00b. Introduction 1-5
00b. Introduction 1-5
1. INTRODUCTION
width is 5.4 m and having 1.0m width of soft shoulders. The provided existing carriageway
of the bridge is around 3.8m. That is not adequate. During rainy seasons the existing
Western Province. This proposed bridge belongs to Maho Executive Engineer’s division of
Introduction 1
Professional Review Examination - 2024(February/March)
1.2 Existing Bridge Details
Introduction 2
Professional Review Examination - 2024(February/March)
1.2.2 Structural Details of Existing Steel Bridge
• No of spans - 1m
• Skew angle - 0
• Substructure - Concrete
Even though this bridge is located in a B class road, the bridge access suddenly becomes
narrow making an environment for severe accidents. The road carriageway width is 5.4m
with 1.0m of soft shoulder. But, at the bridge it is reduced to 3.8m width for both vehicle
and pedestrian traffic, which creates bottle neck to the traffic flow at peak time. This road
Hence fully reconstruction of the bridge is required for this location considering public
Introduction 3
Professional Review Examination - 2024(February/March)
1.4.1 Superstructure
The designed bridge is consisted with 3.7m x 2 carriageway width and 1.2m x 2-foot walks.
It is a two-span bridge with 16.5m long beams. Considering the horizontal alignment, the
The bridge superstructure was designed as reinforced concrete with 16.5m long prestress
beam and the all-design calculations for bridge and beam conducted according to BS:5400:
The bore hole investigation has done for identify the soil, rock properties. That bore hole
investigation report shows subsurface soil condition, type of layers and thickness, SPT
values and property of rocks (RQD & UCS). In addition, report shows details of soil
Introduction 4
Professional Review Examination - 2024(February/March)
classifications for each soil layer according to results obtained from sieve analysis. By
considering the bore hole investigation report it is decided to lay both abutment bases and
pier base at 8.5m below the bridge finish level, with spread footing. Foundation for
abutments and wing walls bases, it was decided and designed reinforced concrete sections
for abutments and wing walls stem as an economical design. The allowable bearing
capacity of rock layer obtained from method was suggested by Joseph E Bowels with factor
Introduction 5