 B12 B22 B32 B42 B52 B62 B72 B82
B 2.5 2.5 2.4
carbon steels Special
B15 B25 B35 B40 B50 B60 B70 B80
Mn/S<28 3.0 3.0 3.0
D10 D20 D30 D40 D50 D60 D70 D80
Mn/S≥ 28
Al-killed special 3.0 3.0 2.9 2.8 2.8 2.7 2.7 2.6
steels, not alloyed or D12 D22 D32 D42 D52 D62
D Boron
with total alloy 2.8 2.7 2.6 2.5 2.5 2.5 2.4
content ≤ 2.5 wt% D15 D25 D35 D45 D55 D65 D75 D85
Mn/S<28 2.8 2.8 2.7 2.6 2.5 2.5 2.5 2.4
The liquid steel in the tundish must be covered with insulating powder to protect it
from reoxidation.
The recommended powder types, based on MgO and suitable for all the steel
grades of the production mix are:
5. MOULD COOLING
Section 160x160
Section 160x160
Submerged Open
Section
Casting Casting
Casting Speed Aim (m/min) 2.5-3.0 3.0-3.6
Quadratic Frequency Factor – n f - -
Linear Frequency Factor – m f 55 65
Constant Frequency Factor – c f - -
Frequency Cut Off – C fo 60 60
Frequency 165-198 163-195
Quadratic Stroke Factor – n h - -
Linear Stroke Factor – m h - -
Constant Stroke Factor – c h 12 11
Stoke Cut Off – C ho 2 2
Negative Strip Time (secs) 0.10-0.12 0.11-0.13
Negative Strip % -32 -43
Note: the oscillation parameters are calculated over a realistic range of casting
speed around the aim speed value.
This design provides flexibility of operation by maintaining optimum oscillation
parameters when casting speed is changed for any reason (unless the change is
too large).
The initial oscillation waveform will be of the sinusoidal type. Mould acceleration
will be kept below 3 m/s/s.
Carbon Content < 0.09 0.10-0.17 0.18-0.25 0.26-0.42 0.43-0.59 0.60-0.69 0.70-0.79 0.80-0.94
D10 D20 D30 D40 D50 D60 D70 D80
*** SPH-C411- SPH- SPH-C411- SPH- SPH- SPH- SPH- SPH-
Al-killed special steels, not alloyed or with 81/E C176/ALS 9 81/E C189/E 1 C189/E 1 C189/V3 C189/V3 C189/V3
D
total alloy content ≤ 2.5 wt% D22 D32 D42 D52 D62
Boron SPH- SPH-C411- SPH- SPH- SPH-
C176/ALS 9 81/E C189/E 1 C189/E 1 C189/V3
The generic cooling curve are named: 150Axxx Where 150 stands for the section
size and “xxx” is the value of the specific water volume applied; for example:
160A140 the specific water volume is 1.40 l/kg
Parameter values for each zone (M, C, C.0.) are given in the following tables; the
picture below shows their meanings:
Q M VC C
Where:
Q = Flow rate (l/min)
M = Gradient / proportional factor
C = offset (l/min) (C is usually set to 0)
Vc = Casting speed (m/min)
C.O. = cut-off (minimum water flow rate admitted in l/min)
In next tables list of the “M, C, C.o.” coefficients values are given for the foreseen
specific water volumes.
IVACO Chapter 4
C.4619/401 Page 17
9.1 CURVE PARAMETERS
160A15 79 163 41 18
160A16 84 174 44 19
160A17 90 185 47 13
16022 167 201 52 26
16023 175 210 54 27
243 213
16024 182 219 56 28
16025 190 228 59 29
IVACO Chapter 4
C.4619/401 Page 18
9.2 Selection of spray cooling curves for all steel families
Pressures and Force for Withdrawal / Straightening Unit and Auxiliary Withdrawal Unit
10.1 160X160
Auxiliary Pinch
Withdrawal Roll Straighten roll
roll
Mode
P F P F P F
(bar) (kN) (bar) (kN) (bar) (kN)
1 130 180 - - - -
2 18 31 100 140 - -
3 18 31 20 32 - -
4 15 27 17 28 40 28
IVACO Chapter 4
C.4619/401 Page 20
11. TUNDISH METERING NOZZLE SIZES
IVACO Chapter 4
C.4619/401 Page 22
TECHNICAL DATA SHEET Accutherm ST-SP/511-C
Preliminary Product Description: Granular
3
F 4.58 3.28 5.88 Bulk Density (Kg/dm ) 0.87
Note: The range values listed above are tested and Calculated Break Point (deg. C) 922
controlled as required by our quality control
Note: The items listed above are typical values
system. These values are certified by
determined during our development process.
