C Fakepathlectures
C Fakepathlectures
2000-2010 Its entry into the fields of science and teaching as a new
scientific direction and subject.
2010-2020 Modern systems and vital necessity of Project
Management.
ISO-21500 STANDARDS:
This international standard provides important guidelines for
Project Management. These standards can be used by any public, private
and public organizations and in the management of any type of projects,
regardless of their complexity, size, duration. The standards provide a
high level of explanation of concepts and processes that form the most
efficient practice of Project Management.
This defines projects in the context of international standard
programs and project portfolios. However, detailed information on the
management of programs and project portfolios is not indicated here.
They are addressed because the subjects that belong to the general field
of management reflect only the management of projects.
2. Time limit
In the implementation of projects, it is possible to achieve the goal within
a certain time frame. One of the main parameters that distinguishes
projects from other events and objects is the time limit. As with the
beginning and end of every business, projects have begin (start) and end
(finish) times. These time indicators are usually limited. Therefore, one of
the main conditions for the successful completion of the project is its
implementation within the given time frame.
4. Resources
In addition to the budget in the implementation of projects,
other funds are used. This applies to resources: people, techniques,
equipment, materials and other resources. When planning a project,
each resource is tied to the work or task in the project, and, of
course, all resources are in a limited volume. Resources and their
volume are planned in advance, and on the basis of this, the project
implementation period is determined. One of the main issues for
the approval of the project is the compilation and approval of the
resource appropriation schedule. The correct implementation of
this plan-schedule serves the project purpose and the successful
completion of the project.
7. Legal provision
Legal support of all stakeholders participating in the project and the
establishment of legal relations between them is one of the main
conditions for the success of the project. In the new economic conditions,
the creation of a legal framework for the implementation of projects in a
dynamically changing political and economic environment is considered
one of the main issues. For this reason, all actions and decisions related to
the project in the project office should be based on the legal framework
and provided with relevant regulatory documents.
8. Organizational structure
As can be seen from the definitions, the project is a small
enterprise. Just as every enterprise has an organizational structure,
projects must have an organizational structure. In particular, the absolute
importance of the organizational structure is required in the
implementation of complex projects, and in projects of this type, one of
the main parameters is the “creation of organizational structures”.
Organizational structure may not be applied in small projects.
9. Framework standards
The project, like other objects, is closely related to the
environment. The exact limit and scope of each of the works performed
in the project should be determined. Therefore, projects must be covered
by frame standards both externally and internally. In general, projects are
implemented within any framework standards. The project should show
itself vividly by changing the environment in which it is being
implemented. The project should differ from other works in its unique
features. Since projects are closely related and related to the environment,
they can be viewed as a complete system that has a certain feature.
LECTURE 2
Projects are diverse in their nature. They differ from each other in
the subject area, scale, number of participants, degree of complexity and
other indicators. Thus, the classification of projects is as follows:
The environment in which the project is implemented and its main
field of activity determine the type of project. For example: technical
project, organizational project, economic project, Social Project, mixed
project, etc.
The subject area, structure and components of the project
determine the class of the project. Projects are divided into three classes:
- mono-project;
- multiproject;
- the mega-project.
A mono-project is a separate project that has its own type, scale
and structure. A multi-project is a complex of projects consisting of
several mono-projects. A mega-project is a targeted program or
development program that combines mono and multi projects.
The scale of the project is determined according to the number of
participants, their impact on the environment and their size.
By scale, projects are divided into:
- small projects;
- secondary projects;
- great projects;
- and giant projects.
By scope, projects are divided into the following types:
- the intergovernmental project;
- international project;
- national or general government project;
- regional or interregional project;
- the project on intersectoral and sectoral areas;
- corporate projects;
- inter-enterprise and intra-enterprise projects.
Economic factors:
- structure of the national economy;
- gross domestic product indicators;
- types of liability and property rights;
- tax and customs policy;
- insurance coverage;
- currency stability and inflation rate;
- development of the banking system;
- state investment fund and investment policy;
- development environment of entrepreneurship and economic
entities;
- development of the business environment: sales, investment,
production, raw materials and products, labor, etc;
- pricing policy.
