Feng Shun_Daily Report (07-12-2024)
Feng Shun_Daily Report (07-12-2024)
MH-E19 R6 ring excavation and concrete works has completed. Management Staff 4
Slum test and test cube has done on site. Project Director 1
Project manager 1
Phase 2 MH-E19
MH-E26 Hardcore backfill and levelling works in progress for access works. Project Engr 1
WSH Coordinator 1
Phase 2 MH-D17
C. Material Excavated
Hard soil Excavated cum
Cum
E. Comments
MH-E19 -R6 casting done
F. Name & Signature of RTO: Arunachalam & Natarajan