0% found this document useful (0 votes)
7 views

Feng Shun_Daily Report (07-12-2024)

Uploaded by

prasanth kuty
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views

Feng Shun_Daily Report (07-12-2024)

Uploaded by

prasanth kuty
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Weather:

Project Title: Fine a


(A) SITE CLEARANCE AND EARTHWORKS (PHASE II) AT ANG MO KIO N8 Rain r
(B) CONSTRUCTION OF ANG MO KIO STREET 81 (Part I), ANG MO KIO STREET 82 &
ANG MO KIO DRIVE (PRT I) (C)CONSTRUCTION OF TRUNK SEWERS (PART
I) AT ANG MO KIO N8

Proj. Ref.No.: E4480-00009-2023 Date: 12/7/2024


Company : Feng shun construction Pvt Ltd working Time : 8 am to 8 pm

Locations A. Activites Description / Particulars Manpower

MH-E19 R6 ring excavation and concrete works has completed. Management Staff 4
Slum test and test cube has done on site. Project Director 1
Project manager 1
Phase 2 MH-E19
MH-E26 Hardcore backfill and levelling works in progress for access works. Project Engr 1
WSH Coordinator 1

MH-D17 shaft base slab casting works had completed.

Phase 2 MH-D17

Power pack unit repairing works in progress Site Staff 34


Const.Manager 1
Site engineer 1
Site Supervisor 1
Phase 2 MH-D14 to MH-D15 MH-D17- Shaft base slab casting
WSH Coordinator 1
Machine Operator 2
Lifting Sup. 2 Picture
Rigger/signalman 3
TT-47B reistatement works has completed. Banksman 0
Jacking opt 1
TT-56 mark out the excavation area then start the excavation manually. welder 4
found 110 mm UPVC pipe 2 nos with LT PVC slab and star hub PVC slab, General Workers 2
Phase 2 TT-47B and TT 56
450mm x 450mm concrete with brick for sp telecom. Then backfill and reisntatement works has completed. Electrician 1
Subcon HLG 8
Subcone CUDS 7

Site Vehicle (with license


Excavator 6 Gen Set with pump 4 plate)
1
welding machine,4''
Concrete vibrator 2 cutting machine
1 shoring materials as required

Site Vehicle (without


ECM Plant 1 license plate)
0 Electrical breaker 1

Good Soil excavated 4 Load

C. Material Excavated
Hard soil Excavated cum

Cum

Consultant C&S (ECAS)


D. Visitor(s) at Site Consultant M&E (GIMS)
Client (HDB)

E. Comments
MH-E19 -R6 casting done
F. Name & Signature of RTO: Arunachalam & Natarajan

Note: This form serves as a guideline only

You might also like