Infrastructure factors:
- vehicles;
- Communication, Information Technology and telecommunication
facilities;
- power supply;
- utilities;
- purchase and sale and payment systems;
- material and technical equipment;
- industrial infrastructure;
- service areas.
ISO-21500 STANDARDS:
Project environment
General information
The project environment affects the project implementation process
and its successful completion. The project team must take into account
the following:
-socio-economic, geographical, political, legal, technological,
environmental and other external factors of the organization;
- internal factors such as competence and resource provision of the
organization in the field of strategic, technological, project management,
organizational culture and its management structure.
LECTURE 3
The purpose of the project. The parties with interest.
The conditions given to fulfill the project and the result achieved
are called the goal of the project.
One of the main issues when forming the project concept is to
determine the purpose of the project. In all projects, there is a set of goals
that characterize its structure, participants, parties of interest and the
environment, closely related to each other. To achieve these goals, the
selection of appropriate criteria is the main condition, and within the
framework of these criteria, alternative options are also used to achieve
the goal.
Thus, the goals of the projects are formed as follows:
- the purpose of the project should be clearly described;
- to achieve the goal, the results obtained must be evaluated;
- it should be possible to fulfill the project within the limits and
conditions.
In general, the project requires the purchase of a high-quality
product and the achievement of the goal within the framework of time,
budget, reserves and other restrictions.
The purpose of the projects is likely to change. The influence of the
environment on the project, the subject of unforeseen changes in
parameters in the process of its implementation and other extraneous
“exciting” influences can lead to a change in the purpose of the project.
Therefore, the goal of the project is characterized by a dynamically
changing environment. In this case, the current situation is analyzed and,
if required, appropriate adjustments are carried out.
Setting a project goal is a process that requires special skills and is
performed in the following sequence:
- the subject area, general approach, problems and ways to solve it
are determined;
- the direction of the goal is determined;
- in this area, the set of possible goals is formulated;
- the purpose of the project is determined.
The result of the project – determines the state of the subject area
depending on the type and nature of the project.
Project completion time -the project completion time is predicted
in advance, and the end date can be changed within certain restrictions.
However, in some cases, the completion date of the project is
necessarily set as a strict requirement, and changing the time is
considered as an unsuccessful completion of the project.
Costs - refers to the funds required for the full implementation of
the project. In some cases, the maximum limit of project costs is
indicated at the planning stage, in the event of costs above this limit,
project financing may be frozen.
The possibility of changing the goal – during the implementation
of the project, it may be necessary to make some changes to its purpose.
However, in order for the goal to be changed, the internal rules must be
approved and these rules must be known to the project team.
The set of goals and its structure – reflects the principle of
subordination and interconnection of tasks in the project and,
accordingly, their goals in groups when implementing projects.
If there are any risk elements in determining the objectives of the
project, then the following issues should be reflected in the concept of the
project:
- to agree with the parties by analyzing the product, result,
efficiency and environmental impact of the project;
- to form an additional set of comments and proposals on the
budget and duration of the project;
- to analyze, predict and agree with the parties the way to resolve
controversial issues that may arise between the outcome, duration and
budget of the project.
Extensive and detailed writing of the project concept facilitates the
process of its implementation and creates more favorable conditions for
it.
It should be borne in mind that the main idea and its purpose in the
project cannot and cannot be changed. In simple projects, all work can
also be performed by one person. And in complex projects, large-scale
works and tasks can be divided into small parts and these functions can
be assigned to other participants.
The chief ideologist and author of the project is its author and
initiator of the idea. One of the main parties that have a direct interest in
the successful implementation of the project and the achievement of the
result is its customer. The customer is considered the future owner of the
project and one of the parties benefiting from its results. The customer
determines the basic requirements and scale of the project, forms the
budget of the project at the expense of his own funds and investors, and
solves financial issues related to its implementation. The customer, as the
main executor of the project, signs contracts, conducts a division of
responsibilities and regulates relations by establishing communication
links between project participants. The customer is responsible to society
and the law for the project.