Stollberg Inc.
The data presented in this document is in accordance with the present state of our knowledge. We reserve the right
to modify product specifications within the scope of technical progress, new developments and policies of
continuous improvement.
3
F 2.59 1.59 3.59 Bulk Density (Kg/dm ) 0.82
Note: The range values listed above are tested and Calculated Break Point (deg. C) 946
controlled as required by our quality control
Note: The items listed above are typical values
system. These values are certified by
determined during our development process.
Stollberg Inc.
The data presented in this document is in accordance with the present state of our knowledge. We reserve the right
to modify product specifications within the scope of technical progress, new developments and policies of
continuous improvement.
3
F 4.00 3.00 5.00 Bulk Density (Kg/dm ) 0.90
Note: The range values listed above are tested and Calculated Break Point (deg. C) 1026
controlled as required by our quality control
Note: The items listed above are typical values
system. These values are certified by
determined during our development process.
Stollberg Inc.
The data presented in this document is in accordance with the present state of our knowledge. We reserve the right
to modify product specifications within the scope of technical progress, new developments and policies of
continuous improvement.
3
F 5.76 4.46 7.06 Bulk Density (Kg/dm ) 0.80
Note: The range values listed above are tested and Calculated Break Point (deg. C) 1028
controlled as required by our quality control
Note: The items listed above are typical values
system. These values are certified by
determined during our development process.
Stollberg Inc.
The data presented in this document is in accordance with the present state of our knowledge. We reserve the right
to modify product specifications within the scope of technical progress, new developments and policies of
continuous improvement.
3
F 4.70 3.70 5.70 Bulk Density (Kg/dm ) 0.75
Note: The range values listed above are tested and Calculated Break Point (deg. C) 990
controlled as required by our quality control
Note: The items listed above are typical values
system. These values are certified by
determined during our development process.
Stollberg Inc.
The data presented in this document is in accordance with the present state of our knowledge. We reserve the right
to modify product specifications within the scope of technical progress, new developments and policies of
continuous improvement.
3
F 2.70 2.20 3.20 Bulk Density (Kg/dm ) 0.74
The data presented in this document is in accordance with the present state of our knowledge. We reserve the right
to modify product specifications within the scope of technical progress, new developments and policies of continuous
improvement.
GUIDELINES FOR
QUALITY EVALUATION
1 Introduction 3
Rhomboidity 7
Bulging 8
Corner Depression 9
Macro inclusions 21
Sub-surface cracks (off corners) 22
Diagonal cracks 23
Halfway cracks 24
Center cracks 25
Segregation 26
V-type center segregation 27
Ghost Lines 28
Hair Cracks 29
The purpose of this chapter is to list the criteria for quality evaluation of the
blooms cast.
The object of routine inspection and quality control is:
The inspection of blooms to detect defects is done taking different kind of sample
depending on the information requested. This in turn depends on what the end
product will be and how confident the customer is in their process control.
It is not often necessary to do a full inspection of the cast product. A random
check provides all the required information.
The number and type of samples taken for different grades is commonly referred
to as a sampling plan.
These sampling modalities, together with causes and corrective actions required
for the elimination of various defects will be described.
Heat specific (which are related to the properties of the liquid steel and
normally caused by problems with superheat, trace element control,
deoxidation practice during secondary metallurgy).
Transverse cross section slice can be inspected immediately after cutting, (still in
rough machined condition, indicated by A1) for dimensional accuracy.
A Sulphur-print (condition A2) or a chemical macroetching (condition A3) can be
performed on the slice after grinding for assessment of internal defects.
Transverse Rough machined section Check for cross section shape and
slice (A1) (saw cut / milling) dimensional accuracy
Entire surface Test scarfing 2mm deep Subsurface slag entrapment. Pinhole
bloom (B2) porosity
Longitudinal section Longitudinal cut and S- Segregation, pipe (for higher C grades
(300mm) (C1) printed subject to possible bridging)
The most common of these samples are described in detail below along with the
defects that may be seen.
IMPORTANT: Routine samples should be taken from blooms cast under normal
conditions i.e. exclude blooms from the beginning and end of a cast. Of course if
an unforeseen event occurs.
Shape defects can be observed on transverse slice cut from a bloom, which
should be taken at least 150 mm away from any torch cut.
The slice in this condition is used to assess the following parameters:
A
B
W1
D1 D2
X1 X2
W2
2 D1 D 2
R hom boidty % 100 Where D1 = long diagonal
D1 D2
(W – X) = Degree of bulging in mm
Primary High casting Speed – leads to a thinner shell on exit from the mould.
Cause The shell is not strong enough to resist the ferrostatic forces above it and
is distorted and may even breakout. Secondary causes may increase this
effect. As section size increases the ferrostatic pressure increases and
bulging tendency will increase. This is normally a strand specific defect.
Secondary Badly adjusted foot rolls or containment rolls – will allow the strand to
Cause (1) bulge on exit from the mould or along the segments. They must always
be set correctly to provide the correct amount of support for the strand
shell
Secondary Worn mould – will allow bulging to occur in the worn section of the mould
Cause (2) especially if the casting speed is high.
Other Steel Chemistry – will affect the strength of the solidifying shell. The
Contributing presence of Cu, Sn and S will all weaken the shell and allow distortion to
Factors occur more easily.
Severity of The normal bloom dimensional tolerance is 1.5 %.
Bulging Deviations larger than 3 % could cause possibly problems in a pushes-
type reheat furnace, while are not relevant in case of walking beam
furnaces.
Corrective Reduce the casting speed. Reset the foot rolls correctly. Change the
Actions mould if worn.. Ensure Mn:S ratio > 28:1. Cu,Sn < 0.25
Surface defects (or External defects) are found by inspection of the entire bloom
surface removing any scale with a sand blaster (condition B1 and B2).
Local areas can be cleaned using a wire brush.
Surface defects that can be seen are described below.
Note: even if the following description is dealing with square cross section,
features, causes and corrective actions related to surface defects are also valid
for round cross section.
Primary Worn mould – These cracks are formed in the mould and often due to a
Cause worn profile in the corner either knicked or key-holed. This causes a
thinner shell to form and allows reheating lower in the mould. This
reduces the strength of the corner allowing a crack to form.
Secondary Bad secondary nozzle alignment – in case of bad spray jet alignment of
Cause (1) upper zones a rhombic-wise shell contraction can generate a longitudinal
corner crack.
Secondary Variable heat transfer – can allow reheating and crack formation. Mould
Cause (2) powder lubrication however normally reduces the chances of this
happening.
Secondary Superheat – has a strong effect on cracking. A hot shell has less
Cause (3) strength to resist thermal stresses set-up in the mould.
Other Carbon content – influences the occurrence of cracks. Cracks are more
Contributing likely above 0.15 C and approach a maximum at 0.40 wt% C. Cu, Sn and
Factors S all weaken the shell and increase crack probability.
Corrective Change the mould if worn. Change mould powder to reduce heat
Actions transfer. Decrease superheat to minimum possible. Check the alignment
of secondary sprays
Primary Worn mould – in the meniscus area in particular will cause the marks to
Cause look smeared in the middle of the face. High tensile stresses can lead to
a breakout.
Secondary Wrong mould lubrication – in case of wrong powder viscosity selection
Cause (1) sticking between newly formed shell and mould wall can take place
Secondary Severe taper – If the taper is too strong for the steel grade deformed
Cause (2) oscillation marks will result. This is accompanied with a high tensile
stress that can pull the bloom shell apart.
Secondary Casting Speed – If the casting speed is too slow the taper shall become
Cause (3) excessive and will generate a lot o stress in the shell as it moves into the
lower part of the mould.
Other If the mould life is low but meniscus area is deformed check the water
Contributing side of the mould in case the water hardness has risen and deposited an
Factors insulating layer of lime scale on the copper;
Scarce lubrication in the mould or mould powder incorrect;
Oscillation parameters incorrect.
Corrective Change the mould if worn.
Actions Cast at the correct speed for section and steel grade.
Improve the mould lubrication.
Check the oscillation parameters (frequency and stroke).
Primary Steel Chemistry – high levels of P, S and other tramp elements can
Cause greatly weaken the shell and in combination with a mechanical stress
cause the cracks to form, normally in oscillation marks.
High amount of Al, Nb and V which decrease the hot ductility in the
temperature range of 600-900°C.
Secondary Mechanical stress – Any mechanical stress coupled with poor chemistry
Cause (1) may cause cracks. Severe mould taper, worn oscillator bearings or a
badly aligned machine can cause stresses. Also poor lubrication alone
can cause enough stress to generate cracks
Secondary Unbending – stresses can be high enough to generate cracks especially
Cause (2) if the grade is crack sensitive and the corner temperature is lower than
900°. The cracks will appear on the top side of the bloom.
Other A severe mould taper or slow casting speed will generate stress. Casting
Contributing parameters that give positive strip will generate stress and negative strip
Factors must always be used.
Corrective Reduce residuals, eliminate mechanical stress, increase straightening
Actions temperature, have negative strip and a short stroke, use low viscosity
lubricant.
Primary Defective mould – This defect is a small breakout that has occurred in
Cause the mould and then solidified again. That is why the teardrops have a
flattened appearance. The breakout is normally caused by another
defect i.e. subsurface crack etc.
Secondary Surface Slag – Slag from the meniscus area can be trapped in the
Cause (1) solidifying shell and on exit from the mould be pushed out of the shell but
ferrostatic pressure. The steel that follows is quenched by the spray
water and leaves a bleed. The slag is normally alumina or solid
manganese silicates.
Secondary Scarce lubrication - mould powder incorrect.
Cause (2)
Other This problem is either a faulty mould or poor chemistry control of the
Contributing steel. Reoxidation in the ladle, tundish or mould can create solid
Factors inclusions if the chemistry is sensitive to this.
Wrong oscillation parameters.
Corrective Change the mould. Adjust the steel chemistry to avoid solid inclusions.
Actions Prevent reoxidation of steel in the tundish and mould.
Macro inclusions
Sub-surface cracks (off corners)
Diagonal cracks
Halfway cracks
Center cracks
Segregation
Piping and Bridging
V-type center segregation
Ghost lines
Haircracks
Note: even if the following description is dealing with square cross section,
features, causes and corrective actions related to internal defects are also valid
for round cross section.
Primary Secondary cooling – is the main reason for these cracks. The change
Cause in cooling intensity between spray zones allows reheating which
generates stresses in the bloom. The solid shell cracks at the solid liquid
interface. The depth of the crack determines how far down the machine
the stress was first developed.
Table of contents
1. INTRODUCTION 3
2. COLD COMMISSIONING & INTEGRATED TESTS 3
3. PERFORMANCE GUARANTEE TESTS 4
4. ANNEXES 4
The objective of this phase is to initially test that all the units of the Caster are
functioning correctly as individual units, it is important that activities during this
phase are coordinated to ensure that all utilities necessary to operate that unit
are available and other outstanding erection activities to not interfere with these
test activities.
To assist Concast personnel and to aid training it is recommended that Control
Room Operators assist in these activities to both familiarise themselves with the
machine movements and controlling them from the HMI and Local Control boxes.
The Integrated Test Phase is a precursor to the first cast and the start of the Hot
Test Phase. During the Integrated Test the operation of individual units of the
machine will be consolidated until the machine functions faultlessly as one
integrated unit.
In the later stages of Integrated Tests the Casting Operators are introduced to
the machine, and Operator training begins. The objective of the Operator training
will be for them to successfully operate (with assistance from Concast) the
Casting Machine for the First Cast without causing damage to the equipment or
injury to personnel. The minimum requirement for the end of the integrated test
phase is to conduct 3 casting simulations during which both machine and
operators function faultlessly.
During Integrated tests it is essential that the all Commissioning Check Lists are
completed and any deficiencies are recorded, all equipment and materials should
be present and correct, and all vulnerable areas of the machine are protected
from liquid metal and heat damage Annex 3.
To monitor the performance of the initial start up phase a Start Up Curve as
should in Annex 4 should be developed during the project liaison meetings to
which actual data can be added during the Hot Test phase.
4. ANNEXES
3) Spray Chamber
Start Up Curve
100
Cummulative Production
140 1
90
140000
Section160sq
0.9
Total Heats
120 80
Percentage of Nominal
Weekly Production 120000 0.8
70
100
0.7
100000
Planned
Percentage of Nominal Ouput
60
Cummulative
Tonnes
0.6
80
Actual
Heats
50 80 000
Cummulative
Tonnes
Tonnes
Heats
0.5
Planned
Cummulative Heats
60 40
60 000 0.4
Actual
Cummulative Heats
30
0.3
40
40 000
20
0.2
20
20 000
10 0.1
0 0 0 0
Day 1
Day 2
Day 3
Day 4
Day 5
Day 6
Day 7
Week 2
Week 3
Week 4
Week 5
Week 6
Week 7
Week 8
Week 9
Week 10
Week 11
Week 12
1 2 3 4 5 6 7 8 9 10 11 12
Week
Customer Concast
Representative Representative
CHECKLIST_001.doc Page 1
LADLE TURRET OPERATION FD111, 112
Safety
• Check clearance of handrails etc, and possible danger areas for operators.
• Check horn sound during all rotations (Auto, Manual and Emergency).
CHECKLIST_001.doc Page 2
LADLE WEIGHING SYSTEM FD114
Ccustomer Concast
Representative Representative
CHECKLIST_002.doc Page 1
TUNDISH PREHEAT STATION FD 152
Customer Concast
Representative Representative
CHECKLIST_003.doc Page 1
TUNDISH CAR FD 131, 132
Customer Concast
Representative Representative
Emergency Operation
• Check the emergency operation from the Emergency pushbutton.
• Check the position in which the tundish car stops.
• With emergency slidegate cylinders attached and in Submerged casting
mode, check the cylinders actuate when the tundish Emergency button is
pressed.
CHECKLIST_005.doc Page 1
CASTING FLOOR GENERAL
Customer Concast
Representative Representative
CHECKLIST_008.doc Page 1
MOULD LEVEL CONTROL FD233
CHECKLIST_011.doc Page 1
MOULD OIL SYSTEM FD213
Customer Concast
Representative Representative
CHECKLIST_012.doc Page 1
CASTING FLOOR GENERAL
Customer Concast
Representative Representative
CHECKLIST_008.doc Page 1
MOULD COOLING WATER AND EMERGENCY SYSTEM FD511, 514
Customer Concast
Representative Representative
CHECKLIST_014.doc Page 1
MOULD OSCILLATION FD211
Customer Concast
Representative Representative
CHECKLIST_015.doc Page 1
MEMS and FEMS FD271, 273
Customer Concast
Representative Representative
CHECKLIST_016.doc Page 1
DUMMY BAR FD291
Customer Concast
Representative Representative
CHECKLIST_017.doc Page 1
SPRAY COOLING FD512
Customer Concast
Representative Representative
CHECKLIST_019.doc Page 1
LEVEL 1 VDU
Navigation
• Be familiar with the basic layout of the Level 1 screens, and how to navigate.
• Practice changing parameters on some key screens, e.g .secondary cooling
page.
• Practice making trends.
Recipe system
• Understand how the casting parameters are stored in the recipe system and
how to change.
• Understand how the steel grades are stored in the families.
• Transfer the casting parameters to the PLC.
CHECKLIST_020.doc Page 1
LEVEL 2 SYSTEM
• Understand how the casting parameters are stored in the recipe system and
how to change.
• Understand how data is received from the steel shop ( e.g. next heat details)
• Understand how to look at casting data, and how to detect “out of limits” data.
• Understand how to produce reports
• Understand how to insert data, such as mould tube number.
CHECKLIST_021.doc Page 1
INTEGRATED TEST OF CASTING PREPARATION SEQUENCE (open casting without tundish)
CHECKLIST_022.doc Page 1
INTEGRATED TEST OF CASTING PREPARATION SEQUENCE (open casting without tundish)
CHECKLIST_022.doc Page 2
INTEGRATED TEST OF CASTING SEQUENCE (stopper casting with tundish)
C. S. Huachipato Concast
Representative Representative
CHECKLIST_024.doc Page 1
FULL INTEGRATED COLD TEST (OPEN CASTING)
Operators 2-4 • Insert wooden pin into the dummy bars using the local DBRCP
pendant
Operators 1-3 • Clean and pre-lubricate the moulds.
Pulpit • Insert dummy bars (automatic cycle) – MOP selector must be in
DUMMY BAR position – The dummy bar will stop below the mould
Operators 2-4 • Dry the dummy bar head (use torches), put the Conseal on, leave
cooling chamber and close the doors.
Operators 1-3 • Select PREPARE on MOP, insert the dummy bar into mould. Check
that the Conseal enters smoothly in the mould and is not torn or
CHECKLIST_025.doc Page 1
FULL INTEGRATED COLD TEST (OPEN CASTING)
damaged (in this case, replace Conseal and repeat). Use the
aligning tool to introduce the dummy bar into mould exactly at the
specified level. Leave MOP in PREPARE after completing this
operation.
Pulpit, foreman • Check READY TO CAST conditions on VDU
All • All operational personnel put on necessary protection clothes.
Foreman • Open radioactive sources
(Crane) • Place ladle onto ladle turret arm at loading position.
Operators 1-2-3 • Connect hydraulic cylinder and air to CNM as soon as the ladle has
left the LF (Foreman to give proper timing).
Foreman • Swing ladle into casting position (ladle arm must be UP)
• Operator 4 connects hydraulic cylinder to ladle slide gate
Operator 4
Ladleman • Ladleman helps with slide gate pendant
• Operator 4 reaches the casting floor immediately after this operation
Foreman • Gives the instruction to switch tundish preheater off
Operator 3 • Switch tundish preheater off and lift preheater arm
Operator 1 • Switch nozzle preheaters off
Foreman • Drive tundish to casting position
• Align tundish with moulds
Foreman
Operator 1 • Lower tundish
• Lower turret arm
Operators 2-3 • Put ladle shroud in position
• For each strand, perform following actions:
• Select CASTING on MOP
A strand, which has no ready to cast, does not
• CHECK THAT THE STRAND IS READY TO CAST (LIGHT
prevent casting on the other strands. For
STEADY ON – a blinking light gives NO ready to cast) – REPORT
safety reasons, the strand nozzle must be
Foreman to Foreman if the strand is not ready
plugged. Leave MOP on CASTING and leave
Operator 1 • Check that the level indicator (red bar) on MOP displays ZERO (= dummy bar in the mould.
radioactive source is open) The strand can be opened later if the problem
• Push CALIBRATE EMPTY button on MOP to calibrate the level has been solved.
control system
• Push the AUTO button of the mould level control (green light
CHECKLIST_025.doc Page 2
FULL INTEGRATED COLD TEST (OPEN CASTING)
flashes)
• Select OIL and AUTO (for the simulation, selector can remain in
MANUAL) – adjust oil potentiometer on the specified level
• Must check the correct execution of the procedure described under
Foreman the previous point, especially the ready to cast on all strands, then
give the order to open the ladle
Operator 4 • Position himself ready to lance open the ladle
Ladleman • Opens ladle
Operators 2-3-4 • Simulate oxygen lancing
Ladleman • Simulates quick filling of tundish.
Operators 2-4 • Add powder to tundish.
• Place themselves in front of the strands
Operators 1-2-
3-4 • Operators 1-2 are responsible for strands 1-2-3, operators 3-4 for the
strands 4-5
• After five minute (tundish fill) simulate opening with oxy-lance pipe as • Strand opening sequence: 2 and 4, then 1
follows: and 5, last 3
Operators 1-2- • Operator 1: opens Strand 2 and Operator 2 helps with burner (to • Foreman gives the order to open the strands
3-4 ignite oxylances) and keep ready to plug the nozzle if necessary • Foreman (or Concast during commissioning)
• Operator 3 opens Strand 4 approximately at the same moment and gives the order to plug a strand when
Operator4 keeps ready to plug the nozzle needed
(Concast) • Simulate filling of the mould using the source shutter, manual will be
required to control the speed.
Operators 1-2-
3-4 • Start remaining strands in sequence: 1 and 5, then 3.
Pulpit, Foreman • Check disconnection on all strands. Check parking of the dummy
bars.
Three operators are required on the casting
• One operator must observe disconnection and first cut of all strands. floor until the head cuts has been completed
Operators 1-2-3 The others are ready to plug and stop any strand if disconnection Later, 2 operators (or operator and foreman) on
fails. casting floor are enough
Operator 4 • Go downstairs, ready to help the ground floor operator with the torch
in case of missed cuts
CHECKLIST_025.doc Page 3
FULL INTEGRATED COLD TEST (OPEN CASTING)
CHECKLIST_025.doc Page 4
FULL INTEGRATED COLD TEST (OPEN CASTING)
• Bring back the tundish to casting position, start the strands again and
All simulate ladle and tundish removal in emergency. Memorise the
EMERGENCY CLEAR procedure and the escape routes from the
casting floor.
CHECKLIST_025.doc Page 5
MOULD PREPARATION AREA
Customer Concast
Representative Representative
CHECKLIST_026.doc Page 1
TUNDISH PREPARATION AREA
Customer Concast
Representative Representative
CHECKLIST_027.doc Page 1