The graph of the “life path of the project”shown in Figure 1 is a classic and
more widespread form of description. Apparently, according to these standards, the
“idea” is not included in the life path of the project. Therefore, according to these
standards, the “idea” is not included in the costs of the project and funds are not
allocated for it, and therefore the mentioned stage is not reflected in the project budget
as a separate item. But according to some standards” idea " the life of the project
it is included in its path and, therefore, the life path of the project is made up of 5
(five) main stages: idea, concept, development, implementation and closure.
Resources
Idea Concept Development Execution Closure Time
Let's consider each of the 4 (four) phases that cover the life path of
the project separately:
1) Conception phase. In this phase, the concept of the project is
developed and its philosophy is disclosed. The concept of the project
includes:
- analysis of the mission of the project and similar projects,
collection of information about it;
- to change the situation and to confirm the need to change the
current situation;
- to determine the purpose, technical task and result of the project;
- determining the requirements, limitations, conditions and
criterion of the project;
- to identify risks in the project;
- to determine the environment and participants of the project;
- to determine the required time, resources, management methods.
4) Closing phase. During this period of the project, the final goal is
achieved, the result is achieved, conflicts are resolved, and the project is
closed. This phase is made up of the following works:
- planning and closing of the project completion process;
- testing of the final product of the project;
- personnel training for the newly created facility;
- transfer of the object to the customer, commissioning and
preparation of documents related to these works;
- finalization of the project and evaluation of the result;
- preparation of final documents;
- finalization and closure of work on the project;
- resolution of conflict issues;
- realization of unused resources;
- creation of a knowledge base about the project and its
implementation;
- the release of the command staff of the project.
LECTURE 5
The structure of the project.
Models and types of project structure.
LECTURE 6
Implementation of the structure of the project.
Project structures
Portfolio, program and project managers coordinate various
structures in the respective areas.
The portfolio (in many cases, sub-portfolios) includes various
types of projects and programs, costs, risks, profits, time constraints,
dimensions, strategic importance, innovations, territory efficiency, and
other parameters. The portfolio manager must be able to analyze the
portfolio data and submit them to the higher governing body by various
methods for their verification, decision-making. The joint Organization of
projects and programs included in the portfolio is carried out within the
framework of a single activity, and after the completion of the project, as
well as programs, they are sanctioned and removed from the portfolio.
Programs are small-scale portfolios, as well as consisting of
relevant projects and related work. Unlike a portfolio, programs are
executed within a limited time frame and provide relevant benefits.
Projects can be divided into components according to different
components, for example, such as the hierarchical structure of work,
project organization, project costs, data and the structure of documents.
Project structures are the main mechanism that serves to form
certain rules within the project. Hierarchical structures provide for the
interconnection of the components of the project and the establishment of
relationships between them on the basis of the principle of subordination.
Jobs they can be broken down according to tasks, small group of
tasks and directions of activity. According to these works and groups,
resources should be distributed, work should be planned, costs should be
estimated, work schedules should be drawn up, work should be assigned,
supervised and completed. A report on the works and actual costs must be
made, and then received by the management of Project, program and
portfolio managers.
The project organization represents the work of the organization,
which includes individual parts of the project and members of the project
(sub-project) team, that is, depending on the type of project, it provides
planning, financial issues, Infrastructure, Information and communication
technologies, research and development strategies, procurement and
supply procedures, solution of issues such as product and result
management. Each of the sub-projects (modules) has a project manager
or team members. In the event that the project manager or team members
do not have sufficient experience, they should be informed in more detail
about the structures of the project so that all aspects are covered.
The project is divided into different phases during the “crisis path",
reflecting intermediate final results, key decision-making stages (stopping
or continuing), investment decisions and other issues.
Costs are divided into internal and external costs in terms of the
time spent, non-discretionary and discretionary costs, capital costs in
comparison with income.
Information relating to the project can be divided into facts used in
the formation of decisions made, knowledge derived from data and
formed on the basis of data. If this knowledge is complex and
voluminous, a database of related information can be created and survey
and analysis tools can be used to conduct their research.
Documentation related to the project the documentation related to
the definition of the project, its management plan, meetings of various
types of team members, monitoring of the project, analysis of the
executors, the final results of the project, etc.such parameters must
comply with the standard forms. Also, documents must be reviewed,
stored in a physical and electronic archive with restricted